C/o additional SPS Class rooms in existing premises under Jurisdiction Zone-18 of District West-B (Priority-I) (SH:- C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc. at G(Co-ed) Bindapur, GGSSS Bindapur, SKV A-Block Janakpuri) (Package-D)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note        
T.S. Amount
1422.57 Lacs
Dated
12/01/2016
Tender Amount
1408.34 Lacs
Dated
16/02/2016
Progress Details
Date of Start: 18/02/2016
Date of Completion: 01/07/2016
Expected Date of Completion: 31/03/2017
Actual Completion Date: 12/06/2017
Contractor
M/s Varun Gupta & Co.
Payment
Civil:  74.92 Lacs (Jul 2019)
% Progress :100.00 % (Jul 2019)
Present Position
Civil :  11/10/2019
Work Completed & 44 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null