Construction of water module.
Office Name
Karkardooma Court Division
History Sheet                
Progress Details
Date of Start: 22/04/2016
Date of Completion: 20/06/2016
Expected Date of Completion: 20/06/2016
Actual Completion Date: 20/06/2016
Payment
Present Position
Civil :  10/08/2021
Completed.