Education Work
Last Updated on: 20/09/2017
Details of Education Works - Additional SPS Class Rooms (Progress)
S. No. Name of School No
of
Room
Agency Stipulated
DOS
Stipulated
DOC
Site Handed
Over on
Expected
Date of
Completion
Progress in % Remarks View
1 1607 Additional Classrooms in existing premises under jurisdiction EO Zone 25 & 29 of DDE South East (Priority-I) of 22 Govt. School Buildings. - Costing Rs. 221.44 Cr.
1.1 Madanpur Khadar Extn. J.J.Colony GGSSS 80 M/s Subham Builders 13/03/2016 25/07/2016 11/05/2016 31/07/2017 110.00 % COMPLETED Detail Report
1.2 GGSSS at Tuglakabad Extn 44 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.3 SBV at Tuglakabad Extn 44 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % COMPLETED Detail Report
1.4 New Friends Colony. 32 M/s Subham Builders 13/03/2016 25/07/2016 11/05/2016 30/06/2017 100.00 % completed Detail Report
1.5 Kalkaji, DDA Flats, Phase II, GGSS 112 M/s MIA Construction Pvt. Ltd. 04/03/2016 16/07/2016 05/04/2016 30/04/2017 100.00 % COMPLETED Detail Report
1.6 GGSSS, Harkesh Nagar 70 M/s Subham Builders 07/03/2016 25/07/2016 11/03/2016 15/03/2017 100.00 % completed Detail Report
1.7 SKV, Rani Jhansi 92 M/s Subham Builders 11/03/2016 25/07/2017 11/04/2016 31/03/2017 100.00 % completed Detail Report
1.8 GGSSS Tehkhand 56 M/s MIA Construction Pvt. Ltd. 03/03/2016 15/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.9 SKV, Tuglakabad Village 92 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 30/04/2017 100.00 % completed Detail Report
1.10 GGSSS No. 2 at Badarpur 118 M/s MIA Construction Pvt. Ltd. 05/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.11 GGSSS-3 Molarband 52 M/s Subham Builders 13/03/2016 25/07/2016 11/05/2016 31/03/2017 100.00 % completed Detail Report
1.12 GGSSS Jasola Village 24 M/s. Krishna Const Co 07/03/2016 19/07/2016 11/04/2016 15/03/2017 100.00 % completed Detail Report
1.13 SKV Hari Nagar Ashram 36 M/s. Krishna Const Co 07/03/2016 19/07/2016 11/05/2016 28/02/2017 100.00 % completed Detail Report
1.14 GGSSS,No.2 at Tuglakabad Railway Colony 56 M/s Shubham Builders 13/03/2016 25/07/2016 11/04/2016 31/03/2017 100.00 % completed Detail Report
1.15 KalkaJi No.2 36 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.16 Kalkaji No.3 60 M/s MIA Construction Pvt. Ltd. 03/03/2016 15/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.17 GGSSS No.1 at Badarpur 118 M/s MIA Construction Pvt. Ltd. 05/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.18 SKV Molarband 45 M/s Subham Builders 07/03/2016 19/07/2016 11/04/2016 30/04/2017 100.00 % completed Detail Report
1.19 GGSSS No.2 Molarband 20 M/s Subham Builders 07/03/2016 19/07/2016 11/04/2016 28/02/2017 100.00 % completed Detail Report
1.20 GGSSS No.2 Tuglakabad Extn 40 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 30/04/2017 100.00 % completed Detail Report
1.21 SKV, Aruna Ali,Tuglakabad Extn. 60 M/s MIA Construction Pvt. Ltd. 06/03/2016 18/07/2016 20/03/2016 31/03/2017 100.00 % completed Detail Report
1.22 GGSSS No.3 at Badarpur 104 M/s Subham Builders 07/03/2016 19/07/2016 11/04/2016 31/03/2017 100.00 % completed Detail Report
1.23 Jangpur-G (Co.ed)SS 52 M/s Subham Builders 07/03/2016 19/07/2016 11/05/2016 15/08/2017 98.00 % Work in Progress Detail Report
1.24 Madanpur Khadar, SKV 112 M/s. Purananand 24/03/2016 05/08/2016 05/04/2016 30/09/2017 92.00 % completed Detail Report
1.25 Hiring of inspection vehicle for Education Maintenance Division (South) and office of The Project Manager (Education) Maintenance, New Delhi M/s. Mahesh Chand 21/07/2017 20/02/2018 awarded Detail Report
2 Construction of additional SPS Class rooms in existing premises under Jurisdiction Zone-18 of District West-B (Priority-I) - Costing Rs. 92.98 Cr.
2.1 G Co-Ed F-Block Vikaspuri 52 M/s S. S. Total Construction Pvt. Ltd. 14/02/2016 27/06/2016 15/05/2016 31/03/2017 100.00 % Work completed & 52 rooms handed over. Detail Report
2.2 SKV A-Block Janakpuri 44 M/s. Varun Gupta & Co. 18/02/2016 01/07/2016 15/03/2016 31/03/2017 100.00 % Work Completed & 44 rooms handed over. Detail Report
2.3 SKV Matiala 16 Mr B. L. Infra Projects Pvt. Ltd. 16/03/2016 28/07/2016 31/12/2016 100.00 % Work completed & 16 rooms handed over. Detail Report
2.4 SKV Kakrola with MP Hall 100 M/s Satya Narain 06/03/2016 18/07/2016 15/04/2016 31/03/2017 100.00 % Work completed & 100 rooms and 1 MP Hall handed over. Detail Report
2.5 SKV, A Block Vikaspuri with 1 M.P. Hall 50 M/s S. S. Total Construction Pvt. Ltd. 14/02/2016 27/06/2016 15/05/2016 31/03/2017 100.00 % Work completed & 44 rooms and 1 MP Hall handed over. Detail Report
2.6 Govt. School Shiv Vihar 12 M/s Satish Builders 29/02/2016 12/07/2016 16/04/2016 31/01/2017 100.00 % Work completed & 12 rooms handed over. Detail Report
2.7 G Co-Ed. GGSSS Bindapur (Shifted to A Block Janakpuri School) 44 M/s. Varun Gupta & Co. 18/02/2016 01/07/2016 30/04/2017 100.00 % Work completed & 64 rooms handed over. Detail Report
2.8 Hastsal Village 32 Mr B. L. Infra Projects Pvt. Ltd. 16/03/2016 28/07/2016 31/03/2017 100.00 % Work completed & 32 rooms handed over. Detail Report
2.9 Construction additional SPS Class rooms in existing premises under Jurisdiction Zone-18 of District West-B (Priority-I) (SH:- C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc.) Mr SHANTI CONSTRUCTION COMPANY 29/12/2016 30/06/2017 30/06/2017 100.00 % work is in progress. Detail Report
2.10 SG(Co.Ed) Vidayalaya Posangipur with 1 M.P. Hall 64 M/s B. L. INFRA PROJECTS PRIVATE LIMITED 16/03/2016 28/07/2016 30/04/2017 70.00 % Work is in progress & 16 rooms handed over. Detail Report
2.11 Govt School, G-Block Vikaspuri with MP Hall 100 M/s Satish Builders 29/02/2016 12/07/2016 10/05/2016 15/01/2017 60.00 % Work is in progress & 52 rooms handed over. Detail Report
2.12 Providing services of Computer Operator at O/o EE(E) M-153N, ITI Campus, Pusa, New Delhi 26/10/2014 25/09/2015 07/12/2015 07/12/2015 Work Completed Detail Report
3 Construction of 625 Additional Classrooms under Jurisdiction of Zone 6 of DDE North East District (Priority-I) - Costing Rs. 91.28 Cr.
3.1 GSKV New Seemapuri 8 M/s S.P.S Infrabuild Pvt Ltd. 05/03/2016 17/07/2016 28/03/2016 05/12/2016 100.00 % Completed (8 Rooms completed) Detail Report
3.2 GGSSS Janta Flat Nand Nagari 65 M/s M/s S.P.G Infraprojects Pvt Ltd 27/03/2016 08/08/2016 28/03/2016 30/06/2017 100.00 % 64 Rooms completed (1 MP Hall to be completed by 30/09/2017 Detail Report
3.3 SKV (St. Eknath) J&K Block Dilshad Garden 48 M/s S.P.S Infrabuild Pvt Ltd. 05/03/2016 17/07/2016 05/03/2016 15/09/2017 99.00 % Work in Progress Detail Report
3.4 RRVSKV B-Block Nand Nagari 48 M/s S.P.S Infrabuild Pvt Ltd. 05/03/2016 17/07/2016 05/03/2016 30/09/2017 98.00 % Work in Progress Detail Report
3.5 Construction of 625 Additional Classrooms under Jurisdiction of Zone 6 of DDE North East District (Priority-I) (SH: SPS type Class Rooms, Labs & MP Halls i/c Internal & External Water supply, Sanitary and Electrical Installations,Development of site and fire fighting system etc.- at GGSSS Janta Flat Nand Nagari And SKV E- Block Nand Nagari,Delhi) Package-2 138 M/s M/s S.P.G Infraprojects Pvt Ltd 27/03/2016 08/08/2016 27/03/2016 30/09/2017 97.00 % Work in Progress Detail Report
3.6 SKV Mandoli 28 M/s. Reliance Elektrik works 27/02/2016 10/07/2016 29/02/2016 31/08/2017 96.00 % Work in Progress Detail Report
3.7 SKV DDA flats of Loni Road 40 M/s. Naresh Kumar Gupta & Co Pvt Ltd 05/03/2016 17/07/2016 05/03/2016 30/09/2017 96.00 % Work in Progress Detail Report
3.8 GGSSS Saboli 26 M/s. Reliance Elektrik works 27/02/2016 10/07/2016 29/02/2016 30/09/2017 96.00 % Work in Progress (14 Rooms Completed) Detail Report
3.9 GGSSS Mandoli Extn. 44 M/s Reliance Elektrik Works, 27/02/2016 10/07/2016 29/02/2016 30/09/2017 96.00 % Work in Progress (16 Rooms Completed) Detail Report
3.10 SKV E-Block Nand Nagari 64 M/s S.P.S Infrabuild Pvt Ltd. 27/03/2016 08/08/2016 28/03/2016 30/09/2017 93.00 % Work in Progress Detail Report
3.11 SKV Mansarover Park No.2 Shahdara 80 M/s. Naresh Kumar Gupta & Co Pvt Ltd 05/03/2016 17/07/2016 13/04/2016 30/09/2017 93.00 % Work in Progress Detail Report
3.12 GGSS F-I,F-II Block Nand Nagari Extn. 24 M/s. Purananand 13/03/2016 25/07/2016 14/03/2016 30/09/2017 92.00 % Work in Progress Detail Report
3.13 GGSSS, Gautampuri, Delhi 44 M/s. A. K. Builders 11/03/2016 23/07/2016 20/07/2016 30/09/2097 90.00 % Work in Progress Detail Report
3.14 G. Co. Ed. SSS Sunder Nagari, Delhi 44 M/s PurnaNand 13/03/2016 25/07/2016 14/03/2016 31/10/2017 78.00 % Work in Progress Detail Report
3.15 GGSSS C-Block Dilshad garden M/s S.P.S Infrabuild Pvt Ltd. 01/10/2016 17/07/2016 15/10/2017 68.00 % Work in Progress Detail Report
3.16 East of Gokulpur Loni Road, Delhi. 16 M/s S.P.S Infrabuild Pvt Ltd. 05/03/2016 17/07/2016 10/08/2016 15/10/2017 68.00 % Work in Progress Detail Report
3.17 Construction of 625 Additional Classrooms under Jurisdiction of Zone 6 of DDE North East District Priority I SH Providing services of inspection vehicle for the office use of Executive Engineer Edu M East and North East Delhi Detail Report
4 Construction additional SPS Class rooms in existing premises under Jurisdiction Zone-17 of District West-B (Priority-I) - Costing Rs. 84.38 Cr.
4.1 Govt. School Paschim Vihar, Jawala Puri Amalvas with MP Hall 52 Mr B. L. Infra Projects Pvt. Ltd. 29/02/2016 12/07/2016 11/05/2016 15/02/2017 100.00 % Work completed & 52 rooms and 1 MP Hall handed over. Detail Report
4.2 GSKV Tikri Kalan 68 Mr B. L. Infra Projects Pvt. Ltd. 16/03/2016 28/07/2016 15/05/2016 31/03/2017 100.00 % Work completed 64 rooms handed over. Detail Report
4.3 Various Govt. Schools of Bakkarwala with 1 M.P. Hall 76 Mr B. L. Infra Projects Pvt. Ltd. 14/02/2016 27/06/2016 15/02/2016 15/02/2017 100.00 % Work completed & 72 rooms and 1 MP Hall handed over. Detail Report
4.4 GBSSS Tikri Kalan with 1 M.P. Hall 68 Mr B. L. Infra Projects Pvt. Ltd. 16/03/2016 28/07/2016 14/05/2016 28/02/2017 100.00 % Work completed & 68 rooms and 1 MP Hall handed over. Detail Report
4.5 Govt.School Jwala Puri Amalvas (Shifted to Peera Garhi) 36 Mr B. L. Infra Projects Pvt. Ltd. 29/02/2016 12/07/2016 28/02/2017 100.00 % Work completed & 36 rooms handed over. Detail Report
4.6 G (Co.Ed) SSS Baprola 102 M/s Satya Narain 29/02/2016 12/07/2016 26/03/2016 31/03/2017 100.00 % Work completed & 100 rooms handed over. Detail Report
4.7 Construction additional SPS Class rooms in existing premises under Jurisdiction Zone-17 of District West-B (Priority-I) (SH:- C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc.) M/s Placement Security Services 23/03/2017 23/11/2017 30/06/2017 100.00 % work is in progress. Detail Report
4.8 C/o additional SPS class rooms under jurisdiction of DDE Zone-17 of District West B SH Providing services of Steno-cum-Computer Operator, MTS in the office of Assistant Engineer III, Education Maintenance Division West. M/s placement security services 23/03/2017 23/11/2017 30/06/2017 100.00 % Work completed. Detail Report
4.9 Govt. School, Mundka 80 M/s Mathra Dass Ahuja & Sons 14/03/2016 26/07/2016 01/06/2016 15/03/2017 98.00 % Work is in progress & 84 rooms handed over. Detail Report
4.10 GSKV Rohtak Road (1617010) Nangloi 64 Shri Pawan Kumar 19/12/2016 27/02/2017 30/06/2017 40.00 % Work is in progress. Detail Report
4.11 Govt. Co.ed.SSS Kavita Colony, Nangloi (1617004) 12 Shri Pawan Kumar 19/12/2016 27/02/2017 30/06/2017 30.00 % Work is in progress. Detail Report
4.12 GBSSS Nangloi (1617021) 32 Shri Pawan Kumar 19/12/2016 27/02/2017 30/06/2017 25.00 % Work is in progress. Detail Report
4.13 Govt.SSS, JJ Colony-2 Nangloi (1617035) 20 Shri Pawan Kumar 19/12/2016 27/02/2017 30/06/2017 20.00 % Work is in progress. Detail Report
4.14 C/o additional SPS Class room in existing premises under Jurisdiction Zone 17 of DDE West-B (Priority-I) SH Providing AMC of Computers, Accessories and Photocopier on rental basis for Edu. M. Division (West) and Edu. M. Sub-Division AE1,AE2,AE3,AE4. M/s STAR COMPUTER SYSTEMS 11/11/2016 10/11/2017 10/11/2017 Work is in progress. Detail Report
5 Construction of additional SPS Class room in existing premises under Jurisdiction Zone 4 of District North East (Priority-I) - Costing Rs. 75.64 Cr.
5.1 GGSSS, Yamuna Vihar Block-B1 16 M/s K.B.G.Engineers 27/02/2016 10/07/2016 23/03/2016 31/10/2016 100.00 % G.G.S.S.S Yamuna Vihar Block-B I completed Detail Report
5.2 G.Co-Ed Middle school Johripur, Delhi with 4 Toilet 12 M/s. K.B.G. Engineers 27/02/2016 10/07/2016 26/02/2016 07/01/2017 100.00 % Completed Detail Report
5.3 SKV Yamuna Vihar C-Block No.2 93 M/s. K.B.G. Engineers 27/02/2016 10/07/2016 26/02/2016 28/02/2017 100.00 % Completed Detail Report
5.4 GGSSS Sonia Vihar, GBSSS Sonia Vihar 23 M/s. Reliance Elektrik works 27/02/2016 10/07/2016 14/04/2016 03/07/2017 100.00 % 26 Rooms Completed Detail Report
5.5 GGSSS Karawal Nagar, Delhi 36 M/s. K.B.G. Engineers 27/02/2016 10/07/2016 11/05/2016 31/05/2017 100.00 % 36 Rooms Completed Detail Report
5.6 CRG SKV No. 01 & No. 02,Ghonda 32 M/s. A. K. Builders 11/03/2016 23/07/2016 04/04/2016 15/09/2017 98.00 % Work in Progress Detail Report
5.7 GGSSS Vijay Park,Moujpur,New 16 M/s. A. K. Builders 11/03/2016 23/07/2016 04/04/2016 15/09/2017 98.00 % Work in Progress Detail Report
5.8 GGSSS No.1 Tukmir Pur, GGSSS No.2 Tukmir Pur 76 M/s Reliance Elektrik Works, 27/02/2016 10/07/2016 14/04/2016 30/09/2017 94.00 % Work in Progress Detail Report
5.9 Construction of additional SPS Class room in existing premises under Jurisdiction Zone 4 of District North East (Priority-I) (SH: SPS type Class Rooms, Labs & MP Halls i/c Internal & External Water Supply, Sanitary and Electrical Installations, Development of site and fire fighting system etc in G.G.S.S.S No. 1 Tukmir Pur, G.G.S.S.S and G.B.S.S.S Sonia Vihar, G.G.S.S.S No. 2 Tukmir Pur, Delhi -Package-2 ) 99 M/s. Reliance Elektrik works 27/02/2016 10/07/2016 27/02/2016 30/09/2017 94.00 % Work in Progress Detail Report
5.10 Co.Edu. Sr. Sec. School Bhajanpura M/s. A. K. Builders 11/03/2016 23/07/2016 04/04/2016 30/09/2017 93.00 % work in Progress Detail Report
5.11 GBSS School at Karawal Nagar 81 M/s. M. C. Construction Co. 05/05/2016 16/09/2016 05/05/2016 15/10/2017 90.00 % (9 V. room) work in progress (36 Rooms completed) Detail Report
5.12 GSSS at Khajuri Khas M/s. M. C. Construction Co. 05/05/2016 16/09/2016 15/10/2017 88.00 % Work in progress Detail Report
5.13 SKV at khajuri khas 40 M/s. M. C. Construction Co. 05/05/2016 16/09/2016 05/05/2016 15/10/2017 86.00 % work in progress Detail Report
5.14 GGSSS Gokulpur Loni Road M/s. K.B.G. Engineers 27/02/2016 10/08/2016 15/10/2017 68.00 % Work in Progress Detail Report
5.15 GSSS at Mustafabad M/s. M. C. Construction Co. 05/05/2016 05/05/2016 05/05/2016 Not available (Court Case is pending. Site not available) Detail Report
6 Construction of Additional SPS Class rooms in existing premises under jurisdiction Zone 9 & 10 of District North West-A (Prioroty-I) (SH: SPS type class rooms, Labs & MP Halls i/c internal & external water supply, sanitary installation and electrical installation, development of site and fire fighting system etc. in GBSSS (Mussadi Lal) Narela, GGSSS Holambi Kalan Block-B, SKV Narela No.2 , SSS, Holambi Kalan, metro vihar, Block-A (Zone-10)( Package D). - Costing Rs. 73.42 Cr.
6.1 GBSSS Dr.Mukharjee Nagar 84 M/s Kamal Singh 21/02/2016 04/07/2016 22/02/2016 15/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress Detail Report
6.2 SKV Guru Teg Bahadur Nagar 28 M/s Kamal Singh 21/02/2016 04/07/2016 22/02/2016 10/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress. Detail Report
6.3 SKV Adarsh Nagar B 32 M/s. Shivalaya Construction Co. Pvt. Limited. 21/02/2016 04/07/2016 05/03/2016 10/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress. Detail Report
6.4 Adarsh Nagar- GGSSSS C 28 M/s. Shivalaya Construction Co. Pvt. Limited. 21/02/2016 04/07/2016 29/03/2016 10/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress. Detail Report
6.5 SSS(Co-Ed) Holambi Kalan Block G 44 M/s Shri Construction Co. 25/02/2016 11/07/2016 27/02/2016 15/06/2017 100.00 % Work completed Detail Report
6.6 SKV Tikri Khurd 40 M/s Shri Construction Co. 25/02/2016 11/07/2016 27/02/2016 28/02/2017 100.00 % Work completed Detail Report
6.7 GBSSS Alipur 64 M/s Shri Construction Co. 25/02/2016 11/07/2016 27/02/2016 31/07/2017 100.00 % Work completed Detail Report
6.8 GOVT. Co-Ed. Middle School Bhalaswa Village 52 M/s. Shivalaya Construction Co. Pvt. Limited. 25/04/2016 04/07/2016 23/05/2016 20/05/2017 99.00 % work in progress Detail Report
6.9 GOVT. Co-Ed. Middle School Bhalaswa Village 48 M/s. Shivalaya Construction Co. Pvt. Limited. 25/04/2016 04/07/2016 23/05/2016 20/05/2017 99.00 % work in progress Detail Report
6.10 GBSSS Block A-6 Pocket-II Narela 68 M/s. Amar Construction Co. 18/03/2016 30/07/2016 12/04/2016 30/09/2017 64.00 % work in progress Detail Report
6.11 GBSSS (Mussadi Lal) Narela (Package-D) 48 M/s. Amar Construction Co. 18/03/2016 30/07/2016 12/04/2016 30/09/2017 64.00 % Work in Progress Detail Report
7 Construction of Additional class rooms in existing premises under jurisdiction under EO Zone-24 of DDE (South) (Priority-I) - Costing Rs. 62.08 Cr.
7.1 School of Mandi Village With 1 MP Hall 88 M/s Harbel Singh & Sons 07/03/2016 19/07/2016 09/03/2016 30/04/2017 101.00 % COMPLETED Detail Report
7.2 Govt Boys Sr Sec School, Fatehpur Beri with MP Hall 76 M/s. Krishna Const Co 20/02/2016 03/07/2016 20/02/2016 30/04/2017 100.00 % work completed. Detail Report
7.3 Aya Nagar 88 M/s Kamal Singh 03/03/2016 15/07/2016 03/03/2016 15/03/2017 100.00 % work completed. Detail Report
7.4 Chattarpur School (Boys) 72 M/s Kamal Singh 05/03/2016 13/07/2016 05/03/2016 15/03/2017 100.00 % work completed. Detail Report
7.5 Chattarpur School (Girls),and 1 M.P. Room 32 M/s Kamal Singh 05/03/2016 13/07/2016 05/03/2016 30/04/2017 100.00 % work completed. Detail Report
7.6 Hakikat Rai SKV, Khanpur 16 Shri Pawan Kumar 07/03/2016 19/07/2016 02/05/2016 28/02/2017 100.00 % work completed. Detail Report
7.7 SBV 'J' Block Saket 68 Shri Pawan Kumar 07/03/2011 19/07/2016 02/05/2016 31/03/2017 100.00 % work completed. Detail Report
7.8 Govt.Girls Sr. Sec. School,Fatehpur Beri 40 M/s. Purananand 20/02/2016 03/07/2016 11/05/2016 31/07/2017 96.00 % Work in progress. Detail Report
8 Construction of 419 additional Class Rooms in existing premises under Jurisdiction of Zone 1 & 2 of DDE East (Priority-I) - Costing Rs. 57.73 Cr.
8.1 RS Kanya Vidyalaya, C-Block Vivek Vihar, Delhi 28 M/s. Naresh Kumar Gupta & Co Pvt Ltd 27/02/2016 10/07/2016 05/03/2016 28/02/2017 100.00 % Completed Detail Report
8.2 GGSS Block-27 Trilokpuri M/s RAMA Contractor 28/02/2016 11/07/2016 30/06/2017 100.00 % Completed Detail Report
8.3 RS Kanya Vidyalaya Kondli 20 M/s Ansum Builders 05/03/2016 17/07/2016 05/03/2016 28/02/2017 100.00 % 20 Room Completed Detail Report
8.4 SSR SKV Block-20 Trilokpuri 56 M/s RAMA Contractor 28/02/2016 11/07/2016 02/03/2016 08/03/2017 100.00 % 56 Rooms Completed Detail Report
8.5 RS Kanya Vidyalaya, New Ashok Nagar,New Delhi 27 M/s RAMA Contractor 28/02/2016 11/07/2016 16/03/2016 30/11/2016 100.00 % 27 Rooms Completed Detail Report
8.6 Govt. (Co-ed) S.S I.P. Extn, Delhi 20 M/s. Naresh Kumar Gupta & Co Pvt Ltd 27/02/2016 10/07/2016 31/07/2016 31/03/2017 100.00 % Work completed (V-20) Detail Report
8.7 GSBV (Veer Udham Singh), Mandavli Delhi 52 M/s. Naresh Kumar Gupta & Co Pvt Ltd 27/02/2016 10/07/2016 14/03/2016 15/09/2017 99.00 % work in progress (28 rooms completed) Detail Report
8.8 SKV No.3 (Veer Udham Singh) Mandawli Delhi 80 M/s. Anshum Builders 05/03/2016 17/07/2016 01/04/2016 30/09/2017 98.00 % Work in Progress Detail Report
8.9 GGSSS Vasundra Enclave 52 M/s Ansum Builders 05/03/2016 17/07/2016 01/04/2016 30/09/2017 97.00 % Work in Progress Detail Report
8.10 SKV No.3(Veer Udham Singh) Mandawli Delhi 80 M/s Ansum Builders 05/03/2016 17/07/2016 05/03/2016 30/09/2017 96.00 % work in progress (56 rooms completed) Detail Report
9 C/o Additional Class Room in SKV under EO Zone 21 District South West - Costing Rs. 37.45 Cr.
9.1 SKV, Samalka 36 M/s Y. D. Builders & Hotel Pvt Ltd 19/02/2016 02/07/2016 16/04/2016 31/05/2017 100.00 % work completed Detail Report
9.2 G (Co-Ed) SSS Dwarka Sector-6 48 M/s Y. D. Builders & Hotel Pvt Ltd 19/02/2016 02/07/2016 21/02/2016 31/03/2017 100.00 % Work completed Detail Report
9.3 GBSSS No.1 Samalka 82 M/s Astha Engineers & Contractor 03/03/2016 15/07/2016 18/03/2016 31/03/2017 100.00 % work completed Detail Report
9.4 Pochanpur 48 M/s Astha Engineers & Contractor 03/03/2016 15/07/2016 18/03/2016 31/03/2017 100.00 % Work completed Detail Report
9.5 SKV No.2 Sagarpur 101 M/s Asha Enterprises Pvt. Ltd. 19/02/2016 02/07/2016 04/04/2016 31/08/2017 92.00 % Work in progress Detail Report
10 C/o 246 Additional Class Room at Burari & Nehru Vihar - Costing Rs. 33.33 Cr.
10.1 SKV Burari 96 M/s N.N.Buildcon Pvt. Ltd. 25/02/2016 24/07/2016 28/03/2016 10/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress. Detail Report
10.2 GGSS Burari 54 M/s N.N.Buildcon Pvt. Ltd. 25/02/2016 24/07/2016 16/04/2016 10/05/2017 100.00 % Work completed and letter written to School Principal for taking over of the building. Delay in taking over due to non procurement of furniture in class room. Minor development work in progress. Detail Report
10.3 SKV Nehru Vihar 96 M/s N.N.Buildcon Pvt. Ltd. 25/02/2016 24/07/2016 28/03/2016 04/05/2017 100.00 % Work completed and handed over to HOS on dt. 04.05.2017 Detail Report
11 Construction of 187 Additional Classrooms in 08 School Buildings under EO Zone-5 of DDE (North East) (Priority-I) - Costing Rs. 25.76 Cr.
11.1 GGSSS Block-X Brahampuri 20 M/s. Devinder Singh 13/03/2016 25/07/2016 30/03/2016 30/09/2017 98.00 % Work in Progress Detail Report
11.2 GGSSS,Brhampuri with vetical Extn. 46 M/s. Devinder Singh 13/03/2016 25/07/2016 30/03/2016 30/09/2017 97.00 % Work in Progress Detail Report
11.3 GGSSS Welcome Colony Delhi 32 M/s. Devinder Singh 13/03/2016 25/07/2016 19/04/2016 30/09/2017 96.00 % Work in Progress Detail Report
11.4 GGSSS Jafrabad Extn. with vertical Extn. 54 M/s. M. C. Construction Co. 30/03/2016 11/08/2016 07/04/2016 30/09/2017 91.00 % Work in Progress Detail Report
11.5 G.Co-Ed SSS New Jafrabad 20 M/s. M. C. Construction Co. 30/03/2016 11/08/2016 15/05/2016 30/09/2017 89.00 % Work in Progress Detail Report
12 C/o 177 Nos. additional class rooms in 04 Nos. school building under EO Zone-14 and 16 of DDE west A Priority-I. - Costing Rs. 24.39 Cr.
12.1 SKV Chand Nagar 88 M/s S. S. Total Construction Pvt. Ltd. 14/02/2016 27/06/2016 05/05/2016 30/04/2017 100.00 % Work completed & 84 rooms handed over. Detail Report
12.2 School of Ramesh Nagar 44 M/s Tewatia Construction Pvt. Ltd. 14/03/2016 26/07/2016 10/03/2016 31/01/2017 100.00 % Work completed & 44 rooms handed over. Detail Report
12.3 School of Patel Nagar 16 M/s Tewatia Construction Pvt. Ltd. 14/03/2016 26/07/2016 11/05/2016 31/01/2017 100.00 % Work completed & 16 rooms handed over. Detail Report
12.4 SBV, West Patel Nagar (School ID-1516143) 28 M/s Tewatia Construction Pvt. Ltd. 14/03/2016 26/07/2016 31/01/2017 40.00 % work is in progress. Detail Report
12.5 Main work Detail Report
12.6 4202 Detail Report
12.7 4202 Detail Report
13 Construction of 20 Nos. Additional SPS Class room in Govt. Co. Edu. Sr. Sec. School Bhajanpura Delhi. under Jurisdiction Zone 4 of District North East (SH: SPS type Class Rooms, Labs & MP Halls i/c Internal & External Water Supply, Sanitary and Electrical Installations, Development of site and fire fighting system etc). - Costing Rs. 2.72 Cr.
13.1 Construction of 20 Nos Additional SPS Class room in Govt Co Edu Sr Sec School Bhajanpura Delhi under Jurisdiction Zone 4 of District North East SH SPS type Class Rooms Labs and MP Halls including Internal and External Water Supply Sanitary and Elect 20 M/s Munsi Ram Kharbanda 21/07/2017 20/01/2018 21/08/2017 1.00 % Work in Progress Detail Report
14 Construction of 10 Nos. SPS Class rooms Double Storey & 4 Nos. Toilets under SSA at Govt. Sr. Sec. School Radhey Shyam Park in East Delhi. - Costing Rs. 1.37 Cr.
14.1 Construction of 10 Nos. SPS Class rooms Double Storey & 4 Nos. Toilets under SSA at Govt. Sr. Sec. School Radhey Shyam Park in East Delhi. Shri Anish Ahmed 08/12/2014 07/08/2015 31/10/2015 70.01 % work in progress Detail Report
15 Construction of 12 Nos. Additional SPS Class rooms & 3 Nos. Toilets in Govt. Co-Education Sr. Sec. School at Lalita Park , Delhi. - Costing Rs. 1.22 Cr.
15.1 Construction of 12 Nos. Additional SPS Class rooms & 3 Nos. Toilets in Govt. Co-Education Sr. Sec. School at Lalita Park , Delhi. M/s. Classic Construction Co. 08/12/2014 07/08/2015 31/10/2015 32.01 % Work In Progress Detail Report
16 Construction of Science Lab, Art & Craft Room, Computer Lab, LIbrary & Toilet Sarvodaya Kanya Vidyalaya Shankar Nagar, Delhi dg. 2015-16 School ID 1003026 - Costing Rs. 0.59 Cr.
16.1 Construction of Science Lab, Art & Craft Room, Computer Lab, LIbrary & Toilet Sarvodaya Kanya Vidyalaya Shankar Nagar, Delhi dg. 2015-16 School ID 1003026 18/05/2016 17/11/2016 18/05/2016 30/09/2017 99.00 % Civil work completed and process regarding execution of electrical items which were not part of the original agreement being done. Detail Report
17 Repairing and renovation of school building such as fixing tiles, door, shutter, glass panes, white wash repair of toilet etc, at GGSS Mukundpur Village. - Costing Rs. 0.26 Cr.
17.1 Civil Work Shri Narender Kumar 28/02/2017 30/03/2017 30/09/2017 100.00 % Work is in Progress Detail Report
17.2 Repairing and renovation of school building such as fixing tiles, door, shutter, glass panes, white wash repair of toilet etc, at GGSS Mukundpur Village. 31/07/2017 31/07/2017 31/07/2017 100.00 % Work Completed Detail Report
17.3 Repair and renovation of school building such as fixing tiles, door shutter, glass panes, white wash, repair of toilet etc. at GGSS Mukundpur Village. 31/07/2017 31/07/2017 30/09/2017 30.00 % Work in Progress Detail Report
18 C/o SPS type 12 additional class rooms, 4 Toilet Block under SSA Scheme at SKV No. 2 Khyala, New Delhi.
18.1 C/o SPS type 12 additional class rooms, 4 Toilet Block under SSA Scheme at SKV No. 2 Khyala, New Delhi. Mr Rishu Constrution Company 27/02/2017 25/08/2017 25/08/2017 Work is in progress. Detail Report
18.2 C/o SPS type 12 additional class rooms, 4 Toilet Block under SSA Scheme at SKV No. 2 Khyala, New Delhi Composite work Civil and Electrical. Mr Rishu Constrution Company 27/02/2017 25/08/2017 25/08/2017 work is in progress. Detail Report
18.3 4202 Under SSA Detail Report
19 Providing furniture in various school for Additional SPS Class Rooms Under East & North East, Delhi, Education Zone- 1,2,3,4,5 & 6 (Priority-I)
19.1 Providing furniture in various schools for additional SPS class rooms under Zone West Delhi Education Zone 16 17 and other schools Priority-I M/s GEEKEN SEATING COLLECTION PVT LTD financial bid opened on dated 21.06.2017. Detail Report
19.2 Providing furniture in various schools for additional SPS class rooms under Zone West Delhi Education Zone 14 18 and other schools Priority I M/s GEEKEN SEATING COLLECTION PVT LTD 31/08/2017 30/11/2017 financial bid opened on dated 21.06.2017. Detail Report
19.3 Providing furniture in various schools for additional class rooms under Zone South and South East Delhi Delhi Education Zone 29 and other schools Priority I financial bid opened on dated 03.08.2017. Detail Report
19.4 Providing furniture in various schools for additional class rooms under Zone South and South East Delhi Delhi Education Zone 25 and other schools Priority I financial bid opened on dated 03.08.2017. Detail Report
19.5 Providing furniture in various schools for additional class rooms under Zone East and North East Delhi Education Zone 5 6 and other schools Priority I financial bid opened on dated 10.08.2017. Detail Report
19.6 Providing furniture in various schools for additional class rooms under Zone East and North East Delhi Education Zone 1 2 and other schools Priority I financial bid opened on dated 10.08.2017. Detail Report