School of Mandi Village
Office Name
Education South & South East Maint Divn
History Sheet         Background Note        
T.S. Amount
861.09 Lacs
Dated
08/01/2016
Tender Amount
852.47 Lacs
Dated
09/03/2016
Progress Details
Date of Start: 07/03/2016
Date of Completion: 19/07/2016
Expected Date of Completion: 30/04/2017
Actual Completion Date: 15/05/2017
Contractor
M/s Harbel Singh & Sons
Payment
Civil:  867.96 Lacs (Jul 2023)
% Progress : % (Jul 2023)
Present Position
Civil :  09/04/2018
work completed.