Building Work
Cost more than 30 Cr.
Building : Work in Progress
S. No.क्र. सं. Project Name A/A & E/S Date of Start
Completion
Expected
Expenditure
Progress
Remarks View
1 Construction of Hospital at Jwalapuri, New Delhi 319.65 Cr.
06/12/2019
F.8(A)/(7)/DGHS/HC/2019/CD#112557057/Js3hfw-4017-4034
07/08/2020
13/08/2022
31/08/2024
146.95 Cr. (Mar'24)
0.00 (Mar'24)
Structure RCC work & masonry work completed. Sanitary installation work completed, façade work, development work & electrical work is in progress. Detail Report
Graph / Photo
2 Setting up of 1912 bedded semi permanent/temporary ICU Hospital at GTB. 316.08 Cr.
08/09/2021
12/Misc/Covid-19/2021/CD-112647590 dated 08.09.2021
23/09/2021
22/02/2022
30/06/2024
0.00 Cr. (Jul'23)
82.00 % (Jul'23)
Work stopped due to non availability of funds. Detail Report
Graph / Photo
3 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 209.59 Cr.
27/11/2015
No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre)
25/01/2019
24/05/2019
30/09/2020
2.16 Cr. (Oct'21)
0.00 (Oct'21)
work in progress Detail Report
Graph / Photo
4 Construction of Mother & Child Block and Screening OPD Block at Dr. B.S.A. Hospital at Rohini, Sector-6, New Delhi 194.91 Cr.
09/05/2018
2(11)/pWD/-upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45 dt. 25.06.2018
06/03/2020
05/09/2021
31/08/2023
6.18 Cr. (Feb'24)
0.00 (Feb'24)
work in progress Detail Report
Graph / Photo
5 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 194.91 Cr.
25/06/2018
2(11)/PWD-Upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45
04/03/2020
03/09/2021
31/08/2024
56.39 Cr. (Mar'24)
0.00 (Mar'24)
work in progress Detail Report
Graph / Photo
6 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 117.78 Cr.
22/06/2018
5/171/SGMH/TCSUB/CT/2016 CD# 112388502/2510-2527
04/09/2019
03/03/2021
31/05/2024
8.60 Cr. (Mar'24)
0.00 (Mar'24)
work in progress. Detail Report
Graph / Photo
7 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) 101.63 Cr.

18/07/2021
17/07/2022
31/10/2023
6.06 Cr. (Oct'22)
2.00 % (Oct'22)

Work in progress.

Detail Report
Graph / Photo
8 Construction of 3 Nos. Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A-6, Paschim Vihar, Vasant Kunj and Ladpur Village, New Delhi (Package - 7). SH : Civil & Electrical work. 101.63 Cr.

18/07/2021
17/07/2022
31/07/2023
64.53 Cr. (Mar'24)
0.00 (Mar'24)

Work is in progress.

Detail Report
Graph / Photo
9 Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. 97.09 Cr.
08/02/2021
12/Misc/Covid-19/2021/CD-112647590 dated 08.09.2021
23/09/2021
22/02/2022
30/06/2024
0.00 Cr. (Jun'23)
88.00 % (Jun'23)
Work stopped due to non availability of funds. Detail Report
Graph / Photo
10 Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) 83.39 Cr.
26/03/2018
F/10/Estate/Renovation of staff rooms/951 schools/DoE/945-50
--
--
--

Detail Report
Graph / Photo
11 Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). 83.38 Cr.
26/03/2018
F.16/estate/renovation of staff rooms/951 Schools/DOE/945-50 dated 26.03.2018 for Rs. 83,38,36,800/-
11/02/2019
10/06/2019
10/06/2019
5.40 Cr. (Jul'22)
0.00 (Jul'22)
WORK IN PROGRESS Detail Report
Graph / Photo
12 Construction of New block Forensic Science Laboratory, Rohini, New Delhi 59.06 Cr.
13/08/2019
3(148)/FSL/2016-17/1717-29 dt. 13.03.2019
06/03/2020
05/09/2021
30/09/2023
0.00 Cr. (Aug'23)
96.00 % (Aug'23)
96% Detail Report
Graph / Photo
13 Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi. 51.20 Cr.
09/08/2019
14012/21/2019-UTP
--
--
--

Detail Report
Graph / Photo