Inspection - 09/02/2026

Working
Repaired
Yet to be repaired
Not Updated

Inspection - 07/02/2026

Working
Repaired
Yet to be repaired
Not Updated

Total as on 09/02/2026

Installed
20,904
Working
20,674
Repaired / Rectified
79
Yet to be repaired
151
Division Name Installed Working Repaired / Rectified Yet to be repaired Target Date Remarks
East Maintenance Zone
M 351
Central & New Delhi Electrical Maintenance Division
3858 3819 20 19 09/02/2026 On 09.02.2026, a total of 39 fittings were reported malfunctioning at BBM Road, due to a cable fault. All the faulty fittings will be rectified and made functional by the evening of 09.02.2026.
M 253
East Building & Players Building Electrical Division
5406 5357 46 3 10/02/2026 The details of non-functional points observed during inspection are as under and work is going on to rectify them: 1. Narwana Road - 5 nos. 2. Dhruva Apartment - 8 nos. 3. Madhu Vihar Road -1 - 4 nos. 4. Madhu Vihar Road-2 - 7 nos. Defective points mentioned on Grievance portal are as under:- 1. Ganesh Nagar/Pandav Nagar-1 No 2. Shakarpur School Block-1 No 3. Nirman Vihar-1 No
South Maintenance Zone
M 152
South West Elect Maintenance Division
11640 11498 13 129 05/03/2026 Major work need to be done such as replacement of defective cables, fittings & accidental poles damaged by third party etc. However day to day maintenance has been attended on regular basis by TATA/BRPL/BYPL & rectified accordingly.