Raising of boundary wall on back side of the school, Grit wash on boundary wall renovation of multipurpose hall and misc work
Office Name
North Building Division
History Sheet     Abstract of Cost            
T.S. Amount
95.79 Lacs
Dated
14/11/2019
Tender Amount
53.77 Lacs
Dated
23/12/2019
Progress Details
Date of Start: 23/12/2019
Date of Completion: 20/04/2020
Expected Date of Completion: 31/10/2020
Actual Completion Date: 31/10/2020
Contractor
Mr Jeetender Kumar Verma
Payment
Civil:  43.28 Lacs (Nov 2020)
% Progress : % (Nov 2020)
  
Present Position
Civil :  28/04/2022
work is in progress (80%)
Bottlenecks
Civil :  28/04/2022
work is in progress