Co 232 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 12
Office Name
Education North Maint Divn
T.S. Amount
4557.83 Lacs
Dated
31/08/2018
Tender Amount
4150.23 Lacs
Dated
13/01/2019
Progress Details
Date of Start: 13/01/2019
Date of Completion: 09/10/2019
Expected Date of Completion: 23/12/2021
Actual Completion Date: 23/12/2021
Contractor
M/s K.B.G. Engineers
Payment
Civil:  5736.25 Lacs (Feb 2024)
% Progress : % (Feb 2024)
Present Position
Civil :  11/07/2022
Work completed.