Education Work
Last Updated on: 02/12/2019
Details of Education Works - Additional SPS Class Rooms (Progress)
S. No. Name of School No
of
Room
Agency Stipulated
DOS
Stipulated
DOC
Site Handed
Over on
Expected
Date of
Completion
Progress in % Remarks View
1 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 182 Nos. of additional SPS class rooms (Package-C) - Costing Rs. 2892.65 Cr.
1.1 SKV Shanker Nagar (School Id- 1003026) 24 17/03/2019 11/12/2019 11/12/2019 37.00 % Column of Ist Floor has been cast. In other block, binding of reinforcement of plinth beam has been cast. Detail Report
1.2 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 182 Nos. of additional SPS class rooms (Package-C) 216 M/s SPS Infrabuild Pvt. Ltd. 17/03/2019 11/12/2019 11/12/2019 35.00 % Work stopped due to pollution Detail Report
1.3 RPVV Gandhi Nagar (School Id- 1003261) 48 17/03/2019 11/12/2019 11/12/2019 32.00 % Binding of reinforcement of Terrace beams is under progress in Block - A (Part-2). In Block - B (Part-2), Ist floor beam has been cast. In Block-A (Part-1), binding of reinforcement of Ist floor column is in progress. Detail Report
1.4 SBV, Rajgarh Colony (School Id- 1001110) 42 17/03/2019 11/12/2019 11/12/2019 0.50 % Block-A RCC work completed upto terrace level & placing of granite of window sill is in progress in block A and laying of 4th floor beams is under progress in block B. Detail Report
1.5 SKV Radhey Shyam Park (School Id- 1003153) 74 17/03/2019 11/12/2019 11/12/2019 Slab of 1st floor has been laid in block-B. Casting of 2nd floor beam is under progress in block-A. Detail Report
1.6 SKV Vievk Vihar (ID : 1001022) (Addl. Rooms) 42 17/03/2019 11/12/2019 11/12/2019 Preparation of structural drawing is under process. Detail Report
1.7 Jhilmil Colony-SBV Avinash Chadda (ID: 1001105 ) (Addl. Rooms) 8 17/03/2019 11/12/2019 11/12/2019 Preparation of structural drawing is under process. Detail Report
2 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 180 Nos. of additional SPS class rooms (Package-B) - Costing Rs. 2892.65 Cr.
2.1 SKV Kondali (Jija Bai) (School Id- 1002026) 20 17/03/2019 11/12/2019 11/12/2019 31.00 % Casting of beam at 3rd floor level completed. Detail Report
2.2 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 180 Nos. of additional SPS class rooms (Package-B) 184 M/s RAMA Contractor 17/03/2019 11/12/2019 11/12/2019 16.00 % Work stopped due to pollution Detail Report
2.3 GGSSS Mayur Vihar Ph-3 (Kondali Gharauli) (School Id- 1002352) 80 17/03/2019 11/12/2019 11/12/2019 10.00 % Casting of footings and brick work in foundation up to plinth beam completed in approximately 70% of area. Excavation work completed for remaining footings Detail Report
2.4 SKV Gazipur (School Id- 1002184) 44 17/03/2019 11/12/2019 11/12/2019 Plinth beam reinforcement of one block is under progress. Detail Report
2.5 GGSSS Kalyanpuri (School ID 1002039) 20 17/03/2019 11/12/2019 11/12/2019 Casting of beam at Second Floor level under progress. Detail Report
2.6 SKV Patparganj (School Id- 1002031) 20 17/03/2019 11/12/2019 11/12/2019 The work of constructing porta cabins is in progress The contractor is being pursued continuously to expedite the progress so that porta cabins could be handed over to the school authorities but seeing the slow progress of the work, it is explicitly clear that the contractor is deliberately delaying the work of Patparganj School on one or the other pretexts despite our repeated efforts and requests. Detail Report
3 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW - Costing Rs. 2892.65 Cr.
3.1 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 200 M/s RAMA Contractor 24/12/2018 19/09/2019 31/12/2019 21.50 % Work stopped due to pollution Detail Report
3.2 SKV Vishwas Nagar (School Id- 1001196) 54 24/12/2018 19/09/2019 24/12/2018 31/12/2019 2.00 % 3rd floor beam casting in progress. Detail Report
3.3 Govt. Co-ed SSS Preet Vihar (School Id- 1002351) 58 24/12/2018 19/09/2019 24/12/2018 28/02/2020 1.50 % (i) 3rd floor column casting is in progress at Block-A (ii) 2nd floor beam block-B in progress Detail Report
3.4 SKV Surajmal Vihar (School Id- 1001102) 44 24/12/2018 19/09/2019 10/01/2019 31/03/2020 1st floor column is in progress in Block-A & 1st floor beam shuttering in progress in Block-B Detail Report
3.5 SKV, Kiran Vihar (School Id- 1001106) 44 24/12/2018 19/09/2019 10/01/2019 30/04/2020 Plinth beam completed in one block & excavation is stopped due to hindrance in disposal of malba on account of neighbour adamancy. Detail Report
4 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 174 Nos. of additional SPS class rooms in various schools (Package-E) - Costing Rs. 2892.65 Cr.
4.1 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 174 Nos. of additional SPS class rooms (Package-E) 218 M/s SPS Infrabuild Pvt. Ltd. 17/03/2019 11/12/2019 11/12/2019 12.00 % Work stopped due to pollution Detail Report
4.2 Kailash Nagar, Delhi (School Id- 1003033) 30 17/03/2019 11/12/2019 11/12/2019 Site hinderd due to tree shifting is not being done. Excavation of footing is in progress. Detail Report
4.3 Bholanath Nagar, Delhi (School Id- 1001020) 58 17/03/2019 11/12/2019 11/12/2019 (i) 2nd floor beam completed upto expension joint & Excavation of footing of next block is in progress. (ii) Plinth beam completed in MP Hall Detail Report
4.4 SKV Gokalpur Village (School Id- 1104021) 40 17/03/2019 11/12/2019 11/12/2019 Casting of footing in progress. Detail Report
4.5 BCP SKV Babarpur (School Id- 1105019) 56 17/03/2019 11/12/2019 11/12/2019 1st floor beam in one block is completed and plinth beam in progress in other block. 1st Floor beam is in progress Detail Report
4.6 SKV Block-13 Geeta Colony (School Id- 1003024) 26 17/03/2019 11/12/2019 11/12/2019 2nd floor roof is in progress. Detail Report
4.7 Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING) 20 17/03/2019 11/12/2019 11/12/2019 Excavation of RWH in progress. Detail Report
5 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 184 Nos. of additional SPS class (Package-D) - Costing Rs. 2892.65 Cr.
5.1 Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 184 Nos. of additional SPS class rooms (Package-D) M/s RAMA Contractor 17/03/2019 11/12/2019 11/12/2019 Excavation of RWH in progress. Detail Report
5.2 Govt. Co-ed I.P. Extension (School Id- 1002189) 94 17/03/2019 11/12/2019 11/12/2019 2nd floor column work is in progress. Footing castted which was hindered by tree. Detail Report
5.3 GGSSS Khichripur (School Id- 1002037) 68 17/03/2019 11/12/2019 11/12/2019 Main site handed over to agency Detail Report
5.4 GGSSS Shivaji Park Shahdara (School Id- 1105022) 24 17/03/2019 11/12/2019 11/12/2019 Demolition work of temporary shade structure is progress Detail Report
5.5 Govt. Co-Ed. SSS Chilla Village. 32 17/03/2019 11/12/2019 11/12/2019 Demolition work of SPS is in progress. Detail Report
6 Construction of 20 Nos Additional SPS Class room in Govt Co Edu Sr Sec School Bhajanpura Delhi under Jurisdiction Zone 4 of District North East SH SPS type Class Rooms Labs and MP Halls including Internal and External Water Supply Sanitary and Electr - Costing Rs. 2.72 Cr.
6.1 Construction of 20 Nos Additional SPS Class room in Govt Co Edu Sr Sec School Bhajanpura Delhi under Jurisdiction Zone 4 of District North East SH SPS type Class Rooms Labs and MP Halls including Internal and External Water Supply Sanitary and Electr 20 M/s SURENDRA KUMAR 08/06/2018 04/12/2018 30/11/2019 113.00 % Finishing work in progress Detail Report
7 C/o 20 nos SPS type (D/S) class rooms with staircase in GSKV (04 nos) & GBSS (08 nos) in Shadikhampur and G. S. Co-Ed. (04 nos), East Punjabi Bagh and GSKV No-2 (04 nos) in Punjabi Bagh New Delhi through S.S.A i/c internal electrical installation - Costing Rs. 2.62 Cr.
7.1 SPS

Preliminary Estimate Sent, Sanction Awaited.

Detail Report
8 Construction of 10 Nos. SPS Class rooms Double Storey & 4 Nos. Toilets under SSA at Govt. Sr. Sec. School Radhey Shyam Park in East Delhi. - Costing Rs. 1.37 Cr.
8.1 Construction of 10 Nos. SPS Class rooms Double Storey & 4 Nos. Toilets under SSA at Govt. Sr. Sec. School Radhey Shyam Park in East Delhi. Shri Anish Ahmed 08/12/2014 07/08/2015 31/10/2015 70.01 % work in progress Detail Report
9 C/o 11 Nos. classroom of SPS (D/S) with staircase and toilet block at SBV Moti Nagar, New Delhi (Phase-I) - Costing Rs. 1.28 Cr.
9.1 SPS . Detail Report
9.2 Construction of two rest room for electrical & civil workers . Detail Report
10 Construction of 12 Nos. Additional SPS Class rooms & 3 Nos. Toilets in Govt. Co-Education Sr. Sec. School at Lalita Park , Delhi. - Costing Rs. 1.22 Cr.
10.1 Construction of 12 Nos. Additional SPS Class rooms & 3 Nos. Toilets in Govt. Co-Education Sr. Sec. School at Lalita Park , Delhi. M/s Classic Construction Co. 08/12/2014 07/08/2015 31/10/2015 32.01 % Work In Progress Detail Report
11 EOR to Govt. Girls Sr Secondary School Ram Nagar Paharganj New Delhi SH Repair of boundary wall and other minor repairs works in school - Costing Rs. 0.02 Cr.
11.1 EOR to Govt. Girls Sr Secondary School Ram Nagar Paharganj New Delhi SH Repair of boundary wall and other minor repairs works in school 03/03/2019 02/04/2019 30/06/2019 40.00 % Work in progress Detail Report
12 Providing furniture in various school for Additional SPS Class Rooms Under North West,Delhi, Education Zone-10,11,12 & 13 (Priority-I)
12.1 Providing furniture in various school for Additional SPS Class Rooms Under North West,Delhi, Education Zone-10,11,12 & 13 (Priority-I) 10/10/2017 09/11/2017 09/11/2017 100.00 %

work done

Detail Report