Repair and renovation of school building such as fixing tiles, door shutter, glass panes, white wash, repair of toilet etc. at GGSS Mukundpur Village.
Office Name
History Sheet                
Progress Details
Date of Start: 31/07/2017
Date of Completion: 31/07/2017
Expected Date of Completion: 10/05/2018
Actual Completion Date: 26/04/2018
Payment
Present Position
Civil :  09/06/2018
Work has been foreclosed vide letter No- 54(511)/CBMD M-321/846 Dated 26.04.2018, as per report pf structural audit, it is found that the building is not structurally safe