Repair of toilets and other misc work at Adarsh Nagar GGSSS 1309034
Office Name
North Building Division
History Sheet     Abstract of Cost     Background Note        
T.S. Amount
7.05 Lacs
Dated
11/06/2019
Tender Amount
3.94 Lacs
Dated
23/07/2019
Progress Details
Date of Start: 24/07/2019
Date of Completion: 23/09/2019
Expected Date of Completion: 31/07/2020
Actual Completion Date: 31/10/2020
Contractor
M/s Sign Age India
Payment
Civil:  3.82 Lacs (Jun 2021)
% Progress : % (Jun 2021)
  
Present Position
Civil :  23/09/2020
Work in progress 90%