Infrastructure Projects - Other Roads
  Sanction Wise   Agreement Wise
Click on Number to view the list
Amount in Lacs
Infrastructure Projects - Other Roads
Less than 1 crore 1 crore to 5 crore 5 crore to 25 crore 25 crore to 100 crore More than 100 crore Total
Status Number Amount Number Amount Number Amount Number Amount Number Amount Number Amount
Work in Progress 497 ₹ 8097.28 10 ₹ 2703.38 3 ₹ 2948.05 510 ₹ 13748.70
Sanction Work not yet Started 2 ₹ 91.53 5 ₹ 1262.88 2 ₹ 1974.04 9 ₹ 3328.45
Work yet to be Sanctioned 3 ₹ 103.83 10 ₹ 2088.12 13 ₹ 2191.96
Conceptual Stage / Planning 230 ₹ 1560.48 14 ₹ 2871.57 3 ₹ 2275.30 247 ₹ 6707.34
Completed in 2018 - 19
Completed in 2017 - 18 4 ₹ 179.18 2 ₹ 252.65 6 ₹ 431.83
Completed before 2017 - 18 137 ₹ 3799.01 61 ₹ 15319.80 32 ₹ 29857.43 7 ₹ 27050.29 5 ₹ 477571226.00 242 ₹ 477647252.54
* Total Amount of Projects