C/o 177 Nos. additional class rooms in 04 Nos. school building under EO Zone-14 and 16 of DDE west A Priority-I (SH : C/o main SPS Type building i/c Internal & External Water Supply Sanitary & Electric Installations, development of site and Fire Fighting System etc. at SKV Chand Nagar. (Package-A)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet                
T.S. Amount
1032.39 Lacs
Dated
12/01/2016
Tender Amount
957.77 Lacs
Dated
16/02/2016
Progress Details
Date of Start: 14/02/2016
Date of Completion: 27/06/2016
Expected Date of Completion: 30/04/2017
Actual Completion Date: 22/05/2017
Contractor
M/s S. S. Total Construction Pvt. Ltd.
Payment
Civil:  202.41 Lacs (Jan 2024)
% Progress : % (Jan 2024)
Present Position
Civil :  30/01/2018
Work completed & 84 rooms handed over.
Bottlenecks
Civil :  30/01/2018
Null