Building - Construction Workभवन - रखरखाव का कार्य
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 C/O Integrated campus of G.B. Pant Engineering College and Polytechnic at Okhla delhi. 2024.03.22 2026.11.21 42361.79 1048.09 (Jul'22) 0.00 (Nov'23) Som Projects Pvt. Ltd. • Tender floated on 10.07.2023 with date of opening 04.08.2023. • 10 Nos bidder participated and technical bid approved by by the competent authority vide letter No. 23(72)/PWD/CE(OP)/2023/ 1582 dt 19.09.2023. • Financial Bid opened on 22.09.2023 and award of work is under process. Detail Report
Graph / Photo
2 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 2021.09.23 2022.02.22 40775.18 12389.92 (Jun'23) 0.00 (Jan'24) SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. Detail Report
Graph / Photo
3 Construction of Hospital at Madipur, New Delhi 2020.11.11 2022.11.10 26970.58 10425.19 (Jun'23) 0.00 (Mar'24) Ramacivil India Construction Private Limited Physical Progress- 92 % Financial Progress - 144.10 Cr. Detail Report
Graph / Photo
4 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 2019.10.18 2021.04.10 13447.15 5225.16 (Jun'23) 0.00 (Feb'24) Roshan Real Estate Pvt Ltd. False ceiling work in Block-A & final painting are under progress. Detail Report
Graph / Photo
5 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) 2021.07.18 2022.07.17 6988.57 605.62 (Oct'22) 2.00 % (Oct'22) A. K. Mehta & Co. Work in progress. Detail Report
Graph / Photo
6 Construction of 3 Nos. Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A-6, Paschim Vihar, Vasant Kunj and Ladpur Village, New Delhi (Package - 7). SH : Civil & Electrical work. 2021.07.18 2022.07.17 6988.57 2658.53 (Jul'23) 0.00 (Mar'24) A. K. Mehta & Co. Work is in progress. Detail Report
Graph / Photo
7 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 2019.08.06 2020.10.29 6563.40 2087.72 (Jul'23) 0.00 (Mar'24) PNSC Infrastructure Pvt. Ltd Finishing works, external façade and external development works are under progress. Detail Report
Graph / Photo
8 Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work). 2021.07.18 2022.07.17 5058.13 255.98 (Jul'23) 0.00 (Feb'24) PNSC Infrastructure Pvt. Ltd Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress. Detail Report
Graph / Photo
9 (a) C/o 76 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 12 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-1B, Sector-41, Rohini, Delhi. (b) C/o 72 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 1MP Hall, 08 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-2,C.F.-3, Sector-41, Rohini, Delhi. 2024.01.20 2025.01.19 3527.47 0.00 (Mar'24) RKMT BUILDCON PRIVATE LIMITED Work in progress Detail Report
Graph / Photo
10 Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes 2022.12.24 2023.06.23 3483.10 2253.60 (Jun'23) 0.00 (Feb'24) OPTIMUM SECURITY SOLUTIONS PVT. LTD. Work in progress Detail Report
Graph / Photo
11 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. 2022.10.17 2023.10.16 3000.18 1296.26 (Oct'23) 0.00 (Feb'24) Jai Bhagwan Terrace slab work completed, Mumty column & slab casting work in progress. Brick masonary at2nd & 3rd floor in progress. plaster work in progress at 1st & 2nd floor and also wall putty work is progress at Ground floor and 1st floor. Wall tile & floor tile work at GF, FF, SF in progress. Granite work in front staircase & GF, FF corridor is progress. Plambing work in Toilet at GF, FF, SF in progress, Terrace parapit Brick work in progress. Detail Report
Graph / Photo
12 Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi 2022.04.05 2022.12.04 2915.78 1077.04 (Mar'23) 0.00 (Mar'24) SVK Infrastructures "Building Work: Structural work of Workshop Building and Admin cum Rest Room had completed. Brickwork in the workshop building is completed and 80% of brickwork has been achieved in the Admin cum rest room. Finishing work in the workshop building is in the advanced stage. Hard standing/CC Pavement: Earthwork has been completed, WMM layer work has been completed and DLC layer work completed. PQC (M40 grade concrete work 40% completed) is in progress. Boundary Wall: The work of construction of the boundary has been completed. Finishing work has also been completed. Drainage Work: 90% of the drainage work completed. The structure for the underground water tank and septic tank has been completed."Hard standing/CC Pavement: Earthwork has been completed, WMM layer work has been completed and DLC layer work completed. PQC (M40 grade concrete work) had just started. Boundary Wall: The work of construction of the boundary has been completed. Finishing work has also been completed. Drainage Work: 90% of the drainage work completed. The structure for the underground water tank and septic tank has been completed. No progress can be achieved in the month of November due to NGT ban work further affected due to fresh ban in December. Detail Report
Graph / Photo
13 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 2019.06.28 2020.06.22 2806.33 381.24 (Mar'23) 0.00 (Mar'24) Roshan Real Estate Pvt Ltd. Work in progress (98% progress) Detail Report
Graph / Photo
14 C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi 2022.02.12 2022.11.09 2800.59 1318.22 (Jun'23) 0.00 (Mar'24) SVK Infrastructures nitially site was encroached by local people. Encroachment on the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Work of swimming pool and MP hall is in progress. Detail Report
Graph / Photo
15 Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. 2022.10.11 2023.09.05 2783.15 1872.39 (Sep'23) 0.00 (Jan'24) DND Infra Private Limit Finishing work & development work under progress. Detail Report
Graph / Photo
16 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 2021.08.23 2022.05.22 2373.12 1117.89 (Mar'23) 0.00 (Mar'24) M/s PK Gupta & Co. Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work completed in Admin cum Rest room has been completed. Workshop Building-Steel Structural work is in advance stage. Hard standing/CC Pavement: 90% Earth Work has been completed, 90% WMM layer work has been completed. DLC Layer work is in advance stage. Boundary Wall: The work of construction of a new boundary wall of approx. 1 Km has almost been completed. Finishing work is in advance stage. Drainage Work: 90% of the drainage work has been completed. The structure for RWH and underground water, septic tank has been completed. Detail Report
Graph / Photo
17 Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. 2023.05.24 2024.01.23 2107.18 0.00 (Mar'24) Kundu Nirma The preparation of the architectural drawing has been completed. Earthwork and excavation for the boundary wall have started. The building work and boundary wall work were affected due to the high water table. The matter of constructing the building and boundary wall on the pile foundation was finalised accordingly the structural were issued to the agency. Casting of more than 220 piles out of 450 has been completed. Detail Report
Graph / Photo
18 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 2020.05.31 2021.05.30 1874.70 1644.00 (Jun'23) 0.00 (Mar'24) SSP Promoters and Builders Private Limited Work in progress Detail Report
Graph / Photo
19 Construction of Residential Hostel at Chhattrasal Stadium, Model Town, Delhi. SH: C/o Hostel Building including External Development works, Internal Electrical Installation, External Lighting, lifts, fire fighting system, fire alarm with PA System, CCTV, Audio video system, HVAC works 2023.02.27 2024.07.26 1839.86 217.20 (Jun'23) 0.00 (Feb'24) KALYAN CHANDRA GOYAL & CO. 28% Detail Report
Graph / Photo
20 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 2022.04.01 2023.02.24 1798.93 374.04 (Jun'23) 0.00 (Feb'24) K. L. ARORA & SON Water proofing/ coba work on terrace for 50% area in progress, wall tile and kota, Granite flooring in progress at 1st floor, 2nd floor & 3rd floor classroom, water supply & drainage work in toilet at ground floor, 1st floor, 2nd & 3rd floor in progress. Slow progress due to space scarcity at site. Terrace parapet brick masonary work for 20% area in progress, 2nd floor column casting for 20% area in progress & balance 10% area could not start due to space constraints. Detail Report
Graph / Photo
21 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 2023.03.24 2023.09.19 1729.05 0.00 (Feb'24) SPS Infrabuild Pvt. Ltd. 39% Detail Report
Graph / Photo
22 C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. 2023.03.27 2024.02.19 1554.26 307.14 (Jun'23) 0.00 (Feb'24) SWASTIC CONSTRUCTION CO Block structure work completed also brick work completed and flooring work is in progress along with wall clading work. Plaster work at 3rd floor is in progress. For back side block 3rd floor beam casting under progress. Brick work is in progress. Work affected due to GRAP-III implementation & progress slow. Detail Report
Graph / Photo
23 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 2022.03.26 2023.02.19 1553.88 642.50 (Jul'23) 0.00 (Mar'24) K L Arora & Son Tower A -Tile work in toilet blocks & finishing & development work under progress. MP hall - Hall puff pannel and granite work completed & finishing work under progress. DIET block- structural work completed of 2/3 building portion and structural work of remaining 1/3 portion under progress. Tile work & finishing work under progress in structurally completed half building portion. Detail Report
Graph / Photo
24 C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi 2022.03.12 2022.12.06 1542.27 696.74 (May'23) 0.00 (Mar'24) The Krishna Construction Co. Initially some delay in start of work due to revision of layout and land apportioning between the new school and existing school. Layout plan was finalised by client department on 15.07.2022. Building work completed. Development work is in Progress. Detail Report
Graph / Photo
25 C/o Cluster Bus Depot at village Gadaipur, District South, Delhi. SH: Civil works and Electrical works. 2023.05.24 2024.01.23 1500.30 5.00 % (Jun'23) Kundu Nirman Work just awarded. The site has been handed over to the agency on 30.05.2023. The architectural drawing has been finalised.. Detail Report
Graph / Photo
26 Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works 2023.11.01 2024.04.30 1462.98 Kalyan Chandra Goyal & Company Detail Report
Graph / Photo
27 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 2022.04.02 2023.02.25 1359.28 613.77 (Jul'23) 0.00 (Mar'24) K. L. ARORA & SON Structural work completed. Kota stone griding & polishing in progress in part-2 block-A along with plaster work and GRC work & tile in wall cladding & Granite work in progress. External development work in progress. Paint & putty work under progress. Detail Report
Graph / Photo
28 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 2022.03.12 2023.02.04 1275.84 476.42 (Jul'23) 0.00 (Mar'24) M/s SURENDRA KUMAR Work in progress Detail Report
Graph / Photo
29 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 2022.04.06 2025.04.05 1099.29 114.42 (Jul'23) 0.00 (Jul'23) SIKKA ASSOCIATES REGD.

The proposal was submitted to VC, Delhi Sports University as on 05.03.2022 vide letter No. 54(103)/PWD/EPD-III/2021-22/06. The approval has been communincated as on dated 06.10.2022 vide letter No. F.No. 59/DSU/2021-22/441-46. Land ownership document has been sent to consultant for uploading the drawing on portal for local body approval. The PE has been submitted to CE(OP) office after scrutiny from the PM(Hr. Edu. Proj.) office.

Detail Report
Graph / Photo
30 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 2022.04.18 2023.03.13 1090.67 699.55 (Jul'23) 0.00 (Mar'24) K. L. ARORA & SON Block -A Structural work completed. Flooring work at all floor completed and corridor in progress. GRC tiles at front face completed and side portion is in progress. Water proofing at Terrace completed. Wall tiles, C.I. Pipes, water supply lines in toilet completed. Granite flooring in staircase steps completed. Dado work of staircase in progress. Block -B Granite work in staircase is completed. Finishing work is in progress. In B Block surrounding external development work in progress. GRC tiles at external wall in some portion is only pending. Toilet fitting & fixtures i/c W.C., wash basin, urinal, fixing work is in progress. In development work, front C.C. pavement work in front of building 80% completed and rest is in progress. Detail Report
Graph / Photo
31 C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. 2023.03.09 2024.02.01 1058.78 91.00 (Mar'23) 0.00 (Mar'24) AMOCON Pile casting for 80% area is completed and pile cap casting for 80% area is completed, balance area could not start due to space constraints at site. GF column has been completed for 70% area and 1st level Beam reinforcement work is in progress for 25% area. Slow progress due to space scarcity at site and constraints approach from main road to site. Detail Report
Graph / Photo
32 C/o Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar, New Delhi 2020.08.09 2021.11.08 958.41 55.00 (May'22) 0.00 (Feb'24) Sushil Buildwell Pvt. Ltd. Work Just Started Detail Report
Graph / Photo
33 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 2022.06.03 2024.06.02 721.25 351.65 (Aug'23) 0.00 (Feb'24) AZFARUDDIN Work in progress. Detail Report
Graph / Photo
34 Civil and Electrical Work. 2023.03.05 2023.11.29 617.03 16.00 (Sep'23) 0.00 (Mar'24) CHANDRA CONSTRUCTION COMPANY Detail Report
Graph / Photo
35 Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB 2022.09.25 2023.01.24 583.83 0.00 (Nov'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
36 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 2022.01.28 2022.12.27 579.95 360.97 (May'23) 0.00 (Nov'23) Invalid Work is in progress. Detail Report
Graph / Photo
37 C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) 2022.03.02 2022.11.26 385.86 0.00 (Feb'24) M/s. Satyam Construction Work is in progress Detail Report
Graph / Photo
38 Civil & Electrical Work. 2023.03.30 2023.09.29 352.07 0.00 (Mar'24) Engineers India Construction Ltd. Detail Report
Graph / Photo
39 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 2019.02.28 2019.06.27 294.21 58.25 (Feb'22) 0.00 (Dec'23) AASRA Martech Pvt.Ltd. Work in progress. Detail Report
Graph / Photo
40 Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). 2022.08.09 2023.08.08 292.57 8.79 (Mar'23) 0.00 (Feb'24) Nand gopal Gupta Detail Report
Graph / Photo
41 Air Pistol & Rifle 10m Shooting Hall cum all internal finishing fixtures fitting and development of complete setup of electronic type targets, shooting equipment etc. complete 2022.03.18 2022.09.13 290.26 55.31 (Jul'23) 0.00 (Mar'24) Dev Enterprises work is in progress Detail Report
Graph / Photo
42 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 2022.01.16 2024.10.15 288.00 Arcop Associates Pvt. Ltd. Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval. Detail Report
Graph / Photo
43 Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi 2022.12.26 2023.05.24 267.31 208.25 (Jul'23) 0.00 (Feb'24) Sham Lal Gupta & Sons 100% Detail Report
Graph / Photo
44 Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool 2020.12.23 2021.06.20 262.79 113.45 (Jul'23) 0.00 (Nov'23) Maa Narayan Constuction Co. Work Completed. Testing and commissioning of pool is pending. Detail Report
Graph / Photo
45 Construction of Boundary Wall of vacant Land at Madan Halwai Farm Loni, Johripur, Delhi. 2023.09.01 2024.02.27 152.17 0.00 (Feb'24) CBC and Sons 70% Boundary wall brick & column work is completed. Detail Report
Graph / Photo
46 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 2019.01.25 2019.05.24 140.44 216.46 (Oct'21) 0.00 (Oct'21) Uma Shankar work in progress Detail Report
Graph / Photo
47 Remodeling of drain in opposite side of Mansarovar Park to Kendriya Vidhalaya along with G.T. Road under Sub Division M-2111 during 2022-23. 2023.04.21 2023.10.17 136.64 Chaudhary Construction Company Pvt. Ltd. in progress Detail Report
Graph / Photo
48 Construction of boundary wall at vacant lying land measuring 09 Bigha 15 Biswa(7000 sqm. Approx.) bearing khasra No. 1937/1307 to 1990/1307 situated in village-Fahepur Beri. 2022.12.19 2023.06.01 129.24 0.25 (Jun'23) 0.00 (Feb'24) SIROHI CONSTRUCTION CO. Work is in progress Detail Report
Graph / Photo
49 Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) 2022.04.23 2023.01.22 124.05 9.97 (Feb'23) 0.00 (Aug'23) Dheeraj Singh & Company In Progress. Detail Report
Graph / Photo
50 C/o Extention of MADI of Dental Sciences,Ph-II at Bahadur Shah Zafar Marg,ND.SH SITCof Medical Gas Pipeline System including 3 Years Comprehensive Maintenance 2019.08.12 2019.11.09 115.37 Med Freshe Pvt. Ltd. work in progress by Med Freshe Pvt. Ltd Detail Report
Graph / Photo
51 Construction of RCC wall in place of existing boundary wall above ground level and Fencing work 2022.12.21 2023.03.20 96.02 85.00 % (Jun'23)

Work in progress.

Detail Report
Graph / Photo
52 Designing Manufacturing Installation and Commissioning of ceiling mounted Facade Access System on external facade and inner facade in Atrium at S Block Delhi High Court New Delhi 2022.12.16 2023.03.15 91.53 78.12 (Mar'23) 0.00 (Aug'23) M P BHATIA Work in progress Detail Report
Graph / Photo
53 Construction of Extention of Maulana Azad Dental Institute of Dental Sciences, phaseII at Bahadur Shah Zafar Marg, New Delhi.SH Supplying, installation, testing and Commissioning of Modular Operation Theatre 2019.08.12 2019.11.09 83.93 21.56 (Feb'22) 0.00 (Dec'23) MDD Medical System (INDIA) Pvt. Ltd work in progress by MDD Medical System (I) Pvt.Ltd. Detail Report
Graph / Photo
54 Up-gradation of swimming pool and other misc. civil works including electrical work 2021.08.11 2021.12.08 83.39 90.41 (Mar'23) 0.00 (Aug'23) M/s Tanishq Ions In Progress. Detail Report
Graph / Photo
55 Replacement of Water Tanks & M.S. framed platform at various floors of Delhi Secretariat Building 2022.05.21 2022.07.20 81.25 0.00 (Nov'23) Work in progress.70% Detail Report
Graph / Photo
56 Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) 2022.06.25 2022.08.23 78.59 135.99 (Jun'23) 0.00 (Aug'23) Uma Shankar Detail Report
Graph / Photo
57 A A to Karkardooma Court Complex Delhi SH Replacement of damaged Kota stone flooring into Granite stone flooring P F false ceiling and wall tiles in corridor and common area of ground floor including Electrical Work of A C and I block. 2023.04.05 2023.07.03 75.02 0.00 (Dec'23) Rakesh Kumar Rai granite work at A block Detail Report
Graph / Photo
58 1 Govt. Middle School, Sarita Vihar 2 Govt. Sr. Sec. School, Sultanpur 3 Sr. Sec. School, Tehkhand 4 Jonapur-1 5 Jonapur-2 6 RPVV at Sector A, Vasant Kunj Package-C. 2017.11.20 2018.01.19 71.50 42.22 (Oct'21) 0.00 (Oct'21) SPACE DESIGN GROUP work is held up Detail Report
Graph / Photo
59 SH Work of UTCS Complex Employment exchange JJB Court Working Women Hostel HLTB Complex Sanskar Ashram, Department of Social Welfare and CDMO Shahdara KKD Court Division under SD M 2312 during 2022 23. 2023.01.07 2024.01.06 64.35 26.08 (Aug'23) 0.00 (Feb'24) In Progress. Detail Report
Graph / Photo
60 Construction of 4 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of SRD Project Division-2, PWD, Delhi. (Civil & Electrical Work) 2022.06.01 2022.11.27 63.68 0.00 (Nov'23) R K Construction Co. Detail Report
Graph / Photo
61 Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 2022.02.07 2023.02.06 63.52 48.72 (Feb'23) 0.00 (Mar'24) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
62 Supply, installation, testing and commissioning of Router at Rouse Avenue District Court Complex, DDU Marg, New Delhi. 2023.06.01 2023.08.29 63.36 0.00 (Oct'23) TRACOM ENTERPRISES Work in progress Detail Report
Graph / Photo
63 Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi 2022.01.22 2023.01.21 62.58 78.03 (Jun'23) 0.00 (Jan'24) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
64 Providing of EI AC RO Water Cooler EPABX system and Fire Alarm System work including CIVIL works 2021.12.19 2022.02.18 59.70 3.69 (Jul'23) 0.00 (Jul'23) V. S. ENTERPRISES Detail Report
Graph / Photo
65 Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall 2022.03.14 2022.06.11 59.19 70.85 (Jan'23) 0.00 (Sep'23) Srishti Assosiates Detail Report
Graph / Photo
66 Construction of Boundary wall at vacant lying land measuring 02 Bigha 08 Biswa bearing Khasra no. 86/12/2 (02-08) of Directorate situated in Village-Ladpur (District-North-West) Delhi through, PWD. 2022.08.26 2022.12.23 58.39 0.00 (Jan'24) Parth Garg Work in progress Detail Report
Graph / Photo
67 Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi 2021.11.21 2022.02.18 54.92 26.82 (Apr'23) 0.00 (Apr'23) Millennium Furniture Detail Report
Graph / Photo
68 C/o Medical store and Surgical Store in basement area of Indira Gandhi Hospital, Sector-9, Dwarka, New Delhi 2022.09.13 2022.11.11 54.60 11.04 (Jun'23) 0.00 (Feb'24) DEEPAK CONSTRUCTION AND COMPANY Work is under progress. Detail Report
Graph / Photo
69 Renovation of 2nd floor Medical Block IT Cell at first floor Medical Block and Library room no. 5 18 240 and 241 at A Block Delhi High Court New Delhi. 2023.08.05 2023.11.02 52.03 0.00 (Jan'24) R L WADHWA Work in progress Detail Report
Graph / Photo
70 Construction of shed for Gate No. 1, 2 and 3 at District Court Complex, Saket, New Delhi. 2023.03.17 2023.06.16 51.74 IZHAR AHMED Detail Report
Graph / Photo
71 Construction of 100 Bedded Portable Hospital reserved for Covid 19 at A and U Tibbia College and Hospital, Karol Bagh, New Delhi (Electrical Works) 2021.12.28 2022.02.20 51.44 52.14 (May'22) 0.00 (May'22) Jain Electric Works Detail Report
Graph / Photo
72 Construction of Lift well including civil work in Utility block from Basement to Top floor at District Court Complex, Saket, New Delhi-110017 Civil + Electrical Work. 2023.04.07 2023.06.06 51.11 Anand Electricals Work in Progress 5% Detail Report
Graph / Photo
73 Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh 2017.06.27 2017.07.26 50.20 Bansal Builder Agreement closed PG forfeited Detail Report
Graph / Photo
74 False Ceiling, Granite and Wooden Flooring work in court rooms of Shahdara district Karkardooma Court Complex Delhi. Civil and Electrical Work. 2023.03.16 2023.06.13 50.09 18.00 (Jun'23) 0.00 (Feb'24) M.N Construction In progress Detail Report
Graph / Photo
75 Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block 2022.06.08 2022.09.05 50.04 55.78 (May'23) 0.00 (Jul'23) M. N. Construction Co. Detail Report
Graph / Photo
76 Provision for 1. Construction of front side boundary wall near main gate 2. Complete renovation of toilet blocks of old Building at Sarvodaya (Co-ed) Vidyalaya, Masjid Moth, New Delhi. (School ID: 1925246, Building ID: 19251141 & EOR ID: 20211430. 2023.09.06 2024.02.05 49.74 Shamshad Ahmad Detail Report
Graph / Photo
77 Construction of new academic block (G+3) with future extention of one floor at Lakshmi Bai College, Ashok Vihar, Delhi. (SH:- SITC of Audio Video System for Classrooms, Labs and Conference Room). 2024.02.13 2024.04.12 48.65 R J P ENTERPRISE Detail Report
Graph / Photo
78 Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi 2022.02.26 2022.03.27 48.15 0.00 (Oct'23) GEEKEN SEATING COLLECTION PVT LTD Detail Report
Graph / Photo
79 Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi 2022.06.25 2022.08.23 47.61 55.48 (May'23) 0.00 (Jan'24) Manish Construction Detail Report
Graph / Photo
80 Stone cleaning of Extension Block, Administrative Block and Outer Boundary Wall, Delhi High Court, New Delhi. 2023.07.17 2023.09.14 45.56 0.00 (Jan'24) Jamshed Ali and Sons Work in progress Detail Report
Graph / Photo
81 A R and M O Jagpravesh Chandra Hospital, Shastri Park, Lal Bahadur Shastri Hospital, Khichripur, Chacha Nehru Bal Chikitsalaya, Geeta Colony, Dr. Hedgewar Arogya Sansthan, Karkardooma, Aam Admi Polyclinic, Kanti Nagar an Delhi Govt. Dispensaries .... 2019.08.19 2020.08.18 45.47 Royal Construction p Detail Report
Graph / Photo
82 Improvement and renovation works in 06 Nos. Type III/IV Quarters. 2023.08.06 2023.11.05 43.58 0.00 (Jan'24) Nasimuddin Detail Report
Graph / Photo
83 SITC of Building Management System 2020.09.12 2021.03.11 43.49 Digital Controls & Automation Material supplied by the firm. Work is held-up by the agency. Notice under Clause 3 submitted to Competent Authority for approval for determination of contract. Detail Report
Graph / Photo
84 Construction of Oxygen Generator plant Hall at GIPMER, New Delhi. (Electrical works) 2021.12.06 2022.01.19 43.31 0.11 (Jul'22) 0.00 (Jul'22) Jain Electric Works Detail Report
Graph / Photo
85 P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). 2022.06.13 2022.09.10 41.34 51.67 (Jun'23) 0.00 (Feb'24) Uma Shankar Detail Report
Graph / Photo
86 Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings incupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) 2022.07.29 2022.09.11 41.32 40.40 (Mar'23) 0.00 (Oct'23) Engineers India Construction Co. Detail Report
Graph / Photo
87 Renovation of toilet blocks at post office and ATM side in Lawyers Chamber Block-I, Delhi High Court, New Delhi. 2023.07.11 2023.10.08 41.13 0.00 (Nov'23) SHREE PAL SINGH Work in progress Detail Report
Graph / Photo
88 Water proofing treatment of Main Court Block A Block podium and basement area at Delhi High Court New Delhi 2023.01.07 2023.05.06 40.42 14.95 (Jun'23) 0.00 (Jan'24) Complete waterproofing system inc. Work in progress Detail Report
Graph / Photo
89 Toilets renovation works 2021.07.09 2021.10.06 40.06 49.76 (Jan'23) 0.00 (Jan'23) Saeed Builders In progress. Detail Report
Graph / Photo
90 Up gradation of Type V Judges flats No 402 Type IV Judges flats No 205 Type VI Judge s flats No 607 and Servant Qtrs. 402 607 and 102 at Karkardooma Court Complex Delhi Civil and Electrical Works 2023.01.01 2023.03.31 38.79 0.00 (Dec'23) Uma Shankar In progress. Detail Report
Graph / Photo
91 Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings in cupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) 2022.07.29 2022.09.11 35.17 34.64 (Apr'23) 0.00 (Oct'23) Engineers India Construction Co. Detail Report
Graph / Photo
92 CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works 2020.08.15 2020.12.14 34.45 80.00 % (Dec'20) CSM CONSTRUCTION Detail Report
Graph / Photo
93 Providing Roof mounted Solar Plant of capacity 19 kwp and VRV/VRF Air Conditioning system at DIET, Ghumanhera. (SH : VRV/VRF system). 2023.11.18 2024.01.17 34.29 RefAir India Pvt. Ltd. Detail Report
Graph / Photo
94 Providing smoke extraction system from Ground floor to 4th floor for common corridors at Forensic Science Laboratory Building, Sector 14,Rohini, Delhi 110085. 2023.11.28 2024.02.01 34.23 R J P ENTERPRISE Detail Report
Graph / Photo
95 Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system 2019.07.09 2019.10.08 33.85 14.13 (Oct'22) 0.00 (Oct'22) SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. work in Progress 6th RA 18182135 Detail Report
Graph / Photo
96 Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi 2019.08.11 2019.11.10 33.77 19.85 (Mar'23) 0.00 (Mar'23) Med Freshe Pvt. Ltd. Work in progress Med Freshe Pvt. Ltd. Detail Report
Graph / Photo
97 Providing Ongrid Solar Power Plant in Fir Station Sec-5, Rohini, Delhi. 2023.12.21 2024.01.20 33.64 Yogesh Kumar Tyagi Detail Report
Graph / Photo
98 Construction of porta cabins Legal Aid Defence Counsel System office near facilitation centre for Legal Aid Defence Counsel System office Karkardooma Court Delhi. Civil Furniture and Electrical Works 2nd recall 2022.08.31 2022.09.29 33.23 0.25 (Mar'23) 0.00 (Mar'23) MUZAMMIL ALI Detail Report
Graph / Photo
99 Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) 2021.12.16 2022.04.15 32.92 29.75 (Jan'23) 0.00 (Jan'23) AKSHAY KUMAR DAGAR Work in Progress 80% Detail Report
Graph / Photo
100 Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) 2022.04.05 2022.07.03 32.79 30.24 (Nov'22) 0.00 (Nov'22) Cembond Construction Pvt. Ltd Detail Report
Graph / Photo
101 C O Police Housing Complex at Mandoli Delhi. (SH Annual Comprehensive Maintenance Contract of Johnson Make lift installed at Police Housing Complex, Mandoli Delhi) 2023.01.14 2024.01.13 32.49 Invalid Work in progress Detail Report
Graph / Photo
102 Renovation and Modification of 32 Nos Chambers of Honble Judge in A Block Delhi High Court New Delhi 2022.09.09 2022.11.07 31.97 119.75 (Mar'23) 0.00 (Aug'23) R L WADHWA Work in progress Detail Report
Graph / Photo
103 SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi 2018.10.16 2018.12.15 30.64 15.29 (Feb'19) 50.00 % (Feb'19) San Infotech Services work in progress 2nd RA 1696099 Detail Report
Graph / Photo
104 Supplying, Installation, Testing & Commissioning of high mast poles with Suitable LED fittings & fabrication of LT panel at FU-Block, Sports Complex, Pitampura, Delhi. 2024.03.13 2024.06.12 30.19 SUDHIR KUMAR Detail Report
Graph / Photo
105 Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 2021.12.17 2022.04.15 29.81 28.23 (Feb'23) 0.00 (Oct'23) Cembond Construction Pvt. Ltd In Progress. Detail Report
Graph / Photo
106 Making Accessible approach. Balance Work 1st recall 2022.09.24 2022.12.22 27.32 20.23 (Apr'23) 0.00 (Feb'24) Shobhit Kumar Detail Report
Graph / Photo
107 SITC of WI-FI & AC. 2023.08.07 2023.10.06 27.08 R J P ENTERPRISE First RA Bill Rs. 1969497/- CV No. 32 dt. 21.09.2023 Detail Report
Graph / Photo
108 Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi 2022.06.13 2022.08.11 26.85 27.90 (Jul'23) 0.00 (Jul'23) Uma Shankar Detail Report
Graph / Photo
109 Extensive & alternation of Bosch make addressable fire alarm system in Forensic Science laboratory Building, Sect-14, Rohini, Delhi. (SH: Upgradation of AFAS at 2nd, 3rd & 4th Floors.) 2023.12.05 2024.01.04 26.33 S K ELECTRICALS Detail Report
Graph / Photo
110 Up gradation of AFAS at Basement, G.F. & 1 st floors. 2023.07.27 2023.08.26 25.93 R B SUPER ELECTRICALS Detail Report
Graph / Photo
111 Civil work, false ceiling, flooring and finishing work at Multilevel Car parking in Delhi High Court, New Delhi. 2023.03.12 2023.06.10 25.91 0.00 (Nov'23) Yameen Work in progress Detail Report
Graph / Photo
112 Construction of 01 Nos. Clinical care centre under School Health Scheme on the vacant piece of land between Babu Ram Govt. SBV Bhola Nath Nagar and DIET Shahdara. (Civil, Furniture & Electrical Works). (4th Recall) 2022.09.16 2022.11.14 25.77 30.48 (Feb'23) 0.00 (Nov'23) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
113 Renovation of electrical installation for lab no. 403 and 403 A at 4th floor of Forensic Science Laboratory, Rohini, Delhi 2023.04.13 2023.07.02 25.26 R J P ENTERPRISE work in progress Detail Report
Graph / Photo
114 Construction of 5 Nos. Units of Toilets for Male, Female & Transgender, Near OPD, Casualty, Dharamshala Mortuary & MCH Building outside area at GTB Hospital Construction of 03 Nos. sheds with granite benches for patient attendants at Various Locations Near MCH Ground floor and Renovation of Seminar Room of Department of Pediatrics situated at MCH 4rth Floor (Front Wing) at GTB Hospital, Shahdara, Delhi. 2023.08.10 2023.11.07 25.20 0.00 (Dec'23) Sanendra Kumar Work in progress. Detail Report
Graph / Photo
115 Repair and renovation of Veterinary Dispensary, Bankner, Animal Husbandry Unit of GNCT of Delhi-110040 2022.08.01 2022.10.30 24.62 31.73 (Jul'23) 0.00 (Jul'23) Ankur Bhardwaj Work in Progress Detail Report
Graph / Photo
116 Replacement of damaged G.I. Sheets & Covering IRC wire fabric all around Pharmacy for thermal insulation at GTB Hospital, Shahdara, Delhi 2022.11.26 2023.01.24 23.91 7.93 (Mar'23) 0.00 (Jan'24) Shamshad Ahmed Work held up by agency. Detail Report
Graph / Photo
117 SITC of Lifts. 2023.02.21 2023.05.20 23.60 0.00 (Nov'23) Techno Industries Limited 2nd RA Bill Rs. 2242118/- CV No. 137 dt. 29.11.2023 Detail Report
Graph / Photo
118 Replacement of Main Gates No. 1, 2, 3, 5, 6 & 7 with repair of boundary wall for security purpose at GTB Hospital, Shahdara, Delhi. dg. 2023-24. 2023.08.17 2023.11.29 23.44 0.00 (Nov'23) AMIR ISRAR Work in progress. Detail Report
Graph / Photo
119 EOR to Sports complex SU- Block, Pitampura, Delhi during 2021-2022 (SH: Electrical Works) 2023.12.24 2024.03.23 22.48 R S ELECTRIC CO. Detail Report
Graph / Photo
120 Construction of some boundary wall after demolition of tilted existing boundary wall behind Principal office & construction of new boundary wall and construction of new stage on ground at Dr. Ambedkar Nagar, Sector-IV, No. 1- SBV (Yogi Arvind), New Delhi. (School ID: 1923005, Building ID: 19231163 & EOR ID: 20221410. 2023.07.26 2023.09.25 22.00 Vision Construction Detail Report
Graph / Photo
121 Strengthening of Judges Residential Complex Buildings M N and O Block at Karkardooma Court Delhi.(Repair of the external plaster) 2023.08.05 2023.09.03 21.94 0.00 (Mar'24) Sundriyal Construction - Closed Detail Report
Graph / Photo
122 Re-layering of Damaged Internal Bituminous Roads at Judges Flat including raising of manhole cover, laying of C.C. pavement, paver block & Kerb stone, at Karkardooma Court, Sahadara, Delhi-110032 2022.07.15 2022.08.13 21.86 JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
123 Construction of Boundary Wall, Vehicle Shed with Porta Cabin near UCMS Building, Repair of Structural Glazing and ACP Sheet Cladding of DEM Building GTB Hospital and Renovation of Aam Aadmi Polyclinic Nand Nagri, Delhi. 2023.04.14 2023.07.13 21.65 Nasir Ali Work in progress but progress work is very slow. Detail Report
Graph / Photo
124 Rewiring of main building & primary wing classrooms i/e providing fans, fittings and Air conditioners for computer labs & MP Hall at GSKV, B(AH)-Block, Shalimar Bagh, Delhi (School ID-1309032) 2023.12.04 2024.06.03 21.63 0.00 (Feb'24) BAJRANG ELECTRICAL (INDIA) Detail Report
Graph / Photo
125 Renovation of toilet blocks & miscellaneous civil works- Balance work 2022.06.26 2022.09.23 21.44 6.94 (Mar'23) 0.00 (Oct'23) Sanjeev Kumar Detail Report
Graph / Photo
126 SITC of 08 passengers lift -1 No. and 6 passengers lift -1 No. at Lakshmi Bai College, Ashok Vihar, New Delhi. 2024.02.19 2024.05.18 21.39 EVAAN ELEVATORS PVT LTD Detail Report
Graph / Photo
127 Expansion of Lawyers Cafeteria in B Block and Shifting of Filing Counter in Administrative Block & Providing and fixing work stations for IT Branch at Lawyers Chambers Block-III of Delhi High Court New Delhi. 2023.03.07 2023.04.05 21.18 0.00 (Oct'23) R L WADHWA Work in progress Detail Report
Graph / Photo
128 Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex 2022.06.08 2022.09.05 20.86 22.91 (May'23) 0.00 (Aug'23) Karan Walia Detail Report
Graph / Photo
129 Upgradation of existing analog CCTV system to IP based CCTV system in lockup rooms at District Court Dwarka Sector 10 New Delhi 2022.04.17 2022.07.16 20.86 YASH ENTERPRISES Detail Report
Graph / Photo
130 A/R & M/O to AIT College Shakarpur Delhi dg 2023-24 (SH:- Addition and Alteration of Sub Division Office 2023.10.20 2023.12.19 20.34 0.00 (Feb'24) rajeev kumar Detail Report
Graph / Photo
131 Repair Renovation of Gents Ladies Staff toilet general girls toilet and CWSN toilet block at Sarvodaya Kanya Vidyalaya Prahladpur Banger Delhi (School ID 1310032) 2022.10.21 2022.12.05 19.90 0.00 (Feb'24) M/s R M constrution Work in progress Detail Report
Graph / Photo
132 Providing AC, Fan, Light Fitting, rewiring in Govt. Co-ed. SSS, Sec15, Rohini, Delhi. 2023.08.19 2023.09.18 19.57 0.00 (Mar'24) Kuldeep Traders First RA Bill Rs. 1092671/- CV no. 17 dt. 12.10.2023 Detail Report
Graph / Photo
133 Operation and maintenance of compost machines installed in various jail at Prison Complex Mandoli Delhi (4th Call) 2022.09.26 2023.09.25 19.02 10.89 (Jun'23) 0.00 (Jun'23) Clean India Ventures Pvt. Ltd. Work is in progress Detail Report
Graph / Photo
134 SITC of CCTV in various Mohalla Clinic under sub division M3513 2022.04.13 2022.05.12 18.93 YASH ENTERPRISES

100% Work Completed

Detail Report
Graph / Photo
135 Provision of chequrred tiles, raising of boundary wall and other misc civil work 2022.06.26 2022.07.25 18.67 21.25 (Dec'22) 0.00 (Dec'23) Sanjeev Kumar Detail Report
Graph / Photo
136 SITC of VRV/ VRF Air Condition Plant 2022.06.12 2022.07.11 18.55 12.64 (Sep'22) 0.00 (Dec'23) Airtemp Engineers

100% Work Completed

Detail Report
Graph / Photo
137 Provision of Basket Ball Court along with development of adjoining area in the Residential Campus GTB Hospital Shahdara Delhi 2023.06.16 2023.07.20 18.37 0.00 (Oct'23) Chunesh Bansal Work is in progress Detail Report
Graph / Photo
138 C/o recreation hall at PTS Wazirabad Delhi. (SH- Providing Electrical Installation) 2019.02.12 2019.06.11 18.22 S K Engineers Detail Report
Graph / Photo
139 Renovation of toilets gutter fixing and barricading work. 1st recall 2022.08.21 2022.12.18 18.07 0.24 (Mar'23) 0.00 (Nov'23) MOHAMMAD HUSSAIN Detail Report
Graph / Photo
140 Renovation of Ladies Bar Association Room at KKD Courts Delhi. Civil Furniture and Electrical Works 1st recall. 2023.02.12 2023.03.28 18.05 6.15 (May'23) 0.00 (Dec'23) Detail Report
Graph / Photo
141 Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) 2022.04.01 2022.06.29 17.32 19.11 (Dec'22) 0.00 (Dec'22) SABUR ALAM Detail Report
Graph / Photo
142 Construction of Godown for Horticulture Deptt. at Nursery and Store Room at Fire Station near Delhi Secretariat, Delhi. 2023.02.06 2023.04.05 17.18 RAJU work in progress. 90% work has been done. Detail Report
Graph / Photo
143 Construction of Crèche in IGDTUW Campus, Kashmere Gate, Delhi. 2023.03.09 2023.05.08 17.10 KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
144 Changing the Windows of Nurse Hostel in Residential Campus at GTB Hospital Shahdara Delhi 2022.08.26 2022.11.23 16.17 4.02 (May'23) 0.00 (Jan'24) Sanendra Kumar Work is in progress Detail Report
Graph / Photo
145 A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) 2017.04.13 2017.10.12 16.04 7.45 (Mar'19) 46.00 % (Mar'19) Anup Enterprises Detail Report
Graph / Photo
146 Providing and installation of Audio Visual system in assembly ground with SITC of Public Address system and provision of smart classroom at GBSSS, U Block, Mangolpuri Delhi. (School ID:- 1412009) 2023.12.27 2024.02.26 15.70 Dynamic Systems Detail Report
Graph / Photo
147 SITC of CCTV Cameras at Place of Safety, Majnu Ka Tila, Delhi 2022.04.13 2022.05.12 15.40 15.10 (May'23) 0.00 (May'23) YASH ENTERPRISES

100% Work Completed

Detail Report
Graph / Photo
148 Construction of Rain Water Harvesting Pit inside ITI Campus and ITI Staff Quarter, Vivek Vihar, Delhi. 2022.07.15 2022.10.12 15.37 0.00 (Jul'23) Shivam Builders Detail Report
Graph / Photo
149 SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. 2018.11.07 2019.02.04 15.26 17.61 (Apr'22) 0.00 (Jul'23) MOHAMMAD HUSSAIN in progress. Detail Report
Graph / Photo
150 Annual comprehensive maintenance of existing Air conditioner and Replacement of fans, fittings, security lights , Distribution Boards along with allied switchgears at Laxmi Bai college, Ashok vihar, Delhi. 2023.09.14 2024.09.13 15.18 0.00 (Dec'23) SUDHIR KUMAR First RA Bill Rs. 794141/- CV No. 11 dt. 15.12.2023 Detail Report
Graph / Photo
151 Accessibility works 2022.08.06 2022.10.04 15.09 12.07 (Nov'22) 0.00 (Nov'22) M T Builders In Progress. Detail Report
Graph / Photo
152 SITC of 6 passengers Hydraulic lift in Admin Block basement 1 to basement 2 at District Court Sector 10 Dwarka New Delhi 2022.08.01 2022.10.30 14.92 0.00 (Aug'23) Techno Industries Pvt Ltd Detail Report
Graph / Photo
153 Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work 2022.05.29 2022.08.26 14.87 18.56 (Dec'22) 0.00 (Oct'23) Sushil Kumar Work not started by agency due to rain Detail Report
Graph / Photo
154 Aluminium Works at Delhi Secretariat 2022.07.01 2023.03.31 14.14 9.04 (Feb'23) 0.00 (Oct'23) Nasimuddin Detail Report
Graph / Photo
155 EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section 2018.04.02 2030.09.15 13.58 L V Enterprises Detail Report
Graph / Photo
156 Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) 2022.05.19 2022.06.17 13.23 19.43 (Dec'22) 0.00 (Dec'22) Jain Electric Works Detail Report
Graph / Photo
157 Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. 2019.02.10 2019.05.10 12.52 13.79 (Jan'20) 0.00 (Jan'20) Daya Sagar Sharma work in progress Detail Report
Graph / Photo
158 Repair and AMC of Audio and PA system installed at SKV Sec-1 Avantika, School, Rohini, Delhi. 2023.12.13 2024.12.12 12.17 0.00 (Mar'24) CELTO ACOUSTIQUE LLP Detail Report
Graph / Photo
159 Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) 2022.02.02 2022.03.03 12.04 0.12 (Mar'23) 0.00 (Mar'23) Sanjeev Kumar In progress. Detail Report
Graph / Photo
160 Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi 2021.12.26 2022.02.23 11.65 11.10 (Feb'23) 0.00 (Feb'23) Sanjeev Kumar In progress. Detail Report
Graph / Photo
161 Providing Fans, Light Fitting, Water Cooler at SKV, Sector-1, Avantika, Rohini, Delhi. 2023.07.11 2023.09.10 11.63 Adhiraj Construction Detail Report
Graph / Photo
162 Civil Work. 2023.02.12 2023.05.12 11.21 12.63 (Apr'23) 0.00 (Jan'24) MOHAMMAD HUSSAIN In Progress. Detail Report
Graph / Photo
163 Civil Electrical Works 2021.12.10 2022.02.07 11.21 11.94 (Oct'22) 0.00 (Oct'22) Rainbow Constructions In Progress. Detail Report
Graph / Photo
164 Providing and fixing down comer and manually operated electronic FA system 2019.09.19 2019.10.18 11.18 0.00 (Mar'19) 98.00 % (Jan'21) M/s Royale Meridian India Pvt Ltd Work completed. Final bill yet to be submitted by the agency. Detail Report
Graph / Photo
165 Repair and replacement of defective accessories of Addressable Fire Alarm System & Down comer Fire fighting system at Mangol Puri, ITI New Delhi. 2023.04.27 2023.06.24 11.11 0.00 (Oct'23) R J P ENTERPRISE Detail Report
Graph / Photo
166 Renovation of toilet blocks at G/F (02 nos.), F/F (02 nos.) & S/F (01 no.) 2022.10.05 2022.12.03 10.79 0.00 (Oct'23) MOHAMMAD HUSSAIN Detail Report
Graph / Photo
167 Miscellaneous Civil works 2022.05.10 2022.07.08 10.73 8.62 (Jun'23) 0.00 (Oct'23) MOHAMMAD HUSSAIN Detail Report
Graph / Photo
168 Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi 2022.05.29 2022.06.27 10.53 12.79 (Oct'22) 0.00 (Aug'23) Sundriyal Construction - Closed Detail Report
Graph / Photo
169 ARMO Various Electrical Installations and Mechanical Equipments at FSL, Madhuban Chowk, Sec-14, Rohini, Delhi (SH : AMC of Johnson Make Lifts) 2024.03.01 2025.02.28 10.48 Johnson Lifts Pvt. Ltd. Detail Report
Graph / Photo
170 C/o of Two Nos. of Toilet(One for Handicapped and Other for Transgender) and Water Proofing Treatment of Roof at DDMA and Block-C, P/F Kota stone Slab flooring with Granite strip in front of A block etc at the O/o the D.M(East) dg 2022-23 (Balance work) 2022.08.15 2022.11.14 10.47 Aamir Khan Detail Report
Graph / Photo
171 Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans 2022.02.28 2022.08.27 10.14 0.00 (Mar'24) Dashmesh Enterprises

100% Work Completed

Detail Report
Graph / Photo
172 Wiring/Rewiring i/c providing fans, fittings, flood light, main electrical panel & RO and water cooler at Directorate of education office, FU block Pitampura, Delhi. 2023.11.30 2024.11.29 9.24 R S ELECTRIC CO. Detail Report
Graph / Photo
173 Installation of LED Boards at Entry Gate 1, 1A and 2 and on the roof of Main Building, Tis Hazari Court Complex, Delhi. 2024.02.10 2024.04.09 9.07 MOHD AMJAD work in progress Detail Report
Graph / Photo
174 Supplying, Installation, Testing and Commissioning of oil filled heat radiators for chambers of Ld. Judicial Officers at various locations in District Court Complex, Sector-14, Rohini, Delhi-110085 2024.01.08 2024.02.07 8.04 Lokesh Garg Detail Report
Graph / Photo
175 Wall paneling wooden flooring and toilet renovation work Civil and Electrical works 2022.06.11 2022.07.10 7.36 0.25 (Mar'23) 0.00 (Mar'23) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
176 Construction of 10 Nos. Room for faculty of Anesthesia with gypsum partition at 4th floor, B.L. Taneja Block at MAMC New Delhi 2022.09.12 2022.11.11 7.11 8.76 (Feb'23) 0.00 (Feb'23) M/s Bajrang Electrical (India)

Work in progress

Detail Report
Graph / Photo
177 Construction of underground water storage tanks for upcoming Court Rooms with additional storage facility for existing Court Complex and Residential Complex Saket including upgrading of existing water main line feeding Residential Court Complex--- 2023.02.03 2023.03.02 6.57 0.00 (Mar'24) ARSHAD Detail Report
Graph / Photo
178 Sweeping of road, development of rain water harvesting system, CO sump tank and other misc repair works 2022.08.04 2023.05.10 6.41 4.94 (Mar'23) 0.00 (Sep'23) Invalid Work in Progress Detail Report
Graph / Photo
179 Construction of tin shed near main gate and provision for sitting. 2023.06.28 2023.08.11 6.28 N.M. Construction Co. WORK YET TO STARTED. Detail Report
Graph / Photo
180 Replacement of wooden sofa chair with new visitor chairs at I/C E.D. Lockup and miscellaneous furniture work at courts of Shahdara District Branch, KKD Court Delhi 2022.07.09 2022.08.07 6.07 7.32 (Jan'23) 0.00 (Jan'23) Ganpati Furniture System Pvt Ltd Detail Report
Graph / Photo
181 ARMO various Electrical and Mechanical services (Internal & External) in Keshav Maha Vidyalaya at Pitampura, Delhi during 2023-24. (SH: Replacement of old electrical tube fittings with LED based luminaries & necessary EI work alongwith provision of glow signage board etc.) 2023.12.04 2024.01.03 5.95 BAJRANG ELECTRICAL (INDIA) Detail Report
Graph / Photo
182 Construction of 500 LPM PSA Plant for Covid- 19 at A U Tibbia College Hospital, Karol Bagh, New Delhi. (Electrical Works) 2021.11.11 2022.01.10 5.94 Shyam Electricals & Engineers Detail Report
Graph / Photo
183 SITC of ventilation fans in various wards at CJ-10, Rohini, Delhi dg.2023-24 2023.12.25 2024.01.24 5.77 0.00 (Feb'24) R J P ENTERPRISE Detail Report
Graph / Photo
184 Electrical work. 2023.07.04 2023.09.03 5.68 RAJA ELECTRICAL ENGINEERING WORKS Detail Report
Graph / Photo
185 Tentage & sitting arrangement 2022.07.30 2022.08.09 5.68 6.37 (Mar'23) 0.00 (Dec'23) Vishal Tents and Decorators work in progress Detail Report
Graph / Photo
186 Providing and fixing dustbin at Karkardooma Court Complex, Delhi 2022.06.13 2022.07.12 5.66 77.43 (Mar'23) 0.00 (Mar'23) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
187 Supplying, Installation, Testing and Commissioning of SS Body water coolers at various floors of Forensic Science Laboratory Building,Sector - 14, Rohini, Delhi. 2023.08.21 2023.09.20 5.64 Vivek associates Detail Report
Graph / Photo
188 Civil Works 2022.09.01 2022.09.30 5.36 0.25 (Mar'23) 0.00 (Mar'23) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
189 Providing & Installation of 1000 LPH Reverse Osmosis Plant with Water cooler cum Purifier at each floor of main building in GGSSS No. 2, Mubarakpur Dabas, Delhi. (School ID:- 1412253) 2024.01.22 2024.02.21 5.29 LAXMI WATER WORLD Detail Report
Graph / Photo
190 Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer 2022.01.31 2022.03.31 4.93 5.35 (Jun'22) 0.00 (Jun'22) PURIFIRES INDIA In Progress. Detail Report
Graph / Photo
191 Providing Furnitures at Ladies Bar Association Room at KKD courts, Delhi. 2023.03.22 2023.04.20 4.88 13.84 (Jun'23) 0.00 (Jan'24) Uma Shankar Detail Report
Graph / Photo
192 Major repair work on water supply pipe line tanks. 2023.02.11 2023.04.11 4.70 7.99 (Jun'23) 0.00 (Sep'23) Mohd Azam Detail Report
Graph / Photo
193 Providing and fixing of UPVC Doors and Windows S.S railing Blinds cupboard work. 2023.05.13 2023.06.11 4.67 0.00 (Mar'24) Anuj Kumar Singal In Progress. Detail Report
Graph / Photo
194 Civil Works. 1st Recall 2023.01.06 2023.02.04 4.63 0.87 (Jun'23) 0.00 (Dec'23) Mohd. WAZID Detail Report
Graph / Photo
195 Construction of fire resistant barriers in E and M shafts at Delhi High Court 2019.09.28 2019.10.27 4.49 Naini Electricals Detail Report
Graph / Photo
196 Renovation of Chamber of Office-in-Charge IT & Digitization Cell at Rouse Avenue Court, New Delhi (SH: E&M Works). 2023.12.26 2024.01.25 4.48 R. Diamond Enterprises Work in progress Detail Report
Graph / Photo
197 Providing High Mast type Pole with energy efficient LED fittings alongwith provision of 120 LPH water cooler with inbuilt RO system at Sarvodaya Co-ed Vidyalaya, Sultanpur Majra, Delhi. (School ID:- 1412016) 2024.01.08 2024.02.07 4.37 G K ELECTRICALS Detail Report
Graph / Photo
198 Urgent Repair of boundary wall of Parking between Gate No 1 and 2 and pump house at GTB Hospital Shahdara Delhi 2022.11.07 2023.01.05 4.01 0.00 (Jul'23) Nasir Ali Work in progress. Detail Report
Graph / Photo
199 C/o SPS Structure (4 storey) for ITI at Bakkarwala, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) 2020.01.10 2020.02.08 3.99 99.00 % (Jan'21) A TO Z Engineering Works Work in progress and likely to be completed by the end March 2024. Letter written to firm for completion and submission of final bill. Detail Report
Graph / Photo
200 C/o SPS Structure (4 storey) for ITI at Ranhola, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) 2020.01.10 2020.02.08 3.99 99.00 % (Jan'21) A TO Z Engineering Works Work in progress and likely to be completed by the end March 2024. Letter written to firm for completion and submission of final bill. Detail Report
Graph / Photo
201 Installation of 1 no. borewell at Fire Station Tahirpur Delhi dg. 2022 23. Civil and Electrical Works 2022.09.21 2022.10.20 3.93 4.37 (Jun'23) 0.00 (Jun'23) Lucky Project Detail Report
Graph / Photo
202 RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. 2019.02.03 2020.02.02 3.91 17.36 (Jun'23) 0.00 (Jun'23) ARORA ELECTRICAL WORKS Detail Report
Graph / Photo
203 Replacement of broken glass and painting of grills of window providing and fixing of signage board and other misc. work at DIET Building Karkardooma Institutional area Delhi 110032 1st Recall 2022.09.09 2022.10.08 3.59 4.18 (Mar'23) 0.00 (Dec'23) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
204 Construction of 3 Nos. Pucca School Building (G+3) with Ancillary Facilities including internal water supply sanitary installation internal electrical installation and development of site at GGSSS No.2/GBSSS Uttam Nagar, Desu Colony (DTL) Janakpuri and Kohat Enclave New Delhi (Package-4) (SH : Transplantation and plantation of trees). 2022.03.04 2023.04.03 3.30 101.43 (Nov'22) 0.00 (Feb'24) Rohit Nursery Tree transplantation done at Pucca School Building GGSSS No. 2/GBSSS Uttam Nagar, New Delhi and 365 days for maintenance of Planted Tree Upkeep of transplanted tree work is in progress. Detail Report
Graph / Photo
205 Barricading of dangerous portion of old school building, chipping of unsound/weak concrete & demolishing damaged RCC & brick work in Gandhi Memorial School, Shahdara (Near Shyamlal College), Delhi. (1st recall) 2022.08.17 2022.09.15 3.26 0.00 (Aug'23) JAI KALKA CONSTRUCTION COMPANY Detail Report
Graph / Photo
206 Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23. 1st Recall 2023.01.06 2023.02.04 3.22 4.01 (Feb'23) 0.00 (Sep'23) Mohd. WAZID Detail Report
Graph / Photo
207 Construction of New Passenger Lift for 13 Persons including connection corridor with existing Building PGC, M-Block, Vikas Bhawan, New Delhi (SH. Electrical Works in Lift Shaft and replacement of existing Light in Connecting Corridors) 2017.10.17 2018.01.16 3.14 Chetan Enterprises Detail Report
Graph / Photo
208 Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23 2022.08.26 2022.09.24 3.06 0.25 (Mar'23) 0.00 (Mar'23) PRASHANT BUILDERS Detail Report
Graph / Photo
209 SITC of 500 LPH RO Plant and providng water cooling sytem at GBSSS , SU bLock pitampura, shalimar Bagh (School ID 1411617) 2024.02.13 2024.03.12 2.70 Icon RO Systems Detail Report
Graph / Photo
210 Renovation work 2023.01.13 2023.02.11 2.61 0.00 (Dec'23) Mohd Azam Detail Report
Graph / Photo
211 Renovation of office of Secretary in DSSSB Building at Karkardooma Shahdara Delhi dg 2022 23 2022.08.03 2022.09.01 2.56 6.31 (Apr'23) 0.00 (Apr'23) Mohd Azam Detail Report
Graph / Photo
212 Installation of Stainless Steel Grill on the window for safety and security of Valuable assets 2022.06.13 2022.07.12 2.29 2.90 (Apr'23) 0.00 (Apr'23) Mohd Azam Detail Report
Graph / Photo
213 Stationing of a Porta Cabin in the premises Multilevel Car parking, Delhi High Court, New Delhi. (SH: - Civil Work) 2023.09.30 2023.10.21 2.19 IRFAN KHAN AND CO. Work in progress Detail Report
Graph / Photo
214 Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 2022.06.22 2022.07.06 2.08 2.09 (Aug'22) 0.00 (Aug'22) CHETAN SHARMA

100% Work Completed

Detail Report
Graph / Photo
215 Providing E and M installations for the Fire Tender Porta Cabin near to Ancillary Block at Delhi High Court, New Delhi. 2024.01.21 2024.02.19 2.06 Chetan Enterprises work in progress Detail Report
Graph / Photo
216 SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. 2022.03.25 2022.04.23 1.90 MKSC Design India Private Limited Work in Progress Detail Report
Graph / Photo
217 Construction of 72 Nos. equivalent classrooms (G+3) including internal electrical works sanitary installations, water supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical). (SH: Carrying out structural analysis and preparation of structural drawings)”. 2022.03.23 2022.04.22 1.85 MKSC Design India Private Limited Work in progress Detail Report
Graph / Photo
218 Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri 2021.09.04 2021.10.03 1.85 0.88 (Mar'22) 0.00 (Mar'22) Sanjeev Kumar Detail Report
Graph / Photo
219 Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner 2021.09.05 2023.09.04 1.81 0.82 (Dec'22) 0.00 (Dec'22) Frank Copier Pvt. Ltd. Detail Report
Graph / Photo
220 Supply Installation Testing and Commissioning of Digital Set Top Box in Special Ward at L N Hospital New Delhi due to COVID 19 2021.03.18 2021.04.01 1.70 DURGA ENTERPRISES Detail Report
Graph / Photo
221 Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. 2022.06.23 2022.07.07 0.74 0.74 (Sep'22) 0.00 (Sep'22) Kesari & Associates Detail Report
Graph / Photo
222 Soil investigation and bearing capacity of soil 2021.08.19 2021.08.28 0.50 Allied Engineers Detail Report
Graph / Photo
223 C/o of Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar New Delhi under HSD South-III/HD-South/PWD/New Delhi dg. 2020-21. Transplantation of trees 2021.04.05 2021.05.19 0.16 Om Prakash Sharma BEYPS5726N1ZC Detail Report
Graph / Photo
224 Repairing of aluminium doors & Shutters. 2014.08.19 2014.09.03 Detail Report
Graph / Photo
225 Providing and laying RCC drain cover in open surface drain in basement. 2014.08.16 2014.09.15 2.58 (Mar'21) 0.00 (Mar'21) Detail Report
Graph / Photo
226 Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. 2014.09.16 2014.10.15 Detail Report
Graph / Photo
227 Finishing of exterior wall in 20 nos. CBI flats. 2014.12.08 2014.12.26 Pradeep Kumar Sharma Detail Report
Graph / Photo
228 P/F Manhole cover & Drain cover. 2015.01.08 2015.02.07 M. N. Construction Co. Detail Report
Graph / Photo
229 Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. 2014.08.18 2015.01.01 Detail Report
Graph / Photo
230 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. 2015.01.08 2015.02.04 Detail Report
Graph / Photo
231 Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. 2014.09.18 2014.10.17 Detail Report
Graph / Photo
232 Replacement of Damaged roof of Sub Divn. Office M-233. 2014.11.11 2014.12.10 35.49 (Aug'21) 0.00 (Aug'21) Detail Report
Graph / Photo
233 Cleaning of sewer line, manhole & gully traps etc. 2014.12.22 2015.01.21 Detail Report
Graph / Photo
234 Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. 2015.01.24 2015.02.23 M. N. Construction Co. Detail Report
Graph / Photo
235 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. 2015.01.08 2015.02.07 M. N. Construction Co. Detail Report
Graph / Photo
236 Providing and fixing polycarbonate in available. 2014.12.19 2015.01.18 Detail Report
Graph / Photo
237 Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. 2015.01.17 2015.02.16 Pradeep Kumar Sharma Detail Report
Graph / Photo
238 Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. 2015.02.08 2015.03.08 Detail Report
Graph / Photo
239 Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. 2015.02.06 2015.03.15 Detail Report
Graph / Photo
240 Water proofing treatment of first floor toilet. 2014.12.15 2015.01.14 Detail Report
Graph / Photo
241 Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. 2015.02.06 2015.02.20 Detail Report
Graph / Photo
242 Misc. Civil Works. 2015.03.16 2015.03.30 Shekhar Detail Report
Graph / Photo
243 Providing ramps in Schools & miscellenious works. 2015.02.12 2015.02.26 Detail Report
Graph / Photo
244 P/F Floor tile & broken tile. 2015.11.20 2015.12.12 Detail Report
Graph / Photo
245 Providing and laying cement concrete. 2015.03.12 2015.03.25 Indal Yadav Detail Report
Graph / Photo
246 Providing railing for Park. 2015.11.23 2015.12.05 Detail Report
Graph / Photo
247 Construction of table top in front of Entry and Exit Gates of Residential Complex, District Court Saket at Birla Vidya Niketan Marg under Subdivision -14/ South Road-1 during 2023-24. 2023.08.14 2023.09.13 Work in progress Detail Report
Graph / Photo
248 EOR to Swami Dayanand Sarvoday Kanya Vidyalaya, Old Rajinder Nagar,New Delhi during 2023-24.(Re-construction of boundary wall of school) (Balance Work) 2023.09.28 2023.11.26 work in progress Detail Report
Graph / Photo
249 C/o 40 Nos. equivalent Additional SPS Class rooms, Libraries, Toilets & Labs etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at Sarvodaya Vidyalaya, Mansarover Garden New Delhi (School ID - 1516003) (Civil work & Electrical Work ) 2023.09.25 2024.08.19 0.00 (Mar'24) Work in progress Detail Report
Graph / Photo
250 C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road Delhi. (SH: C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus) 2023.08.14 2024.05.09 0.00 (Oct'23) Work awarded on 14.08.2023. Preparation of Structural drawings & their approval is in progress. Detail Report
Graph / Photo
251 Barrier free infrastructure of school building. 1. Accessible Route/pathway-Entire corridor should have anti-skid surface, tactile path, ramp (with handrails) and signage. 2. Lift / elevator or ramp on every floor. 3. Accessible staircase – Color contrasting strips on the horizontal surface of the steps. 4. Accessible toilet with handrails and urinals. 5. Accessible drinking water facility – Drinking water taps accessible for person with disability. 2023.07.07 2023.10.06 WORK IN PROGRESS Detail Report
Graph / Photo
252 Construction of Change Room including toilet, Guard Room, Office Room, Coach Room, S.S. fencing on Periphery of Athletic Track & Boundary wall with concertina coil fencing etc. and Renovation of existing block, pump house, entry road and provision of stone cladding on boundary wall at Pooth Kalan Sports Complex, Delhi. (Hiring of inspection vehicle) 2023.08.12 2024.08.11 0.00 (Mar'24) Work in progress. Detail Report
Graph / Photo
253 Special Repair of Expansion Joints, RCC Chajja, Column for arresting leakage /seepage and misc. work to Rouse Avenue District Court Complex at DDU Marg, New Delhi. 2023.07.07 2023.08.20 0.00 (Jan'24) The work is in progress Detail Report
Graph / Photo
254 C/o Residential Hostel at Chhatrasal Stadium Model Town, Delhi. (SH : comprehensive maintenance of PC’s and associated accessories for O/o PM(HEP), PWD and O/o EE(E), B141, PWD.) 2023.04.20 2026.04.19 Work in progress. Detail Report
Graph / Photo
255 Cleaning of sewer line, manholes, road gully chambers and storm water drain 2023.05.30 2024.05.30 0.00 (Nov'23) In-progress Detail Report
Graph / Photo
256 Beautification of gate water proofing of new building block S S railing and other misc works Balance Work 2022.09.10 2023.01.09 work in progress. 65% work has been done. Detail Report
Graph / Photo
257 Road marking, Thermoplastic paint and Synthetic enamel paint on road under Sub Division SR-15 2022.09.21 2022.11.04 31.06 (Apr'23) 0.00 (Jan'24) work in progress Detail Report
Graph / Photo
258 A/R & M/O to Rouse Avenue Court Complex at DDU Marg, New Delhi During 2022-23 & 2023-24. (SH: Operation and Maintenance of STP Plant of 180 KLD). 2022.09.30 2024.09.29 4.59 (Mar'23) 0.00 (Mar'23) Work is in progress Detail Report
Graph / Photo
259 Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 2022.11.05 2024.11.04 90.27 (Jun'23) 0.00 (Mar'24) work in progress, as per complaint received in sub division, the regular day to day compliance is made. Detail Report
Graph / Photo
260 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 2023.03.24 2023.09.19 39% Detail Report
Graph / Photo
261 Annual Maintenance and Networking of Computers Systems UPS Photocopier machines and Printers of Circle office M 22 Divisional office M 221 and Sub Divisional Office M 22 2022.09.30 2023.09.29 work in progress. Detail Report
Graph / Photo
262 Consultancy Services for Comprehensive Architectural and Engineering Planning and Designing for Construction of 100 seated Government Veterinary College/Research Institute at Satbari in South Delh. 2023.09.04 2026.12.04 Work on hold Detail Report
Graph / Photo
263 Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W 2023.03.09 2024.02.01 1st floor Column casting of 70% area in progress, brick masonary at GF in progress and gf column casting for 30% area in progress Detail Report
Graph / Photo
264 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 2023.03.24 2023.09.19 3.99 (Jan'23) 0.00 (Jan'23) Structure for left hand side and right hand side portion completed upto terrace level. The mumty roof for LHS & RHS staircase shutters and steel reinforcement is in progress. The AAC block maasonry and plastering work is in progress. The fixing of granite sill level amd Jamb in window is in progress. for LHS putty work also in progress. Plumbing and sanitary work is in progress. The finishing work such as internal and external plastering, false ceiling frame work is in progress. The water proofing at terrace almost 80% completed. Detail Report
Graph / Photo
265 Filling, Carriage and pouring out of drinking and non drinking water into water tank of Burari Hospital complex 1900.01.12 2023.07.11 Tender is under process Detail Report
Graph / Photo
266 Preventive maintenance for Civil works 2023.01.20 2024.01.19 0.00 (Sep'23) work in progress. 40% work has been done. Detail Report
Graph / Photo
267 Construction of Spectator Gallery for VIP’s/ Visitors 2022.12.22 2023.03.21 In-Progress Detail Report
Graph / Photo
268 Laying of sewerline and connecting with main DJB sewerline in SKV Janki Devi 2022.11.13 2022.12.12 work in progress and sewerline connection is pending. Detail Report
Graph / Photo
269 Filling, Carriage and pouring out of drinking and non drinking water into water tank of Dr. BSA Hospital complex 2022.12.30 2023.06.29 100.00 % (Jul'23) work in progress Detail Report
Graph / Photo
270 Repairing works and water proofing of DGHS Dispensary OLD Seemapuri New Delhi 2023.01.08 2023.02.07 0.00 (Sep'23) Work in progress. Detail Report
Graph / Photo
271 Renovation of Emergency Lab and Blood Storage room at Jag Pravesh Chandra Hospital, Shastri Park, Delhi 2023.01.01 2023.03.01 0.00 (Oct'23) Work could not be started due to site is not handed over by the client department. Detail Report
Graph / Photo
272 Restoration of service road near Mall and Max hospital of Press Enclave Road cut by DJB under PWD Division South Road-1/ Sub Division SR-14, New Delhi during 2022-23. 2022.12.30 2023.01.29 0.00 (Dec'23) Work completed Detail Report
Graph / Photo
273 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 2016.01.17 2016.04.30 80.00 % (Jul'16) polycarbonate Detail Report
Graph / Photo
274 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 2016.05.01 2016.06.30 0.01 % (Jul'16)

work in progress

Detail Report
Graph / Photo
275 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 2016.04.10 2016.06.09 0.01 % (Jul'16)

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
Graph / Photo
276 Construction of new boundary wall 2016.04.24 2016.07.20 21.77 (May'17) 100.00 % (May'17) Detail Report
Graph / Photo
277 Repair and renovation of toilets 2016.06.17 2016.08.15 91.00 % (Sep'16) Detailed estimate under process. Detail Report
Graph / Photo
278 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 2016.06.16 2016.09.13 53.00 % (Sep'16)

T.S. under process.

Detail Report
Graph / Photo
279 Acoustic treatment system and renovation of multipurpose hall. 2017.10.20 2018.01.17 40.27 (Nov'21) 0.00 (Nov'21) 65% (Work is delayed due to ongoing electrical work as well as Covid-19) Detail Report
Graph / Photo
280 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 2018.11.02 2019.11.01 214.77 (Sep'19) 0.00 (Sep'19) Work in progress Detail Report
Graph / Photo
281 Installation of Rain Water Harvesting System with bore well in GGSSS Roop Nagar No 3 School Delhi 2019.03.07 2019.04.06 Work In Progress Detail Report
Graph / Photo
282 Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. 2019.07.24 2021.09.22 in progress. Detail Report
Graph / Photo
283 Maintenance of P.C. in Division and Sub-Division Office 2021.07.31 2023.07.30 work in progress Detail Report
Graph / Photo
284 Comprehensive architectural consultancy services for Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Jaffarpur Kalan, Nangli Sakrawati and Qutubapur (Sainik Vihar) New Delhi. (Package-1) 2021.10.04 2022.10.03 51.25 (Mar'23) 0.00 (Feb'24) Agmt. No. 04/EE/Edu. (M)/South-west/2021-22 received from EE (Edu.) South West, PWD, Sector-6, Dwarka, New Delhi. Agency yet to submit the terrace floor and other misc. drawings. Detail Report
Graph / Photo
285 Construction of front office of South West DLSA Near Facilitation Centre and Providing Movable Sentry Post at Lockup Premises at District Court Sector-10, Dwarka, New Delhi 2024.01.01 2024.01.31 7.06 (Dec'22) 0.00 (Dec'22) work in progress Detail Report
Graph / Photo
286 Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 2021.12.15 2022.06.14 274.83 (Mar'23) 0.00 (Oct'23) Work In Progress. Site available in Parts. Detail Report
Graph / Photo
287 Construction of Hospital at Hastsal, New Delhi 2021.06.17 2023.06.16 1643.90 (Jun'23) 0.00 (Mar'24) The brick work, AAC Block, Tile, Granite, Waterproofing, Sanitary & water supply work upto 5th floor is in progress. Detail Report
Graph / Photo
288 C/o East Delhi Campus of Guru Gobind Singh Indrasprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Supply, Installation, Testing & Commissioning of CCTV). 2021.03.30 2021.07.28 222.63 (Jun'23) 0.00 (Jun'23) Inventory verified by the Client Department. Some observations i/e minor repair conveyed by the Client Department. Rectifications conveyed to the working agency. Final bill to be submitted by the working agency alongwith EOT part-1. Detail Report
Graph / Photo
289 C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) 2019.09.04 2021.03.03 632.27 (Mar'23) 0.00 (Mar'23) work in progress Detail Report
Graph / Photo
290 Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi 2019.06.30 2019.08.29 26.71 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
291 Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi 2022.10.06 2023.04.05 Work delayed due to not handing over site / electrical work Detail Report
Graph / Photo
292 Providing fencing around the small plants in Central Park of Dr. BSA Residential complex 2022.06.09 2022.08.08 Detail Report
Graph / Photo
293 Repairs & maintenance of Resource Center for Children with special needs: 1208014--Partap Nagar-SKV 2022.06.30 2022.08.30 Work in Progress Detail Report
Graph / Photo
294 Running and Maintenance and supply of Fittings for Newly constructed Covid Hospital 2022.04.14 2023.04.07 6.88 (Aug'22) 0.00 (Aug'23) Detail Report
Graph / Photo
295 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 2022.05.01 2024.04.30 357.33 (Mar'23) 0.00 (Mar'24) work in porgress Detail Report
Graph / Photo
296 Construction of cycle stand, toilet room, sport room and development of rain water harvesting and other misc. work at RSBV Jheel Khuranja Delhi-110031 (School ID1003003) 2022.03.30 2022.06.29 0.00 (Jan'24) work in progress. 60% work has been done. Detail Report
Graph / Photo
297 Providing and Fixing Bullet Proof Protective Posts 03 Nos at different locations of Delhi Secretariat 2022.06.26 2022.08.09 work in progress & testing required. 95% work has been done. Detail Report
Graph / Photo
298 Strengthening of damaged beams and slabs Beautification of main gates Development of pathways and misc works 2022.03.03 2022.09.02 work in progress. 92% has been done. Detail Report
Graph / Photo
299 Re-construction of boundary wall of school 2023.12.14 2024.05.11 work in progress Detail Report
Graph / Photo