S. No.क्र. सं. | Name of Workकार्य का नाम | Date of Start | Cost (In Lac) | Target Progress | Agency | Present Position | Satisfactory | Viewदेखें | ||
---|---|---|---|---|---|---|---|---|---|---|
Stp. Completion | ||||||||||
Exp. Completion | Expenditure | Phy. Progress | Bottleneck | Quality | Safety | Progress | ||||
1 | Redevelopment of Tis Hazari District Court |
|
519981.00 0.00 (Mar'19) |
0.00 (Mar'19) |
A/A & E/S AWAITED
|
Detail Report
Graph / Photo |
||||
2 | Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment |
18/04/2015
17/10/2017 31/10/2024 |
96400.00 141512.74 (Sep'23) |
92.00 % 0.00 (Sep'23) |
Larson & Toubro Limited |
lower pylon 1st lift in progress
LRP4 well Sinking extremely slow |
Detail Report
Graph / Photo |
|||
3 | Underground Tunnel, Underpass, FOB, Loops, Ramps, Footpath, Road Work including Road Signage, Road/Street Lighting works, Tunnel furnishing (FF& FA system, PA system, Automated drainage, integrated tunnel management system etc.), landscaping/horticulture work & allied works |
08/11/2017
29/08/2019 31/08/2023 |
77700.00 50268.01 (Sep'23) |
100.00 % 0.00 (Sep'23) |
M/s L&T Ltd. |
work is in progress
|
Detail Report
Graph / Photo |
|||
4 | Construction of New Block For Medicine, Maternity And Advanced Pediatric Centre ( Composite Steel plus RCC framed 2B plus G plus 22 Storyed building At LN Hospital including internal water supply, Sanitary installation, External Development works, Dr |
04/11/2020
03/05/2023 31/10/2023 |
46552.58 17215.59 (Jul'23) |
0.00 (Jul'23) |
Swadeshi Civil Infrastructure Pvt. Ltd., 302, DLF Tower B Jasola, New Delhi-110025 |
In LN1 steel Col. erected upto 17 th floor, 20th floor slab has been casted pour 1. 19th floor slab casted in pour 3. 16th floor slab casted in pour2.
In LN2, pour I, 6th floor slab has been casted. In Pour II, 10th floor slab casted. In Pour III, 6th floor slab has been casted, erection of 11th floor is in progress.
No |
Detail Report
Graph / Photo |
|||
5 | Setting up of Semi permanent temporary I.C.U. Hospital at Shalimar Bagh(G plus 3) (1430beds), Kirari (G plus 4)(458 Beds) and Sultanpuri (G plus 3)(525 Beds) Package I |
|
43132.08 1960.76 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
6 | Supply, installation, testing, commissioning of CCTV camera in Delhi. (Sub: Empanelment of firms for supply, installation, testing, commissioning & CAMC of CCTV system in Delhi). |
24/11/2018
23/11/2019 14/11/2027 |
42798.32 7725.71 (Sep'23) |
0.00 (Sep'23) |
Bharat Electronics Ltd |
work completed. The work of CAMC which is part of the project, is going on.
|
Detail Report
Graph / Photo |
|||
7 | setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) |
23/09/2021
22/02/2022 04/08/2022 |
40775.18 12389.92 (Jun'23) |
0.00 (Jun'23) |
SAM India Builtwell |
GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave.
|
Detail Report
Graph / Photo |
|||
8 | Setting up of Semi-permanent temporary I.C.U Hospital at Chacha Nehru Bal Chikitsalaya (G plus 4) (596 beds) and GTB Hospital Complex (G plus 4) (1912 Beds) Package II |
|
35533.93 16967.93 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
9 | C/o Additional Court Rooms on the existing Court Bldg. in District Court Complex at Rohini |
|
33532.67 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
10 | Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi (EPC Mode |
10/09/2022
08/12/2023 08/12/2023 |
33420.85 3025.81 (Sep'23) |
0.00 (Sep'23) |
piling work under progress for retaining wall side of down ramp
none |
Detail Report
Graph / Photo |
||||
11 | Construction of New Hospital Block at Babu Jagjivan Ram Memorial Hospital, Jahangirpuri, New Delhi |
|
31879.73 |
|
PE of Civil Work submitted to the O/o Chief Engineer on dated 10/05/2023
|
Detail Report
Graph / Photo |
||||
12 | Setting up of 1912 bedded semi permanent/temporary ICU Hospital at GTB. |
23/09/2021
22/02/2022 31/12/2023 |
31608.00 0.00 (Jul'23) |
94.00 % 82.00 % (Jul'23) |
Work stopped due to non availability of funds.
The work is delayed due to non-availability of site for GTB, many revisions in drawings by consultant, ban on construction works due to pollution followed by restrictions. STP & water tanks works delayed due to changes in capacity of sizes. |
Detail Report
Graph / Photo |
||||
13 | Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover |
10/09/2022
08/12/2023 08/12/2023 |
30848.06 2236.46 (Sep'23) |
72.00 % 0.00 (Sep'23) |
Work is in progress.
Work is in progress. |
Detail Report
Graph / Photo |
||||
14 | Construction of Home for Assisted Living at Narela, Delhi |
|
30528.15 |
|
Land available. A/A & E/S is yet to be received
|
Detail Report
Graph / Photo |
||||
15 | Providing 600 Nos. LED Screens at Various Locations in Delhi. |
|
29481.84 |
|
The tender has been cancelled on 07.07.2023 due to administrative reasons.
|
Detail Report
Graph / Photo |
||||
16 | Setting up of Semi-permanent temporary I.C.U Hospital at Sarita Vihar (G plus 4) (336beds) and Raghubir Nagar (G plus 3)(1577 Beds) Package III |
|
29175.20 2715.41 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
17 | Repairing of fire alarm system installed at Lawyers chamber block 3 |
28/02/2020
27/03/2020 |
27388.89 |
|
Ekta Enterprises |
|
Detail Report
Graph / Photo |
|||
18 | Construction of Hospital at Madipur, New Delhi |
11/11/2020
10/11/2022 14/09/2023 |
26970.58 12942.33 (Sep'23) |
0.00 (Sep'23) |
Ramacivil India Construction Private Limited |
Physical progress 87%. & Financial Progress Rs. 139.36 Cr.
Factory approval yet to be submitted for structural glazing work to commence. Becoming a critical hindrance |
Detail Report
Graph / Photo |
|||
19 | Construction of Hospital at Jwalapuri, New Delhi |
07/08/2020
13/08/2022 31/03/2024 |
26950.37 11854.61 (Sep'23) |
100.00 % 0.00 (Sep'23) |
Parnika Commercial and Estates Pvt. Ltd. |
Structure RCC work completed. Flooring work, masonry work 95 % completed, façade work, development work & electrical work is in progress.
N.A. |
Detail Report
Graph / Photo |
|||
20 | Construction of Hospital at Hastsal, New Delhi |
17/06/2021
16/06/2023 30/06/2024 |
23695.11 2370.47 (Sep'23) |
0.00 (Sep'23) |
Casting of 7th floor slab is under progress. 60% casting has been completed. The masonry work in 1st, 2nd & 3rd floor are in progress. Granite flooring in upper basement and ground floor is in progress.
|
Detail Report
Graph / Photo |
||||
21 | REWIRING/REPAIRING OF ELECTRICAL ACCESSORIES IN TOILETS AT VARIOUS DELHI GOVT. SCHOOL |
09/08/2017
09/11/2019 |
23127.43 |
|
NKG Infrastructure Limited |
|
Detail Report
Graph / Photo |
|||
22 | C/o Additional Lawyer Chambers near District Court, Dwarka, Sec-10, New Delhi. |
|
22764.65 0.00 (Mar'19) |
0.00 (Mar'19) |
Matter has been pending for appointment of consultant
|
Detail Report
Graph / Photo |
||||
23 | Construction of 132 Type-V Quarters and 52 Type-VI Quarters for Judges at Anand Vihar Delhi. |
|
22456.97 |
|
Land allotment issue
|
Detail Report
Graph / Photo |
||||
24 | C/o Police Housing project at Mandoli, Delhi-93(SH: C/o 300 Nos. Type-II and 60 Type-IV qtrs and its related development works) |
|
22130.16 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
25 | C/o New Building for office of Deputy Commissioner & District Magistrate (South-west) at Sector-10, Dwarka, New Delhi |
|
19481.76 0.00 (Mar'19) |
0.00 (Mar'19) |
Revised drawing submitted to the DC office Dwarka
|
Detail Report
Graph / Photo |
||||
26 | Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-II. |
14/01/2020
11/07/2020 30/09/2023 |
19053.31 2126.06 (Aug'23) |
0.00 (Aug'23) |
Till date approximate 57628 CCTV cameras, out of 61885 approval, have been installed and work is in progress.
|
Detail Report
Graph / Photo |
||||
27 | Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-1 |
14/01/2020
11/07/2020 30/09/2023 |
19050.80 2467.08 (Aug'23) |
0.00 (Aug'23) |
Till date approximate 38485 CCTV cameras, out of 45055 approval, have been installed and work is in progress.
|
Detail Report
Graph / Photo |
||||
28 | Construction additional courts at new plot at Karkardooma in front of existing Karkardooma Court Complex, Delhi. |
|
17394.78 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
29 | C/o 750 Bedded Hospital at Dwarka, New Delhi. |
|
16355.70 441.02 (Jun'23) |
0.00 (Jun'23) |
Work has been transferred to EE(E) South West Health Maintenance Division. |
Detail Report
Graph / Photo |
||||
30 | Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode |
03/02/2023
31/07/2024 31/07/2024 |
15785.00 3316.46 (Sep'23) |
40.00 % 0.00 (Sep'23) |
Ram Kumar Contractor |
Piling work, pile cap, pier, girder casting work in progress
|
Detail Report
Graph / Photo |
|||
31 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi |
18/10/2019
10/04/2021 30/11/2023 |
13447.15 5989.02 (Sep'23) |
100.00 % 0.00 (Sep'23) |
Roshan Real Estate Pvt Ltd. |
Road work, Rainwater harvesting, MGPS and false ceiling work of Block-A is in progress. The work of Nurses hostel & Dormitory is almost completed.
Slow progress of electrical work |
Detail Report
Graph / Photo |
|||
32 | Extension of Ashram Flyover to DND Flyover. |
19/06/2020
18/06/2021 30/09/2023 |
12879.00 620.57 (Aug'23) |
100.00 % 0.00 (Aug'23) |
KCC Buildcon Pvt. LTD |
The extended Ashram Flyover has been inaugurated by the Hon'ble CM, Delhi on 06.03.2023. Development works are in progress.
|
Detail Report
Graph / Photo |
|||
33 | Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. |
23/09/2021
22/02/2022 31/12/2023 |
9709.00 0.00 (Jun'23) |
100.00 % 88.00 % (Jun'23) |
Work stopped due to non availability of funds.
The work of ground floor, 3rd floor and 4th floor in CNBC held up due to changes desired by MD/DGHS. The consultant has modified the plans to be approved by DGHS. This complete exercise will take some time, after that the work in these areas will be taken up. Decision regarding skywalk in CNBC to be issued for execution. |
Detail Report
Graph / Photo |
||||
34 | C/o Family Court Complex at Rohini, New Delhi |
|
9579.83 3.30 (May'19) |
0.00 (May'19) |
Conceptual plans have approved by Hon’ble Delhi High Court, BMCC on 01.12.2022. NIT under process
|
Detail Report
Graph / Photo |
||||
35 | C/o Haji House at Sector-22, Phase-II, Dwarka, New Delhi |
|
9566.03 0.00 (Mar'19) |
0.00 (Mar'19) |
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
36 | C/o New DC office at Mandawali, Fazalpur, Delhi |
|
8432.86 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
37 | Construction of Delhi Fire Service Headquarter Building at Connaught Place, New Delhi-110001 |
|
8094.10 0.00 (Mar'19) |
0.00 (Mar'19) |
The Hon'ble Minister (Home) Govt. of NCT of Delhi has desired that as per FAR and Ground Coverage has already been increase as per MPD-2021 from 120 to 300 and 30% to 50% respectively The Fire Services Deptt. To advice for re-calling the tenders for consultancy services of above work seems justified. A letter has been received from consultant M/s Gian P. Mathur & Association (P) Ltd. (Copy enclosed) for revised escalation of consultancy fees for FAR increased 120 to 300% and Ground Coverage 30 to 50%. The case was sent to the C.E. (OP) . The above case has been review/scrutiny in the C.E. (OP) after review/scrutiny of the case the C.E. (OP) has required to provide current prevailing market rate with justification. The EE (OPD-I) directed to the consultant to provide current prevailing market rate with justification to this office on 28.11.2022.
After scrutiny proposal, the competent authority has been decided on 14.02.2023 to prepare the revised preliminary estimate to obtain revised A/A & E/S from client department before call a fresh tender for consultancy work. A letter has also been received from Delhi Fire Service authority vide No. F6/DFS/MS/BP/2023/271 dated 13.02.2023 for calling fresh tender. The Revised PE amounting to Rs. 2,23,46,965/- for consultancy work has been sent CE (OP), PWD vide this office letter No. 23(1)/EE/OPD-I)/PWD/83 dt. 17.02.2023. Preliminary Drawings are being prepared by Sr. Architect (Projects) and a meeting was also held in the O/o ADG (Projects) among the PWD and Fire Headquarter authorities on 23.03.2023.
|
Detail Report
Graph / Photo |
||||
38 | Maintenance of P.C. in Divn and SD Office. |
|
7122.82 |
|
PNSC Infrastructure Pvt. Ltd |
|
Detail Report
Graph / Photo |
|||
39 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) |
18/07/2021
17/07/2022 31/10/2023 |
6988.57 605.62 (Oct'22) |
2.00 % (Oct'22) |
A. K. Mehta & Co. |
Work in progress.
|
Detail Report
Graph / Photo |
|||
40 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A6 Paschim Vihar, New Delhi (Package - 7). |
18/07/2021
17/07/2022 31/07/2023 |
6988.57 3585.82 (Sep'23) |
0.00 (Sep'23) |
A. K. Mehta & Co. |
Work is in progress. Null |
Detail Report
Graph / Photo |
|||
41 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. |
06/08/2019
29/10/2020 31/12/2023 |
6563.40 2564.48 (Sep'23) |
89.00 % 0.00 (Sep'23) |
PNSC Infrastructure Pvt. Ltd |
Finishing works, waterproofing, external façade and external development works are under progress.
|
Detail Report
Graph / Photo |
|||
42 | Supplying, Installation, Testing and Commissioning of Interactive Display panel, mini PC OPS and Wifi Router in the existing school building |
|
6543.02 |
|
work in progress
|
Detail Report
Graph / Photo |
||||
43 | Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi. |
|
5120.46 |
|
|
Detail Report
Graph / Photo |
||||
44 | Civil and Electrical Composite Work (Dwarka Sector-16 & Qutubapur). |
18/07/2021
17/07/2022 31/07/2023 |
5058.13 392.80 (Jul'23) |
0.00 (Jul'23) |
PNSC Infrastructure Pvt. Ltd |
The process for local body approvals is in progress. DUAC approval received on 19.09.2022. Fire NOC received. Building Plans uploaded on MCD Portal by the consultant for approval. C/o of boundary wall and other misc. work at Dwarka Sector -16 school is in progress.
MCD require Extainsion of time for constrcution from DDA for which request has been made to DDA by L&Estate office vide No.F-16/site/Estate/4210-12 dt. 11.10.2022. As required by DDA, letter requesting waiver of composition Fee for 'Extension of Time" submitted to DDA on 24.11.2022.
Building Plans have been approved by SE (Bldg.), MCD . Approved Building Plans are expected to be released shortly.
All local body approval has been recevied. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency.
Building work started on 19.05.2023. Foundation work / Plinth beams work is in progress.
Qutubapur- SANCTION WITHDRAWN (i). Site layout plan has been uploaded to MCD by consultant for approval on dated 25.05.2022 and property tax of land also has been deposited. (ii). There is no tree cutting and no transplanting required. (iii). Additional Commissioner MCD & CTP, MCD during meeting 3.10.2022 informed that due to urbanization of villages, this gram sabha land is now under control of DDA .MCD is yet to upload their observation regardfing Layout Plan . (iv) DO dated 17.11.2022 issed by E-in-C to VC, DDA regarding clarification required by MCD. Response is still awaited. (v) LoP was discussed during meeting in MCD on 27.03.2023. Minutes of Meeting is still awaited. Above Sanction Withdrawn by DoE vide letter no.F.16/Estate/Cons./ Pucca School/Qutubapur/ 1594-1601 Dated: 24.05.2023 . |
Detail Report
Graph / Photo |
|||
45 | Providing furniture in various govt. schools for new Pucca School Buildings and other additional classrooms under Education, PWD, Delhi. |
|
4919.07 791.32 (Sep'23) |
0.00 (Sep'23) |
PG lette issued
|
Detail Report
Graph / Photo |
||||
46 | Strengthening of Rohtak Road (NH-10) from Punjabi Bagh Round about to Metro Pillar No. 526 under PWD, Maintenance Division West-2 Roads, New Delhi |
|
4613.56 |
|
Estimate submitted to MORTH for approval
|
Detail Report
Graph / Photo |
||||
47 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) |
|
4350.79 7.43 (Jun'19) |
0.00 (Jun'19) |
Technical bid opened Work transffered to Street scapping Division |
Detail Report
Graph / Photo |
||||
48 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) |
|
4350.79 |
|
|
Detail Report
Graph / Photo |
||||
49 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 43,50,79,456 |
|
4350.79 |
|
|
Detail Report
Graph / Photo |
||||
50 | Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. |
14/10/2022
13/10/2023 03/06/2024 |
4329.32 0.00 (Aug'23) |
53.00 % 10.00 % (Aug'23) |
Dharamraj Contracts (I) Pvt. Ltd. |
Work affected due to non-availibility of NOC from I & FC Department, non shifting of utility by IGL, TPDDL etc. Work affected due to non-availibility of NOC from I & FC Department, non shifting of utility by IGL, TPDDL etc. |
Detail Report
Graph / Photo |
|||
51 | C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. |
15/07/2022
14/07/2023 31/08/2023 |
4199.50 2065.77 (Jul'23) |
0.00 (Jul'23) |
Gawar Construction Ltd., |
work in progress
NA |
Detail Report
Graph / Photo |
|||
52 | W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. |
30/10/2012
29/04/2013 29/04/2013 |
3812.11 |
|
KCC Buildcon Pvt. LTD |
.
|
Detail Report
Graph / Photo |
|||
53 | Supplying and installation of Modular Operation Theatre and Medical Gas Pipe line System at orthopedic department of LNH including Emergency Trauma Services and Intensive Care Beds (50) |
|
3742.21 |
|
|
Detail Report
Graph / Photo |
||||
54 | Construction of 140 nos additional SPS Classrooms in DOE Schools GGSSS No. 1 Tukhmirpur, Delhi (1104262) 40 Class rooms, GGSSS No. 2 Tukhmirpur, Delhi (1104419) 32 Class rooms & GSKV Khajuri Khas, Delhi (1104022) 68 Class rooms including Laboratory, staircases, toilets and ramps, internal water supply, sanitary installations, Internal electrification and fire fighting arrangements. |
|
3713.27 |
|
In progres$
2% |
Detail Report
Graph / Photo |
||||
55 | E & M works relating to all day to day operation & maintenance, A/R & M/O Works & Special Repair Works etc |
27/05/2022
26/05/2024 26/05/2024 |
3516.35 1446.89 (Sep'23) |
68.00 % 0.00 (Sep'23) |
Swastik Electrotech Pvt. Ltd. |
Work in progress Work in progress |
Detail Report
Graph / Photo |
|||
56 | Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes |
24/12/2022
23/06/2023 31/08/2023 |
3483.10 2767.81 (Sep'23) |
0.00 (Sep'23) |
OPTIMUM SECURITY SOLUTIONS PVT. LTD. |
Work in progress
|
Detail Report
Graph / Photo |
|||
57 | Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works) |
|
3385.59 2669.18 (Jan'23) |
0.00 (Jan'23) |
|
Detail Report
Graph / Photo |
||||
58 | Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works) |
|
3368.55 678.56 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
59 | Construction of Six Storeyed conventional multilevel Parking at Dr. Baba Saheb Ambedkar Hospital at Rohini Sector-6,Delhi. |
|
3266.00 |
|
work
|
Detail Report
Graph / Photo |
||||
60 | Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work |
30/05/2020
29/05/2022 29/05/2022 |
3194.88 1377.18 (May'23) |
0.00 (May'23) |
MAHAVIR PRASAD GUPTA AND SONS |
work completed
null |
Detail Report
Graph / Photo |
|||
61 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. |
17/10/2022
16/10/2023 31/12/2023 |
3000.18 1118.61 (Aug'23) |
77.00 % 0.00 (Aug'23) |
Jai Bhagwan |
2nd floor slab casting work for 40 % are in progress, 3rd floor column reinforcement worik for 40% area in progress and balance 20% are terrace parapet column casting in progress, brick masonary work at 1st and 2nd floor in progress
2nd floor slab casting work for 40 % are in progress, 3rd floor column reinforcement worik for 40% area in progress and balance 20% are terrace parapet column casting in progress, brick masonary work at 1st and 2nd floor in progress |
Detail Report
Graph / Photo |
|||
62 | Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi |
05/04/2022
04/12/2022 30/09/2023 |
2915.78 433.70 (Sep'23) |
98.00 % 0.00 (Sep'23) |
SVK Infrastructures |
Building Work: RCC work of Admin cum Rest Room is in progress. Reinforcement work of the 3rd floor slab has been completed.
RCC work and Brickwork of the workshop building has been completed.
Hardstanding/CC Pavement: 75% of EarthWork has been completed and 20% of WMM layer work has been completed.
Boundary Wall: The work of construction of the boundary has been completed. Finishing work has also been completed
Drainage Work: 75% of the drainage work completed.
The structure for the underground water tank and septic tank has been completed.
|
Detail Report
Graph / Photo |
|||
63 | Providing services of Data Entry / Computer Operators, Personal Secretary, Clerical Staff, Messengers, Messenger cum Peon & Peon for the office of E-in-C, Pr. Chief Engineer (M&F), Chief Engineer (East)-M, Chief Engineer (Flyover) along with its subordinate office, Circle C & ND – M & C & ND-Roads Division, Providing services of security guard for watch and ward for the office of Circle C & ND-M & C&ND-R Division & Watch and Ward of integrated tunnel in and around ITPO. |
01/04/2023
31/03/2025 31/03/2025 |
2892.73 385.83 (Sep'23) |
21.00 % 0.00 (Sep'23) |
RAKSHAK SECURITAS PVT. LTD. |
Work in progress
|
Detail Report
Graph / Photo |
|||
64 | Street Scaping of Ring Road from Moolchand Junction to Ashram Chowk |
|
2880.35 |
|
|
Detail Report
Graph / Photo |
||||
65 | SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW |
17/10/2019
12/07/2020 30/06/2023 |
2849.35 2883.20 (Sep'23) |
0.00 (Sep'23) |
A. K. Builders |
work in progress.
work in progress. |
Detail Report
Graph / Photo |
|||
66 | Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work. |
|
2820.52 34.01 (Mar'22) |
0.00 (Mar'22) |
|
Detail Report
Graph / Photo |
||||
67 | Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. |
28/06/2019
22/06/2020 31/10/2023 |
2806.33 530.60 (Aug'23) |
0.00 (Aug'23) |
Roshan Real Estate Pvt Ltd. |
Work in progress (90% progress)
|
Detail Report
Graph / Photo |
|||
68 | C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi |
12/02/2022
09/11/2022 23/03/2022 |
2800.59 1635.84 (Sep'23) |
0.00 (Sep'23) |
SVK Infrastructures |
Initially site was encroached by local peoples. Encroachment the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Structural work completed for 64 ECR. Level 4 to 5 is in progress for remaining ECR. Plaster work, Tile Work, Stone work is in progress. MP hall work is in progress.
|
Detail Report
Graph / Photo |
|||
69 | Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. |
11/10/2022
05/09/2023 30/11/2023 |
2783.15 280.61 (Sep'23) |
83.00 % 0.00 (Sep'23) |
DND Infra Private Limit |
Structural work has been completed and tile work and finishing work under progress.
Structural work has been completed and tile work and finishing work under progress. |
Detail Report
Graph / Photo |
|||
70 | Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works |
|
2709.21 |
|
|
Detail Report
Graph / Photo |
||||
71 | SITC and CAMC of CCTV System in Delhi Govt. Schools. SH- Providing and Maintenance of Internet lease line Connection. |
17/08/2019
16/02/2020 30/09/2023 |
2691.32 |
|
Reliance Jio Infocomm |
Work is in progress and shall be completed along with main work of installation of CCTV camera in Delhi Government School.
|
Detail Report
Graph / Photo |
|||
72 | Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi |
23/08/2021
22/05/2022 30/09/2023 |
2373.12 1692.87 (Sep'23) |
0.00 (Sep'23) |
M/s PK Gupta & Co. |
Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work is in progress. Workshop Building-Steel Structural work has started. Hardstanding/CC Pavement: Earth Work has been completed. WMM layer work has just started. .Boundary Wall: The work of construction of new boundary wall of approx. 1 Km has almost been completed. Drainage Work: 75% of the drainage work has been completed.The structure for RWH and underground water, septic tank has been completed. |
Detail Report
Graph / Photo |
|||
73 | Uttam Nagar T Point Ram Mandir Marg Mall Rd C1 to C1A Block Rd under Sub Division WR12 Lala Ganesh Das Khatri Marg G-1 Block Vikaspuri Rd Rd No 235 Rd Adjacent to PVR under SubDivision WR13 80 Feet Chowkhandi Rd Shakti Mandir Marg Major Sudesh Marg |
|
2305.99 |
|
|
Detail Report
Graph / Photo |
||||
74 | Strengthening / Resurfacing of carriageway of Auchandi Border to Tatesar Village Road, Princess Road, Model Town II Road, Model Town III Road, Fire Station to Pump House Road, Kushal Cinema Road............... under North Road Division, Delhi |
|
2242.83 |
|
Work completed
null |
Detail Report
Graph / Photo |
||||
75 | Construction of Old Age Home Sector-4, Rohini, Delhi |
|
2240.23 |
|
|
Detail Report
Graph / Photo |
||||
76 | Improvement and strengthening of Rama Road from Zakhira Crossing to Patel Road including construction of outfall drain |
29/10/2012
28/08/2013 |
2197.33 308.84 (Mar'14) |
193.00 % (Mar'14) |
N.S.C. Project Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
77 | Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. |
24/05/2023
23/01/2024 23/01/2024 |
2107.18 100.00 (Aug'23) |
50.00 % 0.00 (Aug'23) |
Kundu Nirma |
Work just awarded. The site has been handed over to the agency on 24.05.2023, Preparation of the architectural drawing has been completed. Earthwork and excavation for the boundary wall has started.
|
Detail Report
Graph / Photo |
|||
78 | Widening and Stengthening of Road from Najafgarh Dhansa Road to Jhuljhuli Morh via Ghummanhera Village, Delhi. |
08/01/2015
07/11/2015 |
2057.50 |
|
Mahavir Parsad Gupta & Sons |
Work in Progress
|
Detail Report
Graph / Photo |
|||
79 | SITC of Modular Operation Theatre and MOT Integration System and MGPS |
05/06/2023
04/03/2034 04/03/2034 |
1896.47 |
2.00 % |
MDD Medical System (INDIA) Pvt. Ltd |
work in progress work in progress |
Detail Report
Graph / Photo |
|||
80 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. |
|
1887.50 |
|
12%
Demolition of existing Barrack completed. The plinth beam and column upto 2.50 m level for Left hand side portion completed. The excavation of footing and PCC completed for right hand side portion. |
Detail Report
Graph / Photo |
||||
81 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. |
24/03/2023
19/09/2023 30/09/2023 |
1874.71 3.99 (Jan'23) |
0.00 (Jan'23) |
Demolition of existing Barrack completed. The plinth beam and column upto 2.50 m level for Left hand side portion completed. The excavation of footing and PCC completed for right hand side portion.
|
Detail Report
Graph / Photo |
||||
82 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. |
31/05/2020
30/05/2021 30/11/2023 |
1874.70 1818.05 (Sep'23) |
0.00 (Sep'23) |
SSP Promoters and Builders Private Limited |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
|||
83 | STREET SCAPING OF 1000 METER OF NELSON MANDELA ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1870.18 |
|
|
Detail Report
Graph / Photo |
||||
84 | Street Scaping of 800 meter length of Ring Road, Bhairon Road T-Junction to Shantivan Crossing to make it Model Stretch of Street Scaping Project |
|
1859.21 |
|
|
Detail Report
Graph / Photo |
||||
85 | STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1848.01 947.24 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
86 | Construction of Residential Hostel at Chhattrasal Stadium, Model Town, Delhi. SH: C/o Hostel Building including External Development works, Internal Electrical Installation, External Lighting, lifts, fire fighting system, fire alarm with PA System, CCTV, Audio video system, HVAC works |
27/02/2023
26/07/2024 26/07/2024 |
1839.86 217.61 (Sep'23) |
40.00 % 0.00 (Sep'23) |
KALYAN CHANDRA GOYAL & CO. |
Work is in progress. Foundation work done. RCC in columns & plinth beam is under progress.
|
Detail Report
Graph / Photo |
|||
87 | Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project |
|
1814.36 1368.82 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
88 | Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project |
|
1814.36 0.10 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
89 | Balance Civil, Electrical and Horticulture Work as per revised concept |
|
1809.71 |
|
|
Detail Report
Graph / Photo |
||||
90 | Payment of monthly salaries to work charge staff including other payment relating to salary head like arrear, allowance ec. |
|
1800.00 |
|
|
Detail Report
Graph / Photo |
||||
91 | Payment of Electricity bills in respect of East Delhi Road Street Light. |
|
1800.00 9.76 (May'19) |
0.00 (May'19) |
|
Detail Report
Graph / Photo |
||||
92 | C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc |
01/04/2022
24/02/2023 31/12/2023 |
1798.93 43.99 (Sep'23) |
98.00 % 0.00 (Sep'23) |
K. L. ARORA & SON |
Casting of Parapet column over terrace in progress for 50% area and 1st floor column reinforcement work for 40% area in progress and balance 10% area could not strt due to space constraints. Slow progress due to space scarcity at site
Casting of Parapet column over terrace in progress for 50% area and 1st floor column reinforcement work for 40% area in progress and balance 10% area could not strt due to space constraints. Slow progress due to space scarcity at site |
Detail Report
Graph / Photo |
|||
93 | Strengthening of Dev Prakash Shastri Marg (ID: 1255) from T-Point Loha Mandi to Rattan Puri Chowk, Dr. K.S. Krishnan Marg (ID: 216) from Rattan Puri Chowk to Pusa Round about and Girdhari Lal Goswami Marg (ID: 2126) from T- Point Naraina to Shadipur Red Light under Sub Division-III, Division South West Road -1, PWD, New Delhi. |
|
1789.26 |
|
|
Detail Report
Graph / Photo |
||||
94 | Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi |
22/11/2021
17/10/2022 31/10/2023 |
1773.27 441.49 (Sep'23) |
100.00 % 0.00 (Sep'23) |
Harbel Singh & Sons |
'- Work in progress.
- Girder launched of 4 slabs out of 5
- 4 Nos of slab out of 5 casted.
|
Detail Report
Graph / Photo |
|||
95 | Construction of New Teaching Block in DIET at Daryaganj, New Delhi |
|
1764.30 109.73 (Jun'22) |
0.00 (Jun'22) |
|
Detail Report
Graph / Photo |
||||
96 | C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) |
29/12/2018
26/07/2019 30/09/2023 |
1743.19 4145.17 (Aug'23) |
100.00 % 99.00 % (Aug'23) |
AMAR CONSTRUCTION COMPANY |
Work in progress
|
Detail Report
Graph / Photo |
|||
97 | Construction of Skywalk FOB at Madhuban Chowk (on Outer Ring Road ) connecting Pitampura Metro Station and Rohini court, Delhi. |
|
1736.00 |
|
Estimate submitted for obtaining A/A & E/S from competent authority. The work was transferred from F-14 to F-12 vide CE (F) letter No. 23(83)/CE(F)/ 2023/3019 dated 15-06-2023.
Estimate submitted for obtaining A/A & E/S from competent authority. The work was transferred from F-14 to F-12 vide CE (F) letter No. 23(83)/CE(F)/ 2023/3019 dated 15-06-2023. |
Detail Report
Graph / Photo |
||||
98 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. |
24/03/2023
19/09/2023 30/09/2023 |
1729.05 147.72 (Sep'23) |
99.00 % 0.00 (Sep'23) |
SPS Infrabuild Pvt. Ltd. |
Demolition of existing Barrack completed. The plinth beam and column upto 2.50 m level for Left hand side portion completed. The excavation of footing and PCC completed for right hand side portion.
j |
Detail Report
Graph / Photo |
|||
99 | Strengthening of road from Western Yamuna Canal to Bawana under Sub-Division NR-15, North Roads Division, PWD, Delhi. |
|
1715.38 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
100 | Strengthening of road from Western Yamuna Canal to Bawana under Sub-Division NR-15, North Roads Division, PWD, Delhi(Second Call) |
|
1715.38 |
|
Work started
null |
Detail Report
Graph / Photo |
||||
101 | Remodelling and Upgradation of existing Blocks for Expantion of Government Hospitals situated in North West District Delhi.S.H. :- Construction of Multi Level Car Parking,Mortuary,ESS for Sanjay Gandhi Memorial Hospital,Mangolpuri,Delhi, |
|
1700.00 |
|
work
|
Detail Report
Graph / Photo |
||||
102 | Repair and Rehabilitation of ISBT Flyover (Yudhister Setu), Kashmere Gate, Delhi. (SH:Repair and Rehabilitation work). |
27/11/2021
26/11/2022 31/12/2023 |
1677.86 95.81 (Sep'23) |
86.00 % 0.00 (Sep'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
103 | STREET SCAPING OF 700 METER LENGTH OF K.N. KATJU MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1644.08 |
|
|
Detail Report
Graph / Photo |
||||
104 | Construction of Hostel for College Going Blind Students (Boys) at Sewa Kutir, Kingsway Camp, Delhi. |
|
1573.00 |
|
|
Detail Report
Graph / Photo |
||||
105 | C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. |
27/03/2023
19/02/2024 31/03/2024 |
1554.26 396.01 (Aug'23) |
49.00 % 0.00 (Aug'23) |
SWASTIC CONSTRUCTION CO |
2nd & 3rd Floor beam in progress and brick work for ground floor level is started. The LGSF work joint taken up.
2nd & 3rd Floor beam in progress and brick work for ground floor level is started. The LGSF work joint taken up. |
Detail Report
Graph / Photo |
|||
106 | C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc |
26/03/2022
19/02/2023 31/12/2023 |
1553.88 9.58 (Sep'23) |
100.00 % 0.00 (Sep'23) |
K L Arora & Son |
Tower A - Structural work completed except third floor above toilet block which is under progress and finishing work under progress incompleted structural portion.
MP hall - hall puff panel completed and finishing work under progress.
DIET block- RCC slab completed of half building portion and structural work of remaining portion under progress.
Tower A - Structural work completed except third floor above toilet block which is under progress and finishing work under progress incompleted structural portion. MP hall - hall puff panel completed and finishing work under progress. DIET block- RCC slab completed of half building portion and structural work of remaining portion under progress. |
Detail Report
Graph / Photo |
|||
107 | Construction of 66KV GIS Sub station at IGH Dwarka |
|
1549.73 984.49 (Sep'23) |
0.00 (Sep'23) |
|
Detail Report
Graph / Photo |
||||
108 | C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi |
12/03/2022
06/12/2022 23/03/2022 |
1542.27 836.19 (Aug'23) |
0.00 (Aug'23) |
The Krishna Construction Co. |
Initially some delay in start of work due to revision of layout and land apportioning between the new school and existing school. Layout plan was finalised by client department on 15.07.2022 and now Structure work completed. Tile work, Plaster work, Wall putty, Granite work, Stone work, Sanitary work is in Progress.
|
Detail Report
Graph / Photo |
|||
109 | Construction of New Academic Block (G+3) at DIET Keshavpuram, Delhi |
|
1541.76 |
|
|
Detail Report
Graph / Photo |
||||
110 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1524.43 |
|
|
Detail Report
Graph / Photo |
||||
111 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1524.43 1488.08 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
112 | Interior, furniture and auditorium Civil and electrical work |
|
1512.30 |
|
|
Detail Report
Graph / Photo |
||||
113 | C/o Cluster Bus Depot at village Gadaipur, District South, Delhi. SH: Civil works and Electrical works. |
24/05/2023
23/01/2024 23/01/2024 |
1500.30 0.00 (Jun'23) |
50.00 % 5.00 % (Jun'23) |
Kundu Nirman |
Work just awarded. The site has been handed over to the agency on 30.05.2023. The architectural drawing has been finalised..
|
Detail Report
Graph / Photo |
|||
114 | Strengthening of Vandematram Marg from Dhaula Kuan to Dayal Chowk and Shanker Road from Pusa Chowk to Shanker Chowk under PWD Division South West Road-1, Sub Division-IV New Delhi. (Road ID:212 and ID :213). |
|
1494.67 200.00 (Apr'23) |
0.00 (Apr'23) |
|
Detail Report
Graph / Photo |
||||
115 | Strengthening of G.T. Road (Shahdara Flyover to Dharampura T-point & service lane ) under sub-division M-2111 |
|
1491.26 |
|
Preliminary Estimate R.I.O. from Circle office vide letter no. 23(Road)/SE Shah./2980 dated 11.07.2019
Letter written to CRRI vide No. 23(QA)/ 4993 dated 16.10.2019 for milling method. Quotation/ Invoice received from CRRI vide letter No. CRRI/FBD/PWD/Shahdara/857 dated 31.10.2019 for Rs.1770000. Fresh estimate to be prepared after receiving of report from CRRI.
|
Detail Report
Graph / Photo |
||||
116 | Strengthening of Sri Aurobindo Marg (ID - 96), Ch. Harsukh Marg (ID - 19), and Ch. Jhandu Singh Marg (ID - 13) by cold milling and recycling process under SubDivision-II of Division South Road-II PWD, New Delhi during 2022-23. |
19/06/2023
16/09/2023 16/09/2023 |
1489.16 |
99.00 % |
SBG INFRACON PRIVATE LIMITED |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
117 | STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT. |
|
1480.89 |
|
|
Detail Report
Graph / Photo |
||||
118 | STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1480.89 4362.04 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
119 | C/o 64 Nos. Additional SPS Class Rooms in Existing Premises GGSSS (School ID - 1516030) Prem Nagar New Delhi. |
|
1472.47 |
|
Modified Preliminary estimate sent to CE (Projects) on dated 12.04.2023.
Null |
Detail Report
Graph / Photo |
||||
120 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 |
01/05/2022
30/04/2024 30/04/2024 |
1462.16 393.91 (Sep'23) |
68.00 % 0.00 (Sep'23) |
work in porgress
|
Detail Report
Graph / Photo |
||||
121 | Interior, furniture and auditorium Civil and electrical work (SW SITC of Audio visual system for Auditorium , Conference Room etc.) |
|
1445.84 5.17 (Mar'22) |
0.00 (Mar'22) |
|
Detail Report
Graph / Photo |
||||
122 | Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W |
09/03/2023
01/02/2024 30/04/2024 |
1442.22 |
|
Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site.
Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site. |
Detail Report
Graph / Photo |
||||
123 | STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1379.62 |
|
|
Detail Report
Graph / Photo |
||||
124 | Operation & Maintenance of EI & Fans, HVAC, Sub Stations, DG Sets, UPS, Fire Fighting System, Fire Alarm System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 |
27/05/2022
26/05/2024 26/05/2024 |
1369.68 367.72 (Jul'23) |
0.00 (Jul'23) |
In Progress
|
Detail Report
Graph / Photo |
||||
125 | C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc |
02/04/2022
25/02/2023 30/11/2023 |
1359.28 129.39 (Sep'23) |
98.00 % 0.00 (Sep'23) |
K. L. ARORA & SON |
Structural work of block B&C nearly completed and block A part 2 completed and part 1 progress at 2nd floor.
Kota stone flooring in classrooms and corridors in progress along with plaster work.
Structural work of block B&C nearly completed and block A part 2 completed and part 1 progress at 2nd floor. Kota stone flooring in classrooms and corridors in progress along with plaster work. |
Detail Report
Graph / Photo |
|||
126 | Operation & Maintenance of EI & Fans, DG Sets, Fire Engine, HVAC Works, Fire Alarm System, Fire Fighting and Wet Riser System, Sub Station, Solar Water Heating System etc. for the year 2022-23 and 2023-24. |
26/05/2022
25/05/2024 25/05/2024 |
1350.14 102.55 (Mar'23) |
0.00 (Mar'23) |
In Progress
|
Detail Report
Graph / Photo |
||||
127 | Re-development of Chadini Chowk Road in between Lal Jain Mandir to Fateh Puri Mosque. |
12/10/2013
11/04/2014 |
1343.02 |
|
Satya Parkash & Bros. Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
128 | Strengthening/Reconstruction of Service Road of Rohtak Road (NH-10) from Metro Pillar No. 410 to 570 Mundka Industrial Area both sides (Actual length of One side 5.00 Km) under PWD, Maintenance Division West Road-2, New Delhi during 2022-23. |
|
1296.54 |
|
|
Detail Report
Graph / Photo |
||||
129 | Strengthening of S.A. Road under the jurisdiction of Division SER-2/21, New Delhi (Road ID: 946). |
14/04/2023
12/07/2023 12/07/2023 |
1291.28 122.16 (Aug'23) |
0.00 (Aug'23) |
MAHAVIR PRASAD GUPTA AND SONS |
12%
Work in Progress |
Detail Report
Graph / Photo |
|||
130 | Construction of New Academic Block (G+3) at Lakshmibai College, Ashok Vihar, Delhi |
|
1280.15 |
|
|
Detail Report
Graph / Photo |
||||
131 | Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) |
12/03/2022
04/02/2023 31/12/2023 |
1275.84 607.55 (Sep'23) |
0.00 (Sep'23) |
M/s SURENDRA KUMAR |
Work in progress
|
Detail Report
Graph / Photo |
|||
132 | Strengthening of roads from (i) Ramdev Chowk Narela to Singhu Border, NH44 (ii) Ramdev Chowk Narela to Piao Maniyari border (iii) Y-Section railway crossing to CRPF camp, under Sub-Division NR-13, PWD Division North Roads, Delhi |
|
1244.87 |
|
90% work completed
null |
Detail Report
Graph / Photo |
||||
133 | STREET SCAPING OF 800 METER LENGTH OF RING ROAD, BHAIRON ROAD T-JUNCTION TO SHANTIVAN CROSSING TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1226.77 537.67 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
134 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project |
|
1193.08 |
|
|
Detail Report
Graph / Photo |
||||
135 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping projec |
|
1193.08 5024.37 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
136 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project |
|
1193.08 |
|
|
Detail Report
Graph / Photo |
||||
137 | Construction of NGO's Mess Tahirpur, Dilshad Garden, Delhi. (SH: Civil work, Electrical work and Horticulture work) |
|
1162.30 0.50 (Nov'21) |
0.00 (Nov'21) |
|
Detail Report
Graph / Photo |
||||
138 | Widening of Mehrauli Mahipal pur Road from 4 lanes to 8 lanes and service road from Andheria More to Fortis Hospital.(SH- Balance work for available land from Chainage 700Mtr. to 2100mtr.) |
|
1157.23 |
|
|
Detail Report
Graph / Photo |
||||
139 | Construction & connectivity between Anand Vihar Bus Terminal & Road No. 56 and extension of existing entry & exit of ISBT Terminal over trunk drain No. 2 |
|
1143.47 |
|
Modified PE submitted to Circle Office vide letter No. 23(5)/679 Dated 05.03.2020
|
Detail Report
Graph / Photo |
||||
140 | Strengthening of various roads such as Najafgarh Road, Punjab Garden Road, Smt. Ginni Devi Road, Bhagwan Das Road, Hemwati Nandan Bahuguna Marg, road from Milan Cinema to H. No. 19/289 , Road from House no. H-1 to I-47 near Milan Cinema Karampura and Road from House HIL to bus terminal of 234, HIL Karampura, Lal Sai Mandir Marg D story, Pankaj Batra Marg under PWD Maintenance Division WR-2 / Sub Division WR-21, New Delhi during 2022-23. |
28/04/2023
27/08/2023 27/08/2023 |
1124.92 |
100.00 % |
MIA Construction Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
141 | STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1119.07 |
|
|
Detail Report
Graph / Photo |
||||
142 | Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi |
06/04/2022
05/04/2025 05/04/2025 |
1099.29 114.42 (Jul'23) |
46.00 % 0.00 (Jul'23) |
SIKKA ASSOCIATES REGD. |
5
|
Detail Report
Graph / Photo |
|||
143 | C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) |
18/04/2022
13/03/2023 31/10/2023 |
1090.67 780.45 (Sep'23) |
100.00 % 0.00 (Sep'23) |
K. L. ARORA & SON |
Block -A
Column of 3rd floor to Terrace in progress and shuttering is also in progress. And brick work and plaster work of lower floor in progress.
Block -B
GRC tile laying on external walls in progress and Kota stone flooring in classrooms completed. Tiles work in laboratory in progress and corridor also. Finishing work start soon
Block -A Column of 3rd floor to Terrace in progress and shuttering is also in progress. And brick work and plaster work of lower floor in progress. Block -B GRC tile laying on external walls in progress and Kota stone flooring in classrooms completed. Tiles work in laboratory in progress and corridor also. Finishing work start soon |
Detail Report
Graph / Photo |
|||
144 | Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi |
|
1080.14 |
|
Work is in progress null |
Detail Report
Graph / Photo |
||||
145 | Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi(Second Call) |
|
1080.14 |
|
Work is in progress null |
Detail Report
Graph / Photo |
||||
146 | Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi (Balance Work) |
|
1076.89 |
|
|
Detail Report
Graph / Photo |
||||
147 | Strengthening of Josip Broz Tito Marg (BRT Road) from Defence Colony Flyover to Chirag Delhi Flyover under PWD Sub-Division SER-11 of Division SER-1. (Road ID No. 1717). |
|
1069.49 730.17 (Jun'23) |
0.00 (Jun'23) |
|
Detail Report
Graph / Photo |
||||
148 | C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. |
09/03/2023
01/02/2024 30/04/2024 |
1058.78 92.37 (Sep'23) |
55.00 % 0.00 (Sep'23) |
AMOCON |
Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site.
Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site. |
Detail Report
Graph / Photo |
|||
149 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1041.75 |
|
|
Detail Report
Graph / Photo |
||||
150 | Operation & Maintenance of EI & Fans, HVAC, DG Sets & Sub Stations, Fire Alarm System, Fire Fighting and Wet Riser System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 |
26/05/2022
25/05/2024 25/05/2024 |
1031.52 270.36 (Jun'23) |
0.00 (Jun'23) |
In Progress
|
Detail Report
Graph / Photo |
||||
151 | Construction of Footpath, Improvement of drain widening, strengthening of road from Burari Morh RD 3000 to Amrit Vihar RD 4800 and construction of darin from RD 0.00 at ORR to RD 600 at Sahib Singh polyclinic. |
|
1015.30 |
|
|
Detail Report
Graph / Photo |
||||
152 | Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. |
|
988.53 |
|
|
Detail Report
Graph / Photo |
||||
153 | Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. |
|
988.53 |
|
|
Detail Report
Graph / Photo |
||||
154 | C/O OLD AGE HOME AT BG 6 PASCHIM VIHAR DELHI |
|
987.85 |
|
|
Detail Report
Graph / Photo |
||||
155 | Mechanised House Keeping and Security Services/Facility Management services (FMS) for Chandni Chowk Road and appurtenances/System installed from Lal Jain Mandir to Fatehpuri Mosque for the Period 2022-2023(1 Years) |
26/08/2022
25/08/2023 25/08/2023 |
983.09 556.14 (Jun'23) |
100.00 % 0.00 (Jun'23) |
Soni Management & Allied Services Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
156 | Providing Automated Housekeeping at Hon’ble CM residence & Bungalow of Delhi Council of Minister’s Delhi. |
|
981.35 88.56 (Jul'23) |
0.00 (Jul'23) |
|
Detail Report
Graph / Photo |
||||
157 | Repair and Rehabilitation of Shahdara Flyover Delhi. (SH: Construction of New Crash Barrier and Strengthening of edge beam after dismantling of old crash barrier) |
12/03/2023
11/11/2023 11/11/2023 |
971.06 20.98 (Aug'23) |
75.00 % 0.00 (Aug'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
158 | Providing services of various category of Outsourced staff in various office under Flyover Zone, PWD, New Delhi, New Delhi |
|
970.31 |
|
|
Detail Report
Graph / Photo |
||||
159 | Repair and Rehabilitation of 10 Nos. Bridges- Timarpur Crossing (2 nos.), Mall Road Crossing, Maurice Nagar (2 Nos.), Gurmandi (Vijay Nagar Crossing), GT Road Crossing near Shakti Nagar (2 Nos.) and Bharat Nagar (2 Nos.) over Najafgarh Drain, Delhi. |
|
964.90 |
|
|
Detail Report
Graph / Photo |
||||
160 | Strengthening of various roads under PWD Division North West Road-1 under Sub Division NWR-12 During 2022-23 |
|
954.00 |
|
work in progress
Nil |
Detail Report
Graph / Photo |
||||
161 | Strengthening of Nangloi-Najafgarh Road from Nilothi Mor to Airforce Bani Camp under WR-14, PWD New Delhi |
|
953.94 671.44 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
162 | Operation of E.I. and Fans, Pumps, Automatic Fire Fighting system, Fire Alarm system |
|
951.12 |
|
|
Detail Report
Graph / Photo |
||||
163 | Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Auyrved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24 |
|
950.40 43.91 (Dec'22) |
0.00 (Dec'22) |
|
Detail Report
Graph / Photo |
||||
164 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
|
940.18 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
165 | Improvement & strengthening of Road No. 63, Delhi (From Bhopura Border to loni Gol Chakkar except flyover). |
|
935.18 38.95 (Mar'22) |
0.00 (Mar'22) |
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
166 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi |
|
935.00 15.80 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
167 | Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi |
16/07/2022
16/01/2023 31/08/2023 |
926.03 |
|
Work in progress
NA |
Detail Report
Graph / Photo |
||||
168 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi.(Balance Work) |
|
919.83 939.93 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
169 | STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
910.96 508.81 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
170 | Running operation of lifts |
06/05/2021
05/05/2024 05/05/2024 |
909.76 85.36 (Aug'23) |
76.00 % 0.00 (Aug'23) |
Guruji Elevator |
|
Detail Report
Graph / Photo |
|||
171 | Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Ayurved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24 (Balance works). |
|
906.11 49.34 (Jun'23) |
0.00 (Jun'23) |
|
Detail Report
Graph / Photo |
||||
172 | Construction of Police Post at Bakkarwala |
|
900.00 147.82 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
173 | C/o 40 Nos. equivalent Additional SPS Class rooms, Libraries, Toilets & Labs etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at Sarvodaya Vidyalaya, Mansarover Garden New Delhi (School ID - 1516003) (Civil work & Electrical Work ) |
|
897.31 |
|
Work Awarded
|
Detail Report
Graph / Photo |
||||
174 | Strengthening of various roads under sub division NWR-24, Division NWR-2, SainikVihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW |
|
880.22 712.73 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
175 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24 |
14/05/2022
13/05/2024 13/05/2024 |
874.44 0.00 (Jul'23) |
68.00 % 54.00 % (Jul'23) |
Work is in progress.
nil |
Detail Report
Graph / Photo |
||||
176 | Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. (Civil and Electrical Work) |
|
871.75 |
|
|
Detail Report
Graph / Photo |
||||
177 | Strengthening of road at Dev Parkash Shastri Marg under PWD Sub Division-III, S.W.R-I, New Delhi |
|
871.07 |
|
|
Detail Report
Graph / Photo |
||||
178 | Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts RO Plant etc |
|
866.40 |
|
|
Detail Report
Graph / Photo |
||||
179 | Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) |
17/09/2022
15/12/2022 15/12/2022 |
861.04 653.41 (May'23) |
0.00 (May'23) |
Invalid |
|
Detail Report
Graph / Photo |
|||
180 | Repair and Rehabilitation of Gokul Puri Flyover Delhi. (SH: Replacement of Bearings and Expansion joint and repair of Bearing Pedestal). (Recall) |
07/10/2022
12/01/2023 31/12/2023 |
859.23 0.00 (Jun'23) |
77.00 % 20.00 % (Jun'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
181 | Construction of 66 feet Libaspur Gurudwara Road including providing street light fittings (SH- Civil and Electrical Work) |
|
849.98 |
|
Work is in progress null |
Detail Report
Graph / Photo |
||||
182 | Two fixed single court and one doubles court with movable wall and SITC of EI, VRF, CCTV, LAN System, Fire Fighting System, Fire Alarm System & Signage Board) (Civil and Electrical work. |
|
847.08 |
|
|
Detail Report
Graph / Photo |
||||
183 | Operation & Maintenance of EI & FANS, Sub Station & DG Set, HVAC Works , Firen Fighting and Wet Riser System, Fire Alarm System, Lifts, RO Plant etc. |
|
843.88 |
|
|
Detail Report
Graph / Photo |
||||
184 | Operation of lifts |
|
834.91 |
|
|
Detail Report
Graph / Photo |
||||
185 | Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc |
|
831.74 |
|
|
Detail Report
Graph / Photo |
||||
186 | C/o Pucca School Building at Mandawali Fazalpur (I.P Extn) Delhi. |
09/03/2012
08/06/2013 08/06/2013 |
827.32 935.50 (Apr'14) |
100.00 % (Apr'14) |
PNSC Infrastructure Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
187 | Construction of Police Post Sadiq Nagar, New Delhi during 2020-21 (SH: Civil and Electrical work). |
|
824.93 238.04 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
188 | Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). |
30/09/2022
29/03/2023 29/03/2023 |
818.33 711.49 (Jun'23) |
0.00 (Jun'23) |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
189 | Strengthening of various road under North Roads, Division, Sub-Division NR-14, Shaheed Captain Vikram Batra Chowk PWD, New Delhi. 1. Mam Chand Dhaniya Marg from Old GTK Road to Siraspur Village 2. ITI Road at Jahangirpuri from Main Road to Metro Apartment & K-Block from Metro Apartment to dividing road K-Block.3. C-D Park Road from Main Road Jahangirpuri to Kushal Cinema Road. 4. I-Block Road & JBlock Road from Main Road Jahangirpuri to G.T. Road at Jahangirpuri. |
|
804.85 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
190 | Strengthening of various roads of Pitampura area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23 |
|
802.14 |
|
work in progress
DJB work at Gopal mandir marg not completed |
Detail Report
Graph / Photo |
||||
191 | Police Post Rampura Golden Park |
|
798.00 148.18 (Jun'23) |
0.00 (Jun'23) |
|
Detail Report
Graph / Photo |
||||
192 | Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi |
|
793.37 |
|
|
Detail Report
Graph / Photo |
||||
193 | Comprehensive Maintenance ,Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical ,Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi |
|
793.37 |
|
|
Detail Report
Graph / Photo |
||||
194 | Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi |
|
793.37 137.52 (Jul'23) |
0.00 (Jul'23) |
|
Detail Report
Graph / Photo |
||||
195 | Strengthening of Road No. 235, Guru Virjanand Marg, Road between Jupiter Appt. to Priya Appt., Nalanda Appt. to Nightingale Appt., Navyug Appt. to IFC drain (Brotherhood Appt.), Road between Devdoot Appt. to Parmarth Appt., Road between Kirti Appt. to DAV school, Road between Lok Vihar Appt. (PWD Road) to F-block Market, Road Sunrise Appt. to DAV School, Road from F-234 to IFC drain (Over head tank) Vikaspuri, Road from ITICorner to Central School, Road starting from Oxford School to Airport Appt. and Road No. 236 at Vikaspuri under sub division WR-14, Division WR-1 |
|
790.08 638.21 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
196 | Anticarbonation painting with designing and theme painting work on Britannia flyover, Wazirpur Flyover and Shalimar Bagh Elevated Flyover on Ring Road and Elevated Flyover from Mukarba Chowk to Mangolpuri Flyover on Outer Ring Road. |
|
787.93 |
|
|
Detail Report
Graph / Photo |
||||
197 | Strengthening of Road No.40 (Vir Banda Bairagi Marg) from Zakhira Pump House to Metro Pillar No.100 under PWD Division North West Road-1 under Sub Division NWR-13 During 2023-24. |
|
774.14 |
|
|
Detail Report
Graph / Photo |
||||
198 | Addition Alternation in Residence of Honble Chief Minister at 6 Flag Road, Civil Lines, Delhi during 2020 21 (SH:Providing additional Accommodation Civil and Electrical works) |
|
761.07 2920.43 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
199 | Strengthening of Mall Road Extension from Azadpur H Point to Sanjay Enclave (GTK Depot) under Sub Division NR-12, North Roads Division, PWD, Delhi. |
|
760.48 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
200 | Operation & Maintenance of E.I, pumps, sub-station, DG Sets, firefighting & fire alarm system, HVAC & AC units & R.O. Plant etc |
24/05/2022
23/05/2024 23/05/2024 |
754.12 132.64 (Sep'23) |
68.00 % 0.00 (Sep'23) |
SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. |
|
Detail Report
Graph / Photo |
|||
201 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi |
14/07/2022
13/10/2022 13/10/2022 |
751.50 |
|
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
202 | Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 |
15/12/2021
14/06/2022 31/07/2023 |
747.65 274.83 (Mar'23) |
0.00 (Mar'23) |
Work In Progress. Site available in Parts.
|
Detail Report
Graph / Photo |
||||
203 | C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus. |
|
747.30 |
|
|
Detail Report
Graph / Photo |
||||
204 | Providing furniture in various schools for additional SPS class rooms under Zone West Delhi Education Zone 16 17 and other schools Priority-I |
|
744.08 |
|
GEEKEN SEATING COLLECTION PVT LTD |
work in progress
|
Detail Report
Graph / Photo |
|||
205 | Comprehensive Maintenance of Civil works relating Day to day Maintenance, Annual Repair, Special Repair and routine maintenance work etc. of Deep Chand Bandhu Hospital, Ashok Vihar, Phase-IV, Delhi, Babu Jagjivan Ram Hospital, Jahangirpuri, Delhi, Attar Sain Jain Eye Hospital, various dispensaries at Jahangirpuri, Delhi and Bhagwan Mahavir Hospital, Pitampura, Delhi during 2022-23 and 2023-24 |
06/06/2022
05/06/2024 05/06/2024 |
741.51 |
63.00 % |
Dilshad Khan |
Work in Progress Deep Chand Bandhu 55% Progress, For BJRM 57% Progress, For Bhagwan Mahavir 46% Progress
|
Detail Report
Graph / Photo |
|||
206 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 |
03/06/2022
02/06/2024 02/06/2024 |
721.25 351.65 (Aug'23) |
63.00 % 0.00 (Aug'23) |
AZFARUDDIN |
Work in progress.
|
Detail Report
Graph / Photo |
|||
207 | Strengthening of road of Bawana to Auchandi Border under Sub-Division NR-15, PWD Division North Roads, Delhi |
28/04/2022
24/10/2022 24/10/2022 |
718.31 863.97 (Apr'23) |
0.00 (Apr'23) |
Invalid |
work completed
null |
Detail Report
Graph / Photo |
|||
208 | Strengthening of various roads (SGH Road, Kalamandir Cinema Road, LP Road, B Block and G/F Block Road - Mangolpuri, H Block Road and G Block Road - Sultanpuri, Road No. A2 sector 1/2 - Rohini) having ROW<30 meter under sub division NWR-21, Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 and 2023-24. |
|
714.93 |
|
|
Detail Report
Graph / Photo |
||||
209 | Construction of Police Post Mianwali Nagar |
|
714.00 78.07 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
210 | Replacement of chillers installed at Delhi Secretariat Building |
|
700.00 |
|
|
Detail Report
Graph / Photo |
||||
211 | Construction of Police Post Paschimpuri (now Sayyad village at Nangloi) |
|
700.00 96.55 (Sep'23) |
0.00 (Sep'23) |
|
Detail Report
Graph / Photo |
||||
212 | Strengthening of various roads (Road No. 318, Road No. 319, Sir Chhotu Ram Ram Marg-A3 Road, N.S. Hardikar Marg-A1 Road) under Sub Division NW R-21, Division NW R-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. |
|
686.56 |
|
|
Detail Report
Graph / Photo |
||||
213 | Providing and installing factory made Customized Galvanized Steel Sheet Modular Kitchen Cabinets and civil work at ‘A, B, C & D’ block of Judges Quarters, District Court Residential Complex, Saket, New Delhi. |
|
684.19 |
|
|
Detail Report
Graph / Photo |
||||
214 | Comprehensive maintenance of Civil services at Deen Dayal Upadhyaya Hospital & Residential Complex, Hari Nagar, Janakpuri Superspeciality Hospital C2B Janakpuri New Delhi, Shree Dada Dev Matri avum Shishu Chikitsalya, Dabri and DG at various places, P.W.D (GNCTD), New Delhi for 2 years i.e. 2022-2023, 2023-24 |
27/05/2022
26/05/2024 26/05/2024 |
683.47 0.00 (Jul'23) |
68.00 % 60.00 % (Jul'23) |
Anand and Company |
Work in Progress |
Detail Report
Graph / Photo |
|||
215 | Re laying of World Athletics approved 400 Mtr. synthetic athletic track at Chhatrasal Stadium, Delhi |
26/03/2022
24/07/2022 24/07/2022 |
679.06 656.95 (Apr'23) |
0.00 (Apr'23) |
ADVANCED SPORT TECHNOLOGIES LLP |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
216 | Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi |
|
675.71 146.08 (Jul'23) |
0.00 (Jul'23) |
|
Detail Report
Graph / Photo |
||||
217 | Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi |
|
675.71 89.84 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
218 | Strengthening / Resurfacing of (1) Seemapuri Road from Road No. 64 to Road No. 62 (2) GTB Hospital Road from Red Light to Agrawal Sweet (3) CNG West Side road (4) GTB Hospital road from GT Road to Agrawal Sweets (5) G.T.B. Hospital Road from Road No. 64 to Road No. 68 (6) Captain Javed Ali Marg (7) Gandhi Nagar Main Market Road (8) Road No. 75B Ext. (Bhartendu Harish Chander Marg from Yamuna Sports Complex to Karkari More flyover (9) Vishwas Nagar Road (60’0” wide). |
28/02/2020
26/06/2020 31/03/2021 |
675.69 777.41 (Oct'22) |
0.00 (Oct'22) |
Pawan Kumar |
Work in progress
|
Detail Report
Graph / Photo |
|||
219 | Improvement of drainage system and C016-17/o sump well near 52 cusec drain at Mandoli Road, Shahdara Delhi. Agmt. No. 154/EE/2016-17 |
30/12/2016
29/10/2017 31/07/2020 |
671.15 127.12 (Aug'20) |
0.00 (Aug'20) |
Thruogh H/R on account of advance payment against 6th R/A bill Rs. 95 lac. Vide C.V. No. 61 Dated 31.03.2020
|
Detail Report
Graph / Photo |
||||
220 | Construction of Old Age Home including electrical work at BG-6, Paschim Vihar, Delhi. (Composite work). |
|
668.69 |
|
Work is held up for Architectural Plan & revised plan submitted to fire department for approval by SA |
Detail Report
Graph / Photo |
||||
221 | Repair and Rehabilitation of Vikas Marg Flyover & Ashram Chawk Flyover Delhi. (SH: Repair of Spalled and Honeycomb Concrete, RCC Jacketing of Piers, Carbon Fiber wrapping of Pier Cap, Replacement of Expansion joint, Repair of Bearing Pedestal and Maintenance of bearing) |
26/03/2023
25/09/2023 25/09/2023 |
666.76 0.00 (Jun'23) |
99.00 % 30.00 % (Jun'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
222 | Comprehensive Maintenance , Operation of Multi Level underground automated car parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi |
|
661.38 604.53 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
223 | Supplying, Installation, Testing and Commissioning of Audio Video System |
10/06/2022
07/10/2022 30/09/2023 |
660.62 359.78 (Mar'23) |
0.00 (Mar'23) |
Installation of Audio Video System and other accessories completed. Installation work of transmeter and receiver completed. Testing and commissioning yet to be done.
|
Detail Report
Graph / Photo |
||||
224 | Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. |
31/03/2022
28/07/2022 28/07/2022 |
657.45 352.61 (May'23) |
0.00 (May'23) |
K. L. ARORA & SON |
work is in progress
BSES HT Line shifting |
Detail Report
Graph / Photo |
|||
225 | Providing Automated Housekeeping at Honble CM Residence and Bungalow of Delhi Council of Ministers Delhi |
|
649.40 643.11 (Jun'23) |
0.00 (Jun'23) |
|
Detail Report
Graph / Photo |
||||
226 | ARMO Various Electrical and Mechanical services at District Court Rohini, Delhi. |
05/09/2023
04/09/2025 04/09/2025 |
646.46 5.60 (Sep'23) |
0.00 (Sep'23) |
Anand and Company |
|
Detail Report
Graph / Photo |
|||
227 | Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi |
28/04/2022
24/10/2022 24/10/2022 |
643.92 552.30 (Jun'23) |
0.00 (Jun'23) |
Kundu Nirma |
work is in progress null |
Detail Report
Graph / Photo |
|||
228 | Strengthening of roads from Nangli Poona to Mohan Adda, Khera Kalan Road, Safiabad Mor to Safiabad Border, Holambi Kalan Crossing to Bawana Narela Road via Metro Vihar, under Sub-Division NR-13 of North Road Division, PWD, Delhi |
20/03/2022
17/07/2022 17/07/2022 |
640.59 590.71 (Jul'23) |
0.00 (Jul'23) |
SATYA PARKASH AND BROS PVT LTD |
work is in progress null |
Detail Report
Graph / Photo |
|||
229 | Strengthening of DDU Marg, JLN Marg & NS Marg under Sub Division-2/Division SRDP-I dg. 2022-23 |
05/01/2023
19/02/2023 19/02/2023 |
638.88 |
|
ROAD TECH |
|
Detail Report
Graph / Photo |
|||
230 | Construction of Police Post Sector - 21 & 23 Rohini. |
|
634.43 |
|
|
Detail Report
Graph / Photo |
||||
231 | Remodelling of drain from PTS to IIT Both Side of Road on Sri Aurobindo Marg (ID -96) under Sub Division-II of Division South Road-II, New Delhi during 2022-23. (2nd Call). |
25/03/2023
24/07/2023 24/07/2023 |
631.30 |
|
Mangat Ram Gupta |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
232 | E & M works relating to day to day operation & maintenance, A/R & M/O Works & Special Repair Works |
26/05/2022
25/05/2024 25/05/2024 |
619.38 303.69 (Sep'23) |
68.00 % 0.00 (Sep'23) |
H. N. TRADERS & ENGINEERS |
Work in progress Work in progress |
Detail Report
Graph / Photo |
|||
233 | Providing services of Computer Operators MTS and Drivers etc |
16/05/2023
15/05/2024 15/05/2024 |
618.00 114.41 (Aug'23) |
0.00 (Aug'23) |
work in progress
work in progress |
Detail Report
Graph / Photo |
||||
234 | Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi |
20/03/2022
17/07/2022 17/07/2022 |
617.72 347.72 (Aug'23) |
0.00 (Aug'23) |
Sethi Construction |
work is in progress null |
Detail Report
Graph / Photo |
|||
235 | Civil and Electrical Work. |
05/03/2023
29/11/2023 29/11/2023 |
617.03 |
75.00 % |
CHANDRA CONSTRUCTION COMPANY |
|
Detail Report
Graph / Photo |
|||
236 | Strengthening of Road No. 56 i.c Service Road from Gazipur Grade Separator to Apsara Border and its subsequent maintenance for three years. |
27/11/2021
26/03/2022 26/03/2022 |
615.26 670.71 (Feb'23) |
0.00 (Feb'23) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
237 | Renovation and up gradation of 25 Nos class rooms of all the schools in GGSIP University, Sector-16C, Dwarka, New Delhi. |
14/09/2023
11/03/2024 11/03/2024 |
615.12 |
|
Naresh Kumar Aggarwal |
Technical bid opened on 04.08.2023.
|
Detail Report
Graph / Photo |
|||
238 | Making Building and Campus Barrier Free for accessibility of disabled persons CWDS. |
|
614.92 5.08 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
239 | Making Building and Campus Barrier Free for accessibility of disabled persons CWDS. |
|
614.92 |
|
|
Detail Report
Graph / Photo |
||||
240 | Repair and Rehabilitation of Tilak Nagar District Center Flyover, Tilak Nagar Near Metro Flyover & Punjabi Bagh Flyover (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Repair of Bearing Pedestal, Replacement of Elastromeric Bearings, Maintenance of POT-PTFE Bearing and Installation of Height Barrier) |
26/05/2023
25/01/2024 25/01/2024 |
612.17 |
50.00 % |
The agency has not mobilized at the site till date. The correspondence regarding the same has also been done. However, it was conveyed that they will start the work at the earliest.
The agency has not mobilized at the site till date. The correspondence regarding the same has also been done. However, it was conveyed that they will start the work at the earliest. |
Detail Report
Graph / Photo |
||||
241 | Construction of RCC drain from NH-24 Ghazipur Dairy Farm to Kondli Bridge Shamshan Ghat Road |
|
609.62 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
242 | Comprehensive routine maintenance and operation of EI and Fans compound lights High Masts, Lifts, pumps, Fire Fighting System, AFA and PA system, HVAC plant, RO Plant and water softening plant, water coolers and substation DG sets at District Court Dwarka New Delhi |
26/07/2022
25/07/2024 25/07/2024 |
600.77 171.65 (Sep'23) |
59.00 % 0.00 (Sep'23) |
Swastik Electrotech Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
243 | Upgradation of one staff room, each at 951 School under Delhi Govt. SH 123 Nos. of staff rooms under West Maintenance Circle. |
|
593.40 156.62 (Oct'22) |
0.00 (Oct'22) |
|
Detail Report
Graph / Photo |
||||
244 | Supply, Installation, Testing and Commissioning of CCTV System at NSUT, Sector 3, Dwarka, Delhi |
02/03/2022
01/07/2022 30/09/2023 |
591.39 456.64 (Sep'23) |
0.00 (Sep'23) |
Final testing in progress.
|
Detail Report
Graph / Photo |
||||
245 | Structural Work. |
21/02/2012
20/10/2012 30/11/2012 |
588.19 |
|
Rama Const. Co. |
|
Detail Report
Graph / Photo |
|||
246 | Strengthening of various roads of Sector-11 & Rama Road under sub division NWR-22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 |
|
587.47 317.69 (Apr'23) |
0.00 (Apr'23) |
|
Detail Report
Graph / Photo |
||||
247 | Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB |
25/09/2022
24/01/2023 24/01/2023 |
583.83 |
|
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
248 | Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi |
23/11/2021
21/01/2022 21/01/2022 |
581.89 320.63 (Mar'23) |
0.00 (Mar'23) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
249 | Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work |
28/01/2022
27/12/2022 31/08/2023 |
579.95 360.97 (May'23) |
0.00 (May'23) |
Invalid |
Work is in progress.
|
Detail Report
Graph / Photo |
|||
250 | Strengthening of Ring Road from I.P. Flyover to Raj Ghat Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi during 2022-23. |
02/06/2023
01/08/2023 01/08/2023 |
579.40 85.00 (Aug'23) |
100.00 % 0.00 (Aug'23) |
MAHAVIR PRASAD GUPTA AND SONS |
Work in Progress.
|
Detail Report
Graph / Photo |
|||
251 | Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh |
25/09/2022
24/01/2023 24/01/2023 |
578.76 467.80 (May'23) |
0.00 (May'23) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
252 | Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 |
16/10/2019
12/02/2020 12/02/2020 |
567.80 236.37 (Jul'20) |
0.00 (Jul'20) |
Pawan Kumar |
WORK IN PROGRESS
WORK IN PROGRESS |
Detail Report
Graph / Photo |
|||
253 | Repair and Rehabilitation of Africa Avenue Flyover, Moti Bagh Flyover, Savitri Cinema & IIT Flyover, Delhi. (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Maintenance of bearing and Installation of Height Barrier & Seismic Arrester) |
26/05/2023
25/01/2024 25/01/2024 |
566.13 |
50.00 % |
Work in Progress
null |
Detail Report
Graph / Photo |
||||
254 | C/o RCC drain and side berm at Burari Road from Swaroop Nagar to Bhalswa. |
|
565.27 |
|
100%
null |
Detail Report
Graph / Photo |
||||
255 | Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. |
17/03/2023
12/09/2023 12/09/2023 |
564.26 |
99.00 % |
Rajan Builders |
|
Detail Report
Graph / Photo |
|||
256 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
|
559.69 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
257 | Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. |
26/01/2023
25/05/2023 25/05/2023 |
554.25 50.00 (Jun'23) |
0.00 (Jun'23) |
Kundu Nirman |
|
Detail Report
Graph / Photo |
|||
258 | C/o Police Post at Preet Vihar, Delhi. |
|
552.89 0.78 (Mar'22) |
0.00 (Mar'22) |
|
Detail Report
Graph / Photo |
||||
259 | Renovation / Upgradation of one room for Teachers Training at 5 nos. school under NWB-2, Delhi. SH: Civil Work |
|
552.73 |
|
|
Detail Report
Graph / Photo |
||||
260 | Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW |
27/02/2022
26/06/2022 26/06/2022 |
548.07 550.78 (Feb'23) |
0.00 (Feb'23) |
RK Brothers |
|
Detail Report
Graph / Photo |
|||
261 | Strengthening of Kalyanvas road and LBS Hospital road and improvement of footpath and adjoing area. |
|
545.60 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
262 | Providing services of Maintenance vehicle with labour & T&P etc. for all Sub-Division for two year |
|
542.39 |
|
|
Detail Report
Graph / Photo |
||||
263 | Improvement and maintenance of horticulture and landscaping work on central verges and sides of footpath etc on Ring Road from Bhairo T Point toHanuman Setu Ring Road Bypass IP Marg BSZ Marg JLN Marg Vikas Marg Pusta Road MB Road under East Zone PWD |
|
540.48 |
|
|
Detail Report
Graph / Photo |
||||
264 | RMO Electrical and Mechanical services installed at Delhi Sachivalya, New Delhi. (SH Maintenance and Operation of E and M services at Delhi Sachivalaya, New Delhi) |
13/07/2017
12/07/2020 |
540.00 |
|
Swastik Electrotech Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
265 | Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. |
02/11/2018
01/11/2019 01/11/2019 |
539.98 214.77 (Sep'19) |
0.00 (Sep'19) |
Work in progress
No |
Detail Report
Graph / Photo |
||||
266 | SITC of structure cabling and CCTV System at District Court Rohini, Delhi |
|
538.56 |
|
|
Detail Report
Graph / Photo |
||||
267 | Improvement of footpath & Strengthening of road from Chandgi Ram Akhara Red Light to Timarpur Red Light Crossing under Sub Division-4,C&ND-R, New Delhi dg 2023-24. |
10/06/2023
09/08/2023 09/08/2023 |
536.55 |
100.00 % |
Sethi Construction |
Work in Progress.
|
Detail Report
Graph / Photo |
|||
268 | Strengthening of Anuvrat Marg (ID-1198) through cold milling and recycling process under Sub-Division-3 of Division South Road-2 PWD, New Delhi. |
19/04/2023
18/08/2023 18/08/2023 |
536.44 |
100.00 % |
R K Brothers & Company |
Work in progress.
( Delayed due to unexpected rain in May and traffic police permission also received on dated 25.05.2023.)
Work in progress. ( Delayed due to unexpected rain in May and traffic police permission also received on dated 25.05.2023.) |
Detail Report
Graph / Photo |
|||
269 | Construction of Police Post at Sanjay Gandhi Transport Nagar, Delhi. |
|
536.00 |
|
.
|
Detail Report
Graph / Photo |
||||
270 | Civil work comprehensive maintenance of Shanker Road and Vandematram Marg including carriageway, footpaths, central verge, Service road etc within the right... |
|
535.97 |
|
|
Detail Report
Graph / Photo |
||||
271 | Renovation / construction works at Rajiv Gandhi Stadium, Bawana |
07/07/2022
04/11/2022 04/11/2022 |
535.01 |
|
M/s Vinod Kumar & Company |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
272 | Providing services of Maintenance vehicle with labour and T and P etc for Division NW R 1 for two year |
|
533.23 42.86 (Apr'23) |
0.00 (Apr'23) |
|
Detail Report
Graph / Photo |
||||
273 | CIVIL Works - Comprehensive maintenance of various roads i/c carriageway, footpaths, central verge within right of way, mechanised desilting of drains etc and other mi |
|
533.12 |
|
|
Detail Report
Graph / Photo |
||||
274 | Widening of carriageway including shifting of central verge and footpath of Outer Ring Road from Majnu ka Tila Red Light to Wazirabad Flyover (Under 77 corridor improvement plan) in Division C&ND-R New Delhi dg. 2022-23 |
08/11/2022
07/03/2023 31/08/2023 |
532.40 |
|
AMOCON |
Work in Progress.
|
Detail Report
Graph / Photo |
|||
275 | Resurfacing of roads from (i) Shahpur Garhi Turn to Old GTK road Alipur, (ii) Shubhash Chowk to Palla Village via Bakhtawarpur, (iii) Holambi Khurd Crossing to Shahpur Garhi turn, (iv) New GTK Road to Old GTK Road (via Shani Mandir), (v) New GTK Road to Old GTK Road (via PHC Alipur) under Sub-Division NR13, PWD North Roads Division, Delhi. |
20/03/2022
17/07/2022 17/07/2022 |
526.50 659.38 (Apr'23) |
0.00 (Apr'23) |
SATYA PARKASH AND BROS PVT LTD |
work completed
null |
Detail Report
Graph / Photo |
|||
276 | Strengthening of Main Burari Road from BurariMorh to Outer Ring Road and Outer Ring Road to upto Bengali Colony Culvert under jurisdiction of Sub Division-1, C&ND-Road Division Delhi. |
|
525.02 |
|
|
Detail Report
Graph / Photo |
||||
277 | Improvement and reconstruction of footpath on various roads (Mathura Road, Bhairon Marg and Ring Road under Division M-321, Delhi on urgent basis in view of G-20 SUMMIT 2023. |
12/02/2023
14/04/2023 14/04/2023 |
518.84 |
|
In-progress
|
Detail Report
Graph / Photo |
||||
278 | Strengthening/Raising of Road to prevent Water Logging on the Road Deenpur to Kachha Talab and Tazpur mod to police check post at goyala deenpur Road (ID 1168) under Sub Division-V, South West Road-II, PWD New Delhi. |
28/03/2023
25/06/2023 25/06/2023 |
517.09 250.00 (Jul'23) |
0.00 (Jul'23) |
Mahavir Prasad Gupta & Sons |
|
Detail Report
Graph / Photo |
|||
279 | Strengthening of various roads of Sector-3,5,6 & 7 under sub division NWR22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 |
|
513.31 449.62 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
280 | Providing services of 11 Nos. maintenance vehicles for regular use with required labour and T&P for Sub Division NR-11, NR-13, NR14 & NR-15 under North Roads Division. |
|
501.02 |
|
30%
null |
Detail Report
Graph / Photo |
||||
281 | Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi. |
|
500.66 |
|
|
Detail Report
Graph / Photo |
||||
282 | Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi . |
|
500.66 0.20 (Jul'22) |
0.00 (Jul'22) |
|
Detail Report
Graph / Photo |
||||
283 | C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus. |
14/08/2023
09/05/2024 09/05/2024 |
498.97 |
11.00 % |
Satish Chand RaJesh Kumar Pvt. Ltd. |
barricading completed, survey done , drawing work in progress
in progress |
Detail Report
Graph / Photo |
|||
284 | Strengthening of Mehrauli-Mahipalpur Bypass Road (Road Id: 2140) from NH-8 to CPWD Flyover. |
|
492.92 |
|
|
Detail Report
Graph / Photo |
||||
285 | Maintenance and Operation of various Electrical Installations. |
|
491.77 |
|
|
Detail Report
Graph / Photo |
||||
286 | Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. |
21/03/2020
20/09/2020 20/09/2020 |
489.85 255.38 (Nov'22) |
0.00 (Nov'22) |
S S Chauhan & Sons |
Work in Progress.
Work in Progress. |
Detail Report
Graph / Photo |
|||
287 | Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II |
21/03/2020
20/09/2020 20/09/2020 |
489.30 335.56 (Nov'22) |
0.00 (Nov'22) |
S S Chauhan & Sons |
Work in Progress.
Work in Progress. |
Detail Report
Graph / Photo |
|||
288 | Construction of Police Post Sawada Ghevra B Block Colony Delhi |
|
487.01 |
|
|
Detail Report
Graph / Photo |
||||
289 | Running and Maintenance of lifts installed in residential and non-residential buildings at GTB Hospital complex, Shahdara, Delhi Sub Head Running operation of lifts |
17/01/2019
16/01/2021 16/01/2021 |
485.43 66.36 (Sep'23) |
0.00 (Sep'23) |
Guruji Elevator |
Work in progress 3RD RA 40220380
|
Detail Report
Graph / Photo |
|||
290 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
06/08/2022
03/12/2022 03/12/2022 |
484.07 232.87 (May'23) |
0.00 (May'23) |
Invalid |
work is in progress null |
Detail Report
Graph / Photo |
|||
291 | Nazafgarh Road to A-71, Rajauri Garden, A-31 Rajauri Garden, 20-Block Tilak Vihar Road, Radhaswami Satsang Marg and Tilak Nagar Main Market Road under PWD Division WR-1, New Delhi. |
|
481.51 |
|
|
Detail Report
Graph / Photo |
||||
292 | Resurfacing of various roads under PWD North West Road-2 Division during 2016-17. |
|
477.75 |
|
|
Detail Report
Graph / Photo |
||||
293 | Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24 (Civil and Electrical Work). |
|
477.50 |
|
|
Detail Report
Graph / Photo |
||||
294 | (1) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- II, Najafgarh, for clearing storm water drain & dewatering of PWD Roads of South West Delhi. (2) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- III, R K Puram, for clearing storm water drain & dewatering of PWD Roads of South West Delhi. |
|
475.35 76.08 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
295 | Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi |
|
472.59 |
|
|
Detail Report
Graph / Photo |
||||
296 | Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi |
|
472.59 417.19 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
297 | Civil & Electrical Works. |
|
471.61 |
|
|
Detail Report
Graph / Photo |
||||
298 | Construction of Foot Over Bridge with staircase and lift for padestrian at Rao Tula Ram Marg (Road ID-98) near Petrol Pump, New Delhi. |
|
465.11 |
|
|
Detail Report
Graph / Photo |
||||
299 | Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 |
02/04/2022
28/09/2022 28/09/2022 |
462.00 503.28 (May'23) |
0.00 (May'23) |
PRATAP SINGH |
|
Detail Report
Graph / Photo |
|||
300 | (A) Renovation of E.I. and Other Electrical accessories works on 5th, 6th and 7th Floor at DGHS (HQ) Building , Karkardooma, Delhi.(B) Upgradation of Fire Fighting System at Directorate Health Services, Karkardooma, Delhi.(C) Replacement of old damaged/unserviceable Fire Alarm System at Directorate Health Services, F-17, Karkardooma, Delhi.(D)Replacement of existing 1 No. 15 Passenger lift and 2 Nos 10 Passenger lifts at Directorate General of Health Services, Karkardooma, Delhi. |
|
460.54 |
|
|
Detail Report
Graph / Photo |
||||
301 | Providing and installation of informatory directional sign boards on various roads under Division NWR1 and NWR2 for DSEU Campus Ashok Vihar DSEU Campus Pitampura DSEU Campus Rohini DSEU |
|
460.45 |
|
|
Detail Report
Graph / Photo |
||||
302 | Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone |
|
460.45 |
|
|
Detail Report
Graph / Photo |
||||
303 | Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone |
|
460.45 |
|
work in progress.
All locations not decided by client Department. Hence full site not available. |
Detail Report
Graph / Photo |
||||
304 | Improvement of drainange system and C/o sump well near 52 cusec drain at Mandoli Road, Shahdara, Delhi. |
30/12/2016
29/10/2017 29/10/2017 |
459.74 |
|
Thruogh H/R on account of advance payment against 6th R/A bill Rs. 95 lac. Vide C.V. No. 61 Dated 31.03.2020
|
Detail Report
Graph / Photo |
||||
305 | Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc. |
04/06/2022
03/06/2024 03/06/2024 |
457.53 60.00 (Sep'23) |
63.00 % 0.00 (Sep'23) |
M/s Jain Electric Works |
|
Detail Report
Graph / Photo |
|||
306 | Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) |
29/03/2020
29/09/2020 31/03/2021 |
457.44 88.68 (Aug'23) |
0.00 (Aug'23) |
Work in progress null |
Detail Report
Graph / Photo |
||||
307 | Maintenance of E and M Services in Underpasses / RUB’s, Subways, FOB’s, Drains, Fountains and Lifts. 2. Maintenance of Street Lights. |
|
450.40 |
|
|
Detail Report
Graph / Photo |
||||
308 | Construction of approach roads for RUB (North side) along with ROB at Meet Nagar on Road No. 63. |
|
450.13 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
309 | SITC of structure cabling and CCTV System at District Court Rohini, Delhi |
06/03/2023
05/09/2023 05/09/2023 |
449.96 23.90 (Aug'23) |
99.00 % 0.00 (Aug'23) |
TIRUPATI CONSTRUCTION COMPANY |
First RA Bill Rs. 2390388/- dt. 08.08.2023
|
Detail Report
Graph / Photo |
|||
310 | Improvement of Karawal Nagar Road from Wazirabad Road (Near Bhajanpura Mazaar) to Dayalpur Chowk( Length of Road- 1.75Km) |
|
449.01 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
311 | Civil Works - Mechanised Sweeping and Cleaning of Roads including Carriageway, Footpaths, Central Verge, Service Roads etc. within the right of way, Mechanised Desilting |
|
448.15 |
|
|
Detail Report
Graph / Photo |
||||
312 | Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 |
05/11/2022
04/11/2024 04/11/2024 |
445.82 0.00 (Jul'23) |
42.00 % 40.00 % (Jul'23) |
work in progress, as per complaint received in sub division, the regular day to day compliance is made.
nil |
Detail Report
Graph / Photo |
||||
313 | Routine maintenance and operation of EI and fans Compound Lights High Masts Lifts Pumps Fire Fighting System AFA and PA system Sub Station and DG set and 4 x 400 TR Central HVAC Plant at Delhi Judicial Academy and National Law University at Sector 14 |
06/03/2023
05/03/2026 05/03/2026 |
443.54 76.31 (Jul'23) |
16.00 % 0.00 (Jul'23) |
GLOBAL ENTERPRISES |
|
Detail Report
Graph / Photo |
|||
314 | Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi. |
|
440.84 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
315 | Civil & Electrical Works. |
|
440.61 75.00 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
316 | Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division - 3 of Division C and ND - Roads, New Delhi |
|
437.49 |
|
|
Detail Report
Graph / Photo |
||||
317 | Construction of Old Age Home at Sarita Vihar, New Delhi including internal andexternal water supply sanitary installations, electric installations, Lift, SolarHeating System and fire Fighting (Civil + Electrical Works). |
|
436.76 |
|
|
Detail Report
Graph / Photo |
||||
318 | Balance Renovation and Misc. works of Main Academic, Administrative and Printing Blocks i/c Class Rooms &Laboratories, C/o Security Guards rooms and Toilet Water Proofing Treatment of existing building roofs of PIT, DSEU Campus, Pusa, New Delhi. |
03/07/2022
30/10/2022 30/10/2022 |
436.21 |
|
Work completed.
Non-availability of budget. |
Detail Report
Graph / Photo |
||||
319 | Providing additional staircase from Skywalk towards Moti Bagh, MS staircase for underground sump, provision for additional railing over skywalk, Covering of Skywalk with CGI sheet roofing & C/o wall with MS Grill towards Moti bagh at FOB Durgabai Deshmukh Metro Station, Ring Road New Delhi. |
29/06/2023
28/10/2023 28/10/2023 |
435.39 0.00 (Jun'23) |
74.00 % 2.00 % (Jun'23) |
Work in Progress
null |
Detail Report
Graph / Photo |
||||
320 | Operation & Comprehensive Maintenance of FOB Lifts,Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi. |
|
434.57 |
|
|
Detail Report
Graph / Photo |
||||
321 | Operation & Comprehensive Maintenance of FOB Lifts, Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi. |
|
434.57 |
|
|
Detail Report
Graph / Photo |
||||
322 | Construction of 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. Supplying, installation, testing and commissioning of 11 Nos. additional prefabricated Modular Operation Theatre) |
|
432.01 88.29 (Feb'23) |
0.00 (Feb'23) |
Work has been transferred to EE(E) Health Maintenance Elect Divn (N) |
Detail Report
Graph / Photo |
||||
323 | Remoulding of drain from Jahangirpuri Metro Station to G.T.K. Depot, Ramgarh Both Side Carriageway at Mall Road Extension under Sub Division NR-12. |
|
431.98 |
|
work is in progress null |
Detail Report
Graph / Photo |
||||
324 | Replacement of existing metal halide sports flood lights with energy efficient LED Sports Flood Light including all the allied works at Chhatrasal Stadium Model Town Delhi |
|
430.21 134.39 (Apr'23) |
0.00 (Apr'23) |
Updated . |
Detail Report
Graph / Photo |
||||
325 | Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road II PWD New Delhi |
|
429.94 |
|
WORK IN PROGRESS
WORK IN PROGRESS |
Detail Report
Graph / Photo |
||||
326 | Comprehensive improvement and maintenance of horticulture and landscaping work on soft areas of central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD. |
|
429.78 |
|
|
Detail Report
Graph / Photo |
||||
327 | Comprehensive maintenance of various roads under Sub-Division South East Road-13 |
|
425.32 14.60 (Jun'20) |
0.00 (Jun'20) |
|
Detail Report
Graph / Photo |
||||
328 | Routine/Comprehensive Maintenance & Operation of Electrical & Mechanical Services |
|
425.32 112.29 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
329 | Civil and Electrical work |
|
420.91 |
|
|
Detail Report
Graph / Photo |
||||
330 | Operation and comprehensive maintenance of FOB lifts and escalators and other electrical work at various FOBs and subways under AE E SD III R K Puram New Delhi |
|
419.48 4.64 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
331 | Street Scaping of Nelson Mandela Road, New Delhi. |
|
418.83 |
|
|
Detail Report
Graph / Photo |
||||
332 | EI work (Composite Work) |
19/01/2009
31/08/2012 31/08/2012 |
417.80 |
|
Bhart Eletricals (Associated of M/s ERA) |
00
... |
Detail Report
Graph / Photo |
|||
333 | EI work (Composite Work) |
19/01/2009
30/11/2013 30/11/2013 |
417.80 |
|
Bhart Eletricals (Associated of M/s ERA) |
00
.. |
Detail Report
Graph / Photo |
|||
334 | Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I. |
|
417.30 |
|
|
Detail Report
Graph / Photo |
||||
335 | Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I. |
|
417.30 |
|
|
Detail Report
Graph / Photo |
||||
336 | Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I. |
|
417.30 |
|
|
Detail Report
Graph / Photo |
||||
337 | Op. of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I |
|
417.30 |
|
|
Detail Report
Graph / Photo |
||||
338 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of Maharishi Valmiki Hospital Campus and DGD Dispensaries at Pooth Khurd Delhi, SRHC Hospital Complex and DGD Dispensaries at Narela Delhi during 2022-23 and 2023-24 |
15/05/2022
14/05/2024 14/05/2024 |
416.87 |
68.00 % |
Mahavir Parsad Gupta & Sons |
Maharishi Valmiki 73% progress and SRHC 64% Progress
|
Detail Report
Graph / Photo |
|||
339 | Strengthening of various roads (Ahinsha Marg sector-9, Rohini, Babosachowk to Tulsi Aptt., Ring road to Maheswari Aptt., ORR to Road No. B-5 sector-14, Rohini, Internal road of sector-9, Rohini, Pkt.-14 to Pkt.C-1, Pkt.-10 to Pkt.D-4, sector-20, Rohini, Pkt. 8 to Pkt. 9, Pkt. B-2 to Park, Pkt. 13 to pkt. 9, Pkt. 5 to Pkt. 6 sector-21, Rohini) having ROW < 30 mtr. under Sub Division NWR-23, PWD Division NWR-2, Sainik Vihar Delhi under PWD North Zone by cold milling method with recycled material, dg. 2022-23 & 2023-24. |
16/08/2023
15/02/2024 15/02/2024 |
415.97 |
16.00 % |
R K Brothers & Company |
|
Detail Report
Graph / Photo |
|||
340 | Construction of Building for Old Age Home at Geeta Colony, New Delhi. |
|
413.84 |
|
|
Detail Report
Graph / Photo |
||||
341 | Strengthening of Ring Road from Shantivan to Hanuman Setu under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. |
02/06/2023
01/08/2023 01/08/2023 |
413.71 |
100.00 % |
MAHAVIR PRASAD GUPTA AND SONS |
Work in progress
|
Detail Report
Graph / Photo |
|||
342 | Construction of RCC drain in Narela Alipur road along the DDA land from Bhorgarh to Shahpur Garhi turn under Sub Division NR-13, North Roads Division,PWD, Delhi |
07/01/2022
05/07/2022 05/07/2022 |
412.34 111.83 (Jun'22) |
0.00 (Jun'22) |
R K Enterprises |
work is in progress null |
Detail Report
Graph / Photo |
|||
343 | Providing X-ray Baggage scanner, DFMD security equipment at entry/security check points at Delhi High Court, New Delhi. |
|
407.68 282.47 (Apr'23) |
0.00 (Apr'23) |
|
Detail Report
Graph / Photo |
||||
344 | Improvement/providing and fixing of MS railing in central verge from Peeragarhi Chowk to Rama Road Round About (Zakhira Flyover) under PWD Division West Road-2/ Sub Division WR-21 & WR-24, New Delhi during 2019-20 |
|
406.91 |
|
Estimate sent to Circle office for approval
|
Detail Report
Graph / Photo |
||||
345 | Repair and Rehabilitation Mukundpur and Karampura Flyover. SH: - (Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover.- (Recall) |
05/10/2022
04/04/2023 31/10/2023 |
406.38 0.00 (Jun'23) |
90.00 % 15.00 % (Jun'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
346 | AR MO to Various Residential Buildings Type III IV V and VI under Sub Division M 3231 at 16 Rajpur Road Delhi dg 2022 23 |
|
401.13 261.70 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
347 | Main Burari Road from Bengali Colony culvert to Burari Morh (LHS) on side only under Sub Division-1 of Division C&ND-Roads, New Delhi. |
|
400.00 |
|
|
Detail Report
Graph / Photo |
||||
348 | Civil and Electrical works |
|
398.73 |
|
|
Detail Report
Graph / Photo |
||||
349 | stopping vibration and noise |
26/02/2013
25/06/2013 31/05/2014 |
398.44 |
|
K.L. Arora & Son |
Sanctioned
|
Detail Report
Graph / Photo |
|||
350 | Providing remedial measures for stopping vibration and noise due to flyover to Outer Ring Road near Ber Sarai, Munirka and Vasant Vihar. |
26/02/2013
25/06/2013 31/05/2014 |
398.44 |
|
K.L. Arora & Son |
Sanctioned
Work Foreclosed |
Detail Report
Graph / Photo |
|||
351 | (1) SITC of Additional Surveillance CCTV System at different locations of Dwarka Court Complex at Sector10, Dwarka, New Delhi. (2) Up-gradation of existing analog CCTV Surveillance system to I P Base CCTV Surveillance System at District Court, Sector-10, Dwarka, New Delhi |
|
391.76 30.00 (Aug'23) |
0.00 (Aug'23) |
|
Detail Report
Graph / Photo |
||||
352 | Repair and Rehabilitation of ISBT Flyover (Yudhister Setu), Kashmere Gate, Delhi. (SH: Providing and Laying Bituminous concrete and Retro reflective road marking). |
26/01/2023
25/04/2023 30/07/2023 |
391.40 96.10 (Jul'23) |
0.00 (Jul'23) |
Work in Progress null |
Detail Report
Graph / Photo |
||||
353 | Construction of RCC drain and side berm at Burari Road from Swaroop Nagar to Bhalswa, Delhi. |
03/03/2023
30/07/2023 30/07/2023 |
389.94 175.50 (May'23) |
0.00 (May'23) |
AMIT BUILDCONE |
Work completed
null |
Detail Report
Graph / Photo |
|||
354 | Operation of lifts |
22/10/2022
21/10/2024 21/10/2024 |
389.63 81.17 (Jul'23) |
46.00 % 0.00 (Jul'23) |
Akash enterprises |
1st RA bill paid
Work in progress |
Detail Report
Graph / Photo |
|||
355 | Strengthening of MB Road (ID-390) Road through cold milling and recycling process under Sub-Division-1 of Division South Road-1 PWD, New Delhi. |
20/06/2023
19/08/2023 19/08/2023 |
388.26 |
100.00 % |
Pawan Kumar |
Work completed
Work completed |
Detail Report
Graph / Photo |
|||
356 | Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. |
16/10/2019
12/02/2020 |
388.15 0.84 (Apr'22) |
0.00 (Apr'22) |
Pawan Kumar |
UNDER TENDERING PROCESS
UNDER TENDERING PROCESS |
Detail Report
Graph / Photo |
|||
357 | Improvement and maintenance of horticulture and landscaping work on central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD for 36 months. |
|
387.36 |
|
|
Detail Report
Graph / Photo |
||||
358 | Replacement of outlived Sub station equipment installed atDepartment of Trade , Taxes, Vyapar Bhawan Building, I.P. Estate New Delhi |
|
387.07 |
|
|
Detail Report
Graph / Photo |
||||
359 | Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain |
25/09/2022
24/12/2022 24/12/2022 |
386.35 150.00 (Jun'23) |
0.00 (Jun'23) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
360 | C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) |
02/03/2022
26/11/2022 30/09/2023 |
385.86 |
98.00 % |
M/s. Satyam Construction |
Work is in progress
Work is in progress |
Detail Report
Graph / Photo |
|||
361 | SITC of Central Air conditioning Plant in upper 3.5 Three and Half stories including strengthening of sub station and provision of false ceiling of MCH Block 500 Bedded New Ward Block at G.T.B. Hospital Shahdara Delhi |
|
385.28 |
|
|
Detail Report
Graph / Photo |
||||
362 | Strengthening of Amar Shaheed Bismil Marg, Police Line road Parwana Road under Sub Division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW. |
20/08/2023
19/12/2023 19/12/2023 |
381.30 |
25.00 % |
SBG INFRACON PRIVATE LIMITED |
|
Detail Report
Graph / Photo |
|||
363 | Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi |
16/01/2020
15/10/2020 31/03/2021 |
379.24 40.81 (Apr'21) |
0.00 (Apr'21) |
Work in progress null |
Detail Report
Graph / Photo |
||||
364 | Civil works, Furniture works & Electrical works |
|
377.11 |
|
|
Detail Report
Graph / Photo |
||||
365 | Comprehensive repair of road footpath, drain, painting, Speed breakers, Patch repairs and other misc. repair works in SectionI & Section-II for 1 year |
|
376.63 147.49 (Apr'23) |
0.00 (Apr'23) |
|
Detail Report
Graph / Photo |
||||
366 | Comprehensive repair of road footpath, drain, painting, Speed breakers, patch repairs and other misc. repair works in SectionI & Section-II for 1 year |
|
376.63 |
|
|
Detail Report
Graph / Photo |
||||
367 | Construction of Kho-Kho ground, Synthetic Volley Ball Court, Synthetic Basket Ball Court, Change Room, Boundary Wall and Development works in the premises of Govt. CO-Ed Senior Secondary School, Jaffarpur Village (ID No.: 1822055), Najafgarh, New Delhi. |
|
376.56 |
|
Tender has been called on 01.08.2023 and opened on 16.08.2023
|
Detail Report
Graph / Photo |
||||
368 | Operation & Maintenance of E.I, pumps, substation, DG Sets, fire fighting & fire alarm system, HVAC & ductable AC system, lift, Cold Room & solar water heating system etc. |
10/05/2022
09/05/2024 09/05/2024 |
376.50 81.49 (Jul'23) |
68.00 % 0.00 (Jul'23) |
M/s Vivek Associates |
|
Detail Report
Graph / Photo |
|||
369 | (i) Civil work Comprehensive maintenance of Ring Road including carriageway, footpaths, central verge, service road etc. within the right of way, mechanised desilting |
|
375.34 |
|
|
Detail Report
Graph / Photo |
||||
370 | Providing of services of Security Guard ,security supervisor & security manager &Mechanized Housekeeping Services for Internal and External areas of Tis Hazari court Extension block in Delhi-110054. |
01/07/2023
31/12/2023 31/12/2023 |
373.04 60.00 (Sep'23) |
40.00 % 0.00 (Sep'23) |
SONI MANAGEMENT AND ALLIED SERVICES PVT. LTD. |
|
Detail Report
Graph / Photo |
|||
371 | Road Resurfacing of Savitri Cinema (Road ID-601) Road from Guru Ravi Dass Marg to Outer Ring Road under Sub Division SER-24. |
15/04/2023
14/06/2023 31/08/2023 |
372.52 |
100.00 % |
Kundu Nirman |
80%
Work in progress |
Detail Report
Graph / Photo |
|||
372 | Providing, running and maintaining truck mounted Anti Smog Gun on hire basis at various locations |
19/05/2022
18/05/2023 18/05/2023 |
372.34 1398.54 (Apr'23) |
0.00 (Apr'23) |
Invalid |
Work in progress
|
Detail Report
Graph / Photo |
|||
373 | Thermoplastic paint on various roads under Sub-Division R11, R-12, R-13 and 14. |
|
371.03 45.00 (May'23) |
0.00 (May'23) |
|
Detail Report
Graph / Photo |
||||
374 | Construction of RMCRoad From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22 |
|
369.30 |
|
|
Detail Report
Graph / Photo |
||||
375 | Construction of RMC Road From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22 |
|
369.30 |
|
|
Detail Report
Graph / Photo |
||||
376 | Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24 |
|
366.09 |
|
|
Detail Report
Graph / Photo |
||||
377 | Strengthening of Ring Road from Raj Ghat to Shanti Van Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. |
02/06/2023
01/08/2023 01/08/2023 |
364.49 |
100.00 % |
MAHAVIR PRASAD GUPTA AND SONS |
Work in progress
|
Detail Report
Graph / Photo |
|||
378 | Improvement of footpath, construction of crash barrier & toe wall at Road No.51(Arihant Marg) |
|
364.38 |
|
Work is in progress null |
Detail Report
Graph / Photo |
||||
379 | Desilting of road side storm water drain/ sewer line by Super Sucker Machine on Various roads, under SRD Project Division-I. |
|
363.94 |
|
|
Detail Report
Graph / Photo |
||||
380 | Major repair maintenance work i.e. outer plaster, chajjas of windows, balcony, damaged cemented water tank causing seepage, repair of staircase, road, blocked sewer line i/c strengthening, retrofitting works and misc. civil and Electrical works |
|
363.36 208.08 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
381 | Up-gradation of Analog Camera to IP CCTV Surveillance Systems at District Court Karkardooma Delhi. |
|
360.66 |
|
|
Detail Report
Graph / Photo |
||||
382 | Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21 |
|
359.74 1.30 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
383 | Re-Surfacing of various roads of Vasant Vihar Roads (Poorvi Marg (Road ID - 781), Paschimi Marg (Road ID - 782 ), Basant Marg 1 (Road ID - 778), Basant Marg 2 (Road ID - 779), Munirka Marg 1 and2 (Road ID - 783)) and Providing and Laying of Stone Ma |
|
359.35 |
|
|
Detail Report
Graph / Photo |
||||
384 | Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. |
06/09/2022
05/03/2023 05/03/2023 |
358.46 |
|
Fiberfill Engineer |
|
Detail Report
Graph / Photo |
|||
385 | Construction of Old Age Home at Sarita Vihar, New Delhi. |
|
358.09 9.95 (Jun'23) |
0.00 (Jun'23) |
Sanction of Building Plan is under process
|
Detail Report
Graph / Photo |
||||
386 | Strengthening of Timarpur Road (Chaudhary Fatah Singh Marg) from Mall Road to Wazirabad Crossing under Sub-Division-2 of Division C& ND-R. |
|
357.04 |
|
|
Detail Report
Graph / Photo |
||||
387 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
388 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021 22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
389 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
390 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
391 | Improvement and Strengthening of MB Road Khajuri Chowk to Sabhapur Village at City Side. |
|
353.93 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
392 | Civil & Electrical Work. |
30/03/2023
29/09/2023 29/09/2023 |
352.07 27.95 (Jul'23) |
99.00 % 10.00 % (Jul'23) |
Engineers India Construction Ltd. |
|
Detail Report
Graph / Photo |
|||
393 | C/o 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. SITC of Medical Gas Pipe Line System) |
|
350.95 28.21 (Oct'22) |
0.00 (Oct'22) |
Tender Awarded
|
Detail Report
Graph / Photo |
||||
394 | Strengthening of Roshnara Road from Pulbangash Metro Station to Malka Ganj Chowk under Sub-Division-2 of Division C& ND-R. |
|
350.85 |
|
|
Detail Report
Graph / Photo |
||||
395 | Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23 |
|
350.32 |
|
|
Detail Report
Graph / Photo |
||||
396 | Desilting of road side storm water drain/ sewer line by Super Sucker Machine on Various roads, under SRD Project Division-I.) Recall of Tender. |
26/03/2023
25/03/2024 25/03/2024 |
349.42 153.00 (Jun'23) |
49.00 % 0.00 (Jun'23) |
NITIN KUMAR SHARMA |
|
Detail Report
Graph / Photo |
|||
397 | Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24.(Civil and Electrical Work. 1st Recall) |
27/08/2023
22/02/2024 22/02/2024 |
348.05 |
16.00 % |
Mohd Aftab |
|
Detail Report
Graph / Photo |
|||
398 | Comprehensive maintenance of Civil works at Guru Gobind Singh Govt. Hospital, Raghubir Nagar, Delhi and Rao Tula Ram Memorial Govt. Hospital, Jaffarpur Kalan, Delhi P.W.D. (GNCTD), New Delhi for 2 years 2021-22, 2022-23. |
23/05/2022
21/05/2024 21/05/2024 |
343.73 45.00 (Aug'23) |
68.00 % 0.00 (Aug'23) |
Aliyan Constaruction Company |
Work is under progress.
|
Detail Report
Graph / Photo |
|||
399 | Comprehensive Maintenance and Operation of Trauma Block, New Ward Block, OT, Gynae, Old Ward Block, Doctors and Nurses Hospital and Residential Complex Lifts at DDU Hospital, Hari Nagar, New Delhi (SH Operation of Lifts) |
|
341.50 |
|
|
Detail Report
Graph / Photo |
||||
400 | Providing and fixing road signage boards on various roads Under Sub Division I,II,III,IV,V PWD SWR-I New Delhi. |
|
341.49 |
|
|
Detail Report
Graph / Photo |
||||
401 | C/o 17 Nos. additional SPS class rooms & 3 no. staircase i/c internal & external water supply sanitary installation electrical installations development of site fire fighting system at Govt. Sarvodaya Vidyalay, Badarpur, Khadar (School ID 1104418) in District North-East (Zone-4) Delhi |
|
340.93 |
|
sanction awaited null |
Detail Report
Graph / Photo |
||||
402 | Resurfacing of Ring Road under Division CBMD M-321, New Delhi. |
27/05/2023
26/06/2023 26/06/2023 |
339.88 |
|
M/s Chaudhary Construction Company Pvt. Ltd. |
In-progress
|
Detail Report
Graph / Photo |
|||
403 | Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) |
18/04/2022
14/10/2022 14/10/2022 |
339.47 221.93 (Mar'23) |
0.00 (Mar'23) |
Dilshad Khan |
|
Detail Report
Graph / Photo |
|||
404 | Construction of Foot Over Bridge with Staircase and lift for padestrians crossing near Mohammadpur Village at Africa Avenue Road, New Delhi during 2017-18 |
|
338.01 |
|
|
Detail Report
Graph / Photo |
||||
405 | Construction of RCC drains from Block-36 to Block-31 at Trilokpuri under Sub-Division East (Road)-III of Division East (Road)/M-212, Delhi. |
|
335.20 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
406 | Micro Surfacing on Outer Ring Road from Vikas Puri to Meera Bagh |
|
334.06 20.48 (Jun'22) |
0.00 (Jun'22) |
|
Detail Report
Graph / Photo |
||||
407 | PROVIDING, INSTALLATION, TESTING AND COMMISSIONING OF CENTRAL AC PLANT IN ADMINISTRATIVE BLOCK, DELHI HIGHT COURT, NEW DELHI |
|
332.99 |
|
|
Detail Report
Graph / Photo |
||||
408 | Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) |
19/03/2022
18/06/2022 30/09/2023 |
331.52 10.15 (May'23) |
0.00 (May'23) |
Satyam Construction Company |
45%
Work in Progress |
Detail Report
Graph / Photo |
|||
409 | Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). |
23/03/2019
22/09/2019 22/09/2019 |
329.84 160.77 (Jan'23) |
0.00 (Jan'23) |
S. P. CONSTRUCTION COMPANY |
Work in progress |
Detail Report
Graph / Photo |
|||
410 | Comprehensive Maintenance of RO Filtration Units in Ortho Block Hostels LNRDH Various Location in LNH |
02/01/2023
01/01/2026 01/01/2026 |
327.30 236.55 (Feb'23) |
21.00 % 0.00 (Feb'23) |
M/s Vivek Associates |
Work in progress Work in progress |
Detail Report
Graph / Photo |
|||
411 | EOR to PTC/PTS at Jharoda Kalan NEW DELHI |
|
325.15 |
|
|
Detail Report
Graph / Photo |
||||
412 | Civil & Electrical Works. |
30/03/2023
29/07/2023 29/07/2023 |
324.30 |
|
Mohd Ahson Infra Private Limited |
|
Detail Report
Graph / Photo |
|||
413 | Comprehensive Maintenance of RO Filtration Units in Ward Block , Gynae Block , OPD Block , Emergency and OT Block in LNH |
21/10/2022
20/10/2025 20/10/2025 |
322.38 |
30.00 % |
M/s Vivek Associates |
Work in progress Work in progress |
Detail Report
Graph / Photo |
|||
414 | C/o Foot Over Bridge at Block-D, Okhla Phase-I on Shri Maa Anandmayee Marg, New Delhi (Road-ID-946) including EI and Lift |
19/03/2022
18/09/2022 30/09/2023 |
320.49 |
|
Work delayed due to trees were present at site. Permission delayed from forest department.
Work delayed due to trees were present at site. Permission delayed from forest department. |
Detail Report
Graph / Photo |
||||
415 | Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work) |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
416 | Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work) |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
417 | Civil & Electrical Work |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
418 | Construction of Reinforced Cement Concrete Retaining Wall along IandFC drain from Kali Mata Mandir to FOB near Janak Cinema on Pankha Road (ID 2027) under Sub Division-21, Division- SWR-II, PWD, New Delhi. |
03/07/2023
31/08/2023 31/08/2023 |
316.12 148.11 (Aug'23) |
100.00 % 0.00 (Aug'23) |
Surender Singh |
|