New Friends Colony.
Office Name
Education South & South East Maint Divn
History Sheet         Background Note        
T.S. Amount
1624.27 Lacs
Dated
--
Tender Amount
1608.03 Lacs
Dated
13/03/2016
Progress Details
Date of Start: 13/03/2016
Date of Completion: 25/07/2016
Expected Date of Completion: 30/06/2017
Actual Completion Date: 24/05/2017
Contractor
M/s Subham Builders
Payment
Civil:  154.00 Lacs (Jan 2018)
% Progress :100.00 % (Jan 2018)
Present Position
Civil :  15/05/2018
completed