C/o additional SPS Class rooms in existing premises under Jurisdiction Zone-18 of District West-B (Priority-I) (SH : C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc. at SKV Matiala & SG(Co-ed) Vidayala Posangipur) (Package-E)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note        
T.S. Amount
1051.78 Lacs
Dated
12/01/2016
Tender Amount
1041.27 Lacs
Dated
10/03/2016
Progress Details
Date of Start: 16/03/2016
Date of Completion: 28/07/2016
Expected Date of Completion: 31/12/2016
Actual Completion Date: 15/03/2017
Contractor
Mr B. L. INFRA PROJECTS PVT. LTD.
Payment
Civil:  222.61 Lacs (Apr 2022)
% Progress : % (Apr 2022)
Present Position
Civil :  11/10/2019
Work completed & 16 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null