Report of E.O.R. Works of School - Progress
S. No. Name of School Sanction Amount
/ Date / No
Date of Start / Completion / Expected Expenditure / Progress Remarks View
SE (Education) M
EE (Education) M, East & North East
2017-18
1 Construction of Boundary wall at Newly proposed higher Secondary School at Geeta Colony Delhi. Agreement No .: 09/EE/Edu M (E & NE)/PWD/DS/2018-19 0.16 Cr.
10/10/2017

F. 17/Estate/Const./Boundary Wall/Geeta Colony/3627-30 dt. 10/10/2017

14/02/2019
14/05/2019
14/05/2019

10.00 %
Foundation work in progress. Detail Report
EE (Education) M, C&ND
2 119/EE/2014-15 Agreement No .: 119/EE/2014-15

30/01/2015
28/02/2015
17/06/2015

40.00 %
Work completed. Detail Report
3 misc. repair works repair works at Bunglow No. 48. Ashoka Road, New Delhi Agreement No .: 01/EE/CBMD M- 433/2014-15

19/04/2014
03/05/2014
09/05/2014

WORK COMPLETED Detail Report
South East Maintenance Circle
South East Elect Maintenance Division
2016-17
4 Special repair and replacement of EI and Fans in classroom and corridoors and renovation in the hall at SKV NO.2, Kalkaji, New Delhi (ID- 1925038) 0.11 Cr.
19/05/2016

2015000088, F.16/Estate/GSKV NO.2 Kalkaji, New D

14/08/2016
13/10/2016
13/10/2016

work in progress Detail Report
5 Special Repari of Ei & Fans, Panel and compound light in Govt. Sarvodaya Vidyalaya, Ali Ganj, New Delhi. 0.10 Cr.
01/06/2016

SV/AG/2016/348

14/08/2016
13/10/2016
13/10/2016

work in progress Detail Report
2015-16
6 Renovation of EI & replacement Electricals accessories at HARKESH NAGAR GGSSS (ID-1925341) 0.10 Cr.
18/03/2016

.

25/06/2016
24/07/2016
25/09/2016

Work in Progress Detail Report
7 Supply installation testing and commissioning of Surveillance system and flood light fitting at Deffence Colony,Block A-SNSKV-1924025 0.10 Cr.
30/09/2015

.

20/05/2016
19/06/2016

Work in Progress 95% Detail Report
8 Providing & fixing wiring,rewiring,DB,MCB,earthing,electrical light fittings,ceiling fans,flood light fitting and UG cable in GGSS No-3 Molar Band New Delhi. 0.07 Cr.
04/08/2015

.

23/04/2016
31/05/2016
31/05/2016

Work in Progress 80% Detail Report
9 RMO Swimming pool at Sister Nivedita Sarvodaya Kanya Vidyalay "A" Block Defence Colony,New Delhi.(SH:-Operation and Maintenance of electric pumps,fitration plants and allied equipment of swimming pool.) 0.05 Cr.
31/03/2016

.

17/05/2016
16/11/2016
16/11/2016

Work in Progress Detail Report
10 S/I/T/C of water cooler & RO System at Kalkaji,No.2-SKV (ID-1925038) 0.02 Cr.
27/12/2015

.

25/06/2016
24/07/2016
25/09/2016

Work in Progress Detail Report
South East Building Maintenance Division
11 EOR to SKV Hari Nagar Ashram, New Delhi during 2015-16 (SH: 4 nos. class change of roof AC sheet to convert Ref Sand Stone roof & grider and T iron fram Kota Stone Slab flooring 25mm thick Kota stone slab

10/07/2015
09/09/2015
09/09/2015
0.10 Cr.
100.00 %
Detail Report
12 Renovation of Toilet Blocks & Repair to AC Sheet of Classrooms & Providing Water Proofing Treatment at Tughlakabad Village School

14/02/2015
14/02/2015
14/02/2015
0.14 Cr.
100.00 %
Detail Report
South Maintenance Circle
South Electrical Maintenance Division
2016-17
13 Providing and replacing of Ceiling and Exhaust fans in rooms, Corridoors and Toilets at SBV, J Block, Saket, New Delhi (ID-1923056) 0.07 Cr.
09/06/2016

01/07/2016
31/08/2016

90.00 %
Work in Progress Detail Report
14 Installastion of PA System with cable work at Dr. Ambedkar Nagar, Sector-IV No. 1, GGSSS (School Id -1923044) 0.06 Cr.
23/04/2016

GGSSS/No.1/Sect.4/A/N/804 Sanction group 201500003

20/08/2016
19/09/2016

0.01 %

Estimate submitted to Principal vide letter No.23(05)/EE(N)/DB/PWD/16-17/ 1404 Dt.10.06.2016

Detail Report
15 Providing and fixing fans, fittings, LED street light fittings etc. with necessary cabling etc. as reqd. at Govt. Girls Sr. Secondary School , Sector-V, Dr. Ambedkar Nagar, New Delhi-110062.(School Code: 1923050). 0.04 Cr.
04/07/2016

GGSSS No. 2/Sec.5/AN/2016 Sanction Group 2015000196

16/08/2016
15/09/2016

0.01 %
Work complted Detail Report
16 Providing and fixing of Zonal P.A System at Ramanujam, SKV, Mehrauli,New Delhi. 0.04 Cr.
23/04/2016

2015000042/293-96

16/08/2016
15/09/2016

0.01 %
work in progress Detail Report
17 Repair/Re-innovation of security lights & wiring in a 4 nos. Bathroom at Mehrauli Qutab Sarvodaya Bal Sr. Sec. Vidyalaya. (School ID:- 19223120) under AE(E) EMSD-3 (M-South) PTS Malviya Nagar, New Delhi-110017. 0.04 Cr.
09/06/2016

SBSSV/QM/2016-17/50

13/07/2016
20/08/2016

90.00 %
Work in Progress Detail Report
18 SITC of storage Cooler cum purifier at SBV J Block Saket, New Delhi (ID-1923056) 0.02 Cr.
08/06/2016

01/07/2016
31/08/2016

98.00 %
work in Progress Detail Report
19 Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050.
04/07/2016

GGSSS No. 2/ Sec.5/AN/2016/ Sanction Group 2015000195,

20/08/2016
15/09/2016

0.01 %
work completed Detail Report
South Bldg & Saket Court Maintenance Division
20 A/R & M/O to Educational Building and other building under Sub-Division M-4223, M-422, New Delhi duging-2014-15 (SH:- Internal and External finishing work of school building at Saket and Pushp Vihar, New Delhi, section-I) Agreement No .: 22/EE/CBMDM-422/2014-15

24/06/2014
23/12/2014
0.11 Cr.
100.00 %
Detail Report
21 A/R & M/O to Educational Building and other building under Sub-Division M-4223, M-422, New Delhi duging-2014-15 (SH:- Misc. Civil work of School Building at Saket and Pushp Vihar, New Delhi, section-I). Agreement No .: 18/EE/CBMDM-422/2014-15

18/06/2014
17/10/2014
0.18 Cr.
100.00 %
Work completed & agreement closed Detail Report
22 A/R & M/O to Educational Building under Sub-Division M-4223, M-422, New Delhi, dg. 2014-15 (SH:- Repair of RCC column, beams, facia and other misc. repair work of school buildings at Saket and Pushp Vihar, New Delhi, section-1).

23/06/2014
22/12/2014
0.20 Cr.
100.00 %
Work completed & agreement closed. Detail Report
West Maintenance Circle
Tihar Jail Complex & West Building Division
2015-16
23 EOR to Rajkiya Pratibha Vikas Vidyalaya, BE-Block, Hari Nagar, New Delhi. (SH:- Strenthening of building and renovation all toilets, labs, class rooms and misc. civil works i/c electrical and horticulture). 2.35 Cr.
22/04/2015

Vide Sanction group No. 2014000750/87-96 Dated 22-04-2015

08/03/2016
09/07/2016
30/09/2016
0.45 Cr.
65.00 %
 PE send to Education and sanction awaited Detail Report
South West Maintenance Circle
South West Building & Dwarka Court Maintenance Division
2015-16
24 C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. 0.93 Cr.
03/11/2015

.

25/03/2016
24/07/2016
24/07/2016

75.00 %
DOSE PERTAIN TO THIS DIVISION Detail Report
25 EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System 0.10 Cr.
28/07/2015

.

23/05/2016
23/06/2016
23/06/2016

70.00 %
Dose not pertain to this Division Detail Report
26 Fixing of Hard Drawn febric wire in window in preventing monkey menance in all class room s , labs & other rooms at RSKV, Mehrauli, New Delhi. 0.10 Cr.
17/03/2016

.




30.00 %
Work in progress 30% Detail Report
27 Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) 0.06 Cr.
31/07/2015

.

10/05/2016
09/06/2016

50.00 %
Tender re-call and date of opening 24-09-2016 Detail Report
Project Circle
Project Electrical Division
2015-16
28 Renovation work at Swami Dayanand S.K.V. Old Rajender Nagar, New Delhi to develop as Model School. 0.54 Cr.
15/07/2015


30/06/2016

Work Completed

 

Detail Report
SRD Project Division 1
2015-16
29 Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS 0.09 Cr.
05/06/2015

05/04/2016
04/06/2016

80.00 %
Completed Detail Report
2014-15
30 EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. 0.43 Cr.
01/01/2015

15/04/2016
14/10/2016

10.00 %
Completed Detail Report
31 EOR to Govt Sr.Sec School, Chabi Ganj, Kashmere Gate, Delhi. (SH-Kota stone Flooring and Wall tile in seven Class rooms). 0.43 Cr.
01/01/2015




Detail Report
32 EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. 0.37 Cr.
09/02/2015

15/04/2016
14/07/2016

15.00 %
Completed Detail Report
33 EOR to Savitri Bai Phule Industrial Training Institute, Mori Gate, Delhi. dg. 2016-17 (SH-Renovation of COPA Lab and Drafting Room like profile sheet, False Ceiling and Virtrified Tiles) 0.37 Cr.
09/02/2015




Detail Report
Shahdara Maintenance Circle
Karkardooma Court Division
2015-16
34 Providing Rain Water Harvesting pit, laying interlocking paver block in the ground and raising of boundary wall at Govt. Girls Sr. Sec. School at A Block, Nand Nagri, Delhi Building ID-11061019 0.36 Cr.
11/09/2015

F.16/const/GGSSS/Estate/Shahadara/Delhi/2660-2664

10/06/2016
09/10/2016
15/09/2016

76.00 %
work in progress Detail Report
35 Construction of boundary wall at Govt. School Building mayo school and CBSE office in IP Extension Delhi. 0.34 Cr.
18/02/2016

F.16/Estate/site,IPE-I/2011/4139-40

17/07/2016
14/10/2016
14/10/2016

6.00 %

Estimate Sent to  Med. Dir.  GTB vide letter No.  20(02)/fl0Lok0vuq0ea0¼iwoZ½@yks0fu0fo0@2016&17@214 Dated 03.02.2017

Detail Report
36 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 0.28 Cr.
14/03/2016

F.16/Estate/SKV/MPBM Shahadara/

16/06/2016
13/09/2016
13/09/2016

53.00 %

T.S. under process.

Detail Report
37 Renovation of Classrooms, Principal’s Room, Conference Room & Labs. 0.24 Cr.
02/03/2016

F.16/Estate/DIEt/Dilshad Garden/15-16

08/05/2016
05/08/2016
20/08/2016

86.00 %
work in progress Detail Report
38 const. of New cycle stand, Dismantling of tin shed and rovision of free path from toilet to first gate. 0.24 Cr.
30/03/2016

F.16/Estate/GGSSS/C-Block Vivek Vihar/2015-16/5003-5008

13/06/2016
12/07/2016
31/08/2016

11.00 %
Work in porgress Detail Report
39 Renovation of Principal Room, Staff Room and Laboratories. 0.23 Cr.
23/03/2016

F.16/Estate/Mansarovar Park/2015-16(4844-4849)

20/06/2016
18/08/2016
31/08/2016

71.00 %
Work in progress Detail Report
40 Renovation of Classrooms. 0.19 Cr.
20/08/2015

F.16/Estate/BID-11061482/North-East/GGSSS,C-Block,Dilshad Garden/2015-16

07/05/2016
05/07/2016
25/08/2016

66.00 %
Work in progress Detail Report
41 Provision of boundary wall with iron grill, footpath from second gate to the classrooms & along with boundary wall (Opposite of Park). 0.17 Cr.
28/09/2015

F.16/Const/Estate/GGSSS/VV/Delhi/2965-2969

02/05/2016
30/07/2016
31/08/2016

76.00 %
Work in Progress Detail Report
42 Renovation of M.P. Hall 0.15 Cr.
05/08/2015

F.16/Estatew/GGSSS/Dilshad Garden/C-Block/NE/2015-16

26/04/2016
04/06/2016
24/08/2016

66.00 %
work in progress Detail Report
43 Repair and renovation of toilets 0.11 Cr.
31/03/2016

F.16/Estate/SKV Shahadara

17/06/2016
15/08/2016
20/08/2016

91.00 %

 Detailed estimate  under process.

Detail Report
44 Repair of boundary wall and toilets. 0.11 Cr.
23/06/2015

2015000115

06/05/2016
03/08/2016
31/08/2016

86.00 %
Work in progress Detail Report
45 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 0.07 Cr.
22/08/2015

17/01/2016
30/04/2016

80.00 %
polycarbonate Detail Report
46 Renovation of Toilet, Swimming Pool and other misc. works. 0.07 Cr.
22/08/2015




Detail Report
47 Repair of Basketball Court Flooring. 0.06 Cr.
07/08/2015

2015000272

06/05/2016
19/06/2016
31/08/2016

25.00 %
site is not handed over to contractor since in the working areathe work of SPS Detail Report
2014-15
48 Renovation of M.P. Hall with Toilet Block of G.S.K.V at E Block, Nand Nagri, Delhi 0.21 Cr.
01/01/2015

.

29/01/2016
28/05/2016
31/08/2016
0.07 Cr.
100.00 %
work in progress Detail Report
49 Waterproofing treatment of roof. 0.18 Cr.
14/01/2015

F.16/RSKV/SMV/2013/3329

08/04/2016
06/06/2016
31/08/2016
0.02 Cr.
100.00 %

In progress 80%

Detail Report
EE (C) (Shahdara) Bldg
2015-16
50 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 0.36 Cr.
10/09/2015

01/05/2016
30/06/2016

0.01 %

work in progress

Detail Report
51 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 0.17 Cr.
20/08/2015

10/04/2016
09/06/2016

0.01 %

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
52 Renovation of MP Hall. 0.15 Cr.
05/08/2015

26/04/2016
24/06/2016

0.01 %
Work recently awarded. Detail Report
53 Renovation of toilet & water module. 0.07 Cr.
26/06/2015

22/04/2016


0.01 %

Work Started.

Detail Report
54 Providing and fixing M.S.Sheet doors and other misc. work. 0.04 Cr.
05/11/2015

22/04/2016
21/05/2016

0.01 %

WORK COMPLETED

Detail Report
55 Construction of water module. 0.03 Cr.
05/11/2015

22/04/2016
20/06/2016

0.01 %
Work recently awarded. Detail Report
East Maintenance Circle
East Building Division
2015-16
56 renovation of toilets on second floor in pucca building Kalyanvas- 0.08 Cr.
28/07/2015

20151391




completed Detail Report
57 Construction and Renovation Setup of Nursery Classroom Pre School in 20 Nos Sarvodaya Vidyalaya of East District

24/06/2018
23/10/2018

work in progress 50% Detail Report
North Maintenance Circle
North Building Division
58 "EOR to SKV No-2 Adrash Nagar under Sub-Division NB-13 Model Town Delhi. (SH: - Replacement of window & misc. repair work). "

05/06/2018
04/10/2018
31/10/2018

Work in progress (5%) Detail Report
59 E.O.R of roof (water proofing treatment) and other misc. work like plinth protection, Door, window, plaster etc. at Govt. Co-ed. Sr. Sec. School, Ghoga, Delhi.

07/10/2018
06/12/2018
06/12/2018

Work in progress (15%) Detail Report
60 EOR TO G.B.S.S.S. at Badli, Delhi. (SH: - Construction of security guard room 2nd main gate for emergency exit, car/ motorcycle parking shed.

08/06/2018
07/11/2018
07/11/2018

Work in progress (40%) Detail Report
61 EOR TO G.B.S.S.S. at Badli, Delhi. (SH: - Development of backside of class rooms, path approaching class rooms & main entrance path.)

08/06/2018
07/11/2018
07/11/2018

Work in progress (40%) Detail Report
62 EOR to Govt.Sarovdaya Kanya Vidyalaya, Lalita block, Shastri Nagar, Delhi. (SH:- Renovation of Ground and first floor toilets, Renovation of Principal room, Staff room and Misc Repair Works.)

21/09/2017
20/12/2017
30/10/2018

Work in progress (80%) Detail Report
63 EOR to Non-residential Building under Sub-Division NB-13, Delhi during 2016-17. (SH: - Construction of R.C.C. boundary wall at Aryabhatt Polytechnic ,G.T. Karnal Road, Delhi).

21/08/2017
20/02/2018
20/03/2018

Work in progress (95%) Detail Report
64 EOR to SKV Badli. (SH:- Raising of existing Boundary wall.)

11/12/2017
10/03/2018
10/03/2018

Work in progress (90%) Detail Report
65 Repair and Raising of boundary wall & making pedestrian path around the boundary wall at Govt. Sarvodaya Co-ed. Sec. School, Auchandi, Delhi.

04/06/2018
03/10/2018
20/10/2018

Work in progress (60%) Detail Report
66 Water proofing treatment on Roof at Govt. Boys Sr. Sec. School No.2, J.J. Colony, Bawana, Delhi.

06/08/2018
05/11/2018
05/11/2018

Work in progress. (20%) Detail Report
67 Water proofing treatment on Roof at Govt. Boys Sr. Sec. School, Bawana, Delhi.

06/08/2018
05/11/2018
05/11/2018

Work in progress. (20%) Detail Report