SKV (St. Eknath) J&K Block Dilshad Garden
Office Name
Education East & North East Maint Divn/Education Elect Maint Division 2
History Sheet     Abstract of Cost     Background Note        
Progress Details
Date of Start: 05/03/2016
Date of Completion: 17/07/2016
Expected Date of Completion: 15/10/2017
Actual Completion Date: 15/10/2017
Contractor
M/s S.P.S Infrabuild Pvt Ltd.
Payment
Present Position
Civil :  01/08/2019
Work completed (48 rooms completed)
Bottlenecks
Civil :  01/08/2019
Completed