Const 180 Nos. of additional SPS class rooms (Package-B)
Office Name
Education East & North East Maint Divn
T.S. Amount
4172.33 Lacs
Dated
06/09/2018
Tender Amount
3636.43 Lacs
Dated
13/03/2019
Progress Details
Date of Start: 17/03/2019
Date of Completion: 11/12/2019
Expected Date of Completion: 12/10/2022
Actual Completion Date: 12/10/2022
Contractor
M/s RAMA Contractor
Payment
Civil:  3212.52 Lacs (Aug 2023)
% Progress : % (Aug 2023)
Present Position
Civil :  11/04/2023
work completed.
Bottlenecks
Civil :  11/04/2023
work completed.