Building - Construction Workभवन - रखरखाव का कार्य
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis 2014.08.27 2017.02.26 54511.43 1039.10 (Feb'23) 0.00 (Feb'23) Larson & Toubro Limited Minor rectifications & left out works is under progress. Detail Report
Graph / Photo
2 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 2021.09.23 2022.02.22 40775.18 9915.49 (Mar'23) 0.00 (Mar'23) SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. Detail Report
Graph / Photo
3 CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. 2020.08.10 2023.05.09 38439.53 15429.40 (Mar'23) 0.00 (Mar'23) Ramacivil India Construction Private Limited work in progress Detail Report
Graph / Photo
4 Construction of Hospital at Jwalapuri, New Delhi 2020.08.07 2022.08.13 26950.37 7029.55 (Mar'23) 0.00 (Mar'23) Parnika Commercial and Estates Pvt. Ltd. Structure RCC work completed. Flooring work, masonry work, façade work, road work, water proofing, gypsum plaster etc. & electrical work is in progress. Detail Report
Graph / Photo
5 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works 2017.08.09 2019.11.09 23127.43 6589.16 (Mar'23) 0.00 (Mar'23) NKG Infrastructure Limited Physical Progress of the work is 98%. Detail Report
Graph / Photo
6 Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 2019.10.04 2020.07.03 14316.00 1610.31 (Mar'23) 0.00 (Mar'23) Quality Buildcon Pvt. Ltd. 140 Temporary court rooms at Karkardooma, Saket and Tis Hazari The Work is in progress with upto date progress is approx. 99.5%. (i) Karkardooma: The work is completed and inaugurated on 13.05.2022, possession taken on 26.08.22. Keys have been taken over by caretaking branch during the course of third week of November. (ii) Saket: The work is completed, courts made functional dated 01.09.22. Some additional work has been proposed by court authorities which has been started and will be completed by January. (iii) Tis Hazari: Work is completed and defect rectification work is underway and final furniture placing, interconnection of fiber cable between old & new building is in progress. Fire clearance obtained dated 14.10.22. Some additional work has been proposed by court authorities has also been completed and the building has been made ready for handover pending certain costly fixtures which will be fixed and final testing and commissioning of all services will be completed within 10 days, once the security personnel are provided by the district court authorities. An estimate regarding basic housekeeping and security had also been sent to the court authorities and to the dedicated maintenance wing to facilitate the handover as well. 15th December is the tentative date of handing over to the district court authorities as decided during site visit dated 5th December however, security protocol is yet to be given. Certain minor defects were pointed out by court authorities again during 30.12.22 visit which will be rectified by year end and building will be tentatively handed over during 15 Feb 2023. Detail Report
Graph / Photo
7 Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 2019.12.10 2020.06.01 13992.80 2103.50 (Mar'23) 0.00 (Mar'23) Kamladitya Construction Private Limited OPD block is completed. The deceision of Health Ministry for change in scope of work is awaited. Detail Report
Graph / Photo
8 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 2019.10.18 2021.04.10 13447.15 3634.52 (Feb'23) 0.00 (Feb'23) Roshan Real Estate Pvt Ltd. Work is under progress. Detail Report
Graph / Photo
9 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 2020.03.04 2021.09.03 10708.84 3123.00 (Mar'23) 0.00 (Mar'23) Quality Buildcon Pvt. Ltd. work in progress Detail Report
Graph / Photo
10 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 2019.09.04 2021.03.03 7122.09 1553.62 (Mar'23) 0.00 (Mar'23) PNSC Infrastructure Pvt. Ltd work in progress. Detail Report
Graph / Photo
11 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 2019.08.06 2020.10.29 6563.40 1224.21 (Mar'23) 0.00 (Mar'23) PNSC Infrastructure Pvt. Ltd Work is under progress. Detail Report
Graph / Photo
12 C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) 2019.01.14 2019.11.09 4874.05 5266.38 (Mar'23) 0.00 (Mar'23) Shri kamal singh Work in progress Detail Report
Graph / Photo
13 C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) 2019.01.20 2019.11.15 4603.38 4716.31 (Mar'23) 0.00 (Mar'23) Sh. Kamal Singh Work in progress Detail Report
Graph / Photo
14 Const 182 Nos. of additional SPS class rooms (Package-C) 2019.03.17 2019.12.11 3699.32 3727.61 (Feb'23) 0.00 (Feb'23) SPS Infrabuild Pvt. Ltd. Work completed. Detail Report
Graph / Photo
15 Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 2018.12.24 2019.09.19 3675.76 3278.89 (Jan'23) 0.00 (Jan'23) RAMA Contractor Work completed. Detail Report
Graph / Photo
16 Const 180 Nos. of additional SPS class rooms (Package-B) 2019.03.17 2019.12.11 3636.43 19151.12 (Oct'22) 0.00 (Oct'22) RAMA Contractor Handed over to HOS. Detail Report
Graph / Photo
17 Const 174 Nos. of additional SPS class rooms in various schools (Package-E) 2019.03.17 2019.12.11 3553.31 3181.90 (Mar'23) 0.00 (Mar'23) SPS Infrabuild Pvt. Ltd. Handed over to HOS Detail Report
Graph / Photo
18 Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. 2019.11.14 2021.02.13 3541.69 863.13 (Jan'23) 0.00 (Jan'23) Tewatia Construction Pvt. Ltd. work in progress Detail Report
Graph / Photo
19 Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes 2022.12.24 2023.06.23 3483.10 261.11 (Mar'23) 0.00 (Mar'23) OPTIMUM SECURITY SOLUTIONS PVT. LTD. Work in progress Detail Report
Graph / Photo
20 Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 2019.03.17 2019.12.11 3455.84 3857.92 (Mar'23) 0.00 (Mar'23) RAMA Contractor Work completed. Detail Report
Graph / Photo
21 Civil work and Internal E.I. work 2007.04.24 2009.07.23 3002.21 Globe Civil Project Pvt. Ltd. Detail Report
Graph / Photo
22 SKV Sangam Vihar J Block Sch. ID 1923346 2019.03.17 2019.12.11 3002.10 3233.23 (Mar'23) 0.00 (Mar'23) Devinder Singh Work is in progress Detail Report
Graph / Photo
23 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. 2022.10.17 2023.10.16 3000.18 395.49 (Feb'23) 0.00 (Feb'23) Jai Bhagwan Plinth beam & stilt floor column in progress. Detail Report
Graph / Photo
24 Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi 2020.05.29 2021.05.28 2931.78 4167.17 (Mar'23) 0.00 (Mar'23) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
25 SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW 2019.10.17 2020.07.12 2849.35 2549.96 (Feb'23) 0.00 (Feb'23) A. K. Builders work in progress. Detail Report
Graph / Photo
26 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 2019.06.28 2020.06.22 2806.33 268.76 (Feb'23) 0.00 (Feb'23) Roshan Real Estate Pvt Ltd. Work in progress (40% progress) Detail Report
Graph / Photo
27 Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. 2022.10.11 2023.09.05 2783.15 559.78 (Mar'23) 0.00 (Mar'23) DND Infra Private Limit Pile work & Block-1 plinth beam steel binding in progress. Boundary wall lintel beam in progress & drain work completed. Detail Report
Graph / Photo
28 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 2021.08.23 2022.05.22 2373.12 965.09 (Mar'23) 0.00 (Mar'23) M/s PK Gupta & Co. RCC work of Admin cum Rest Room, Toilet Block, Workshop buildings are in progress. Work is being hampered due to : 1) Non availability of permission from SDM office for playing of Good Earth truck. 2) Progress of work effected due to NGT construction ban. Detail Report
Graph / Photo
29 SBV Jonapur, School ID: 1923359 2018.12.08 2019.08.04 2342.87 1530.26 (Mar'23) 0.00 (Mar'23) Reliance Elektrik works Work is in progress Detail Report
Graph / Photo
30 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 2020.05.31 2021.05.30 1874.70 1314.56 (Mar'23) 0.00 (Mar'23) SSP Promoters and Builders Private Limited WORK IN PROGRESS Detail Report
Graph / Photo
31 Furniture Work RECALL 2019.11.04 2019.12.18 1858.08 6.26 (Sep'21) 0.00 (Sep'21) Rajdhani Furnitures PVT. LTD. Detail Report
Graph / Photo
32 Co Hostel Bldg inclu External Development works Internal Elect Installation External Lighting lifts fire fighting system fire alarm with PA System CCTV Audio video system HVAC works 2023.02.27 2024.07.26 1839.86 KALYAN CHANDRA GOYAL & CO. v Detail Report
Graph / Photo
33 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 2022.04.01 2023.02.24 1798.93 215.60 (Mar'23) 0.00 (Mar'23) K. L. ARORA & SON St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. Detail Report
Graph / Photo
34 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 2018.12.29 2019.07.26 1743.19 4490.50 (Dec'22) 0.00 (Dec'22) AMAR CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
35 Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi 2021.03.08 2021.11.02 1583.17 773.07 (Dec'22) 0.00 (Dec'22) Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 90% Detail Report
Graph / Photo
36 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 2022.03.26 2023.02.19 1553.88 518.51 (Mar'23) 0.00 (Mar'23) K L Arora & Son St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. Detail Report
Graph / Photo
37 Construction of 80 Nos G plus 3 equivalent SPS Class Rooms at Govt Co Ed Sr Secondary School Gandhi Brahampur Delhi including 8 toilet blocks, 4 nos staircase 1 lift and internal and external water supply sanitary installations, electrical installations, development of site, RWH & UGR fire fighting system etc. 2022.03.26 2023.02.19 1377.43 K. L. ARORA & SON Work foreclosed. Detail Report
Graph / Photo
38 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 2022.04.02 2023.02.25 1359.28 486.49 (Mar'23) 0.00 (Mar'23) K. L. ARORA & SON Columns of Block-3 from 1st floor level to 2nd level in progress. In Block-1, Reinforcement binding of raft in progress. Plinth beams & column casting in progress in Block-2. Work delay due to insufficient labour & resources. Detail Report
Graph / Photo
39 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 2022.03.12 2023.02.04 1275.84 174.07 (Feb'23) 0.00 (Feb'23) M/s SURENDRA KUMAR Work in progress Detail Report
Graph / Photo
40 GGSS No. 3 Sec IV, Ambedkar Nagar 2016.03.03 2016.07.15 1212.87 Devinder Singh completed Detail Report
Graph / Photo
41 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Non-Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi). 2021.07.11 2021.09.23 1118.83 35111.01 (Mar'23) 0.00 (Mar'23) M/s Rajdhani Furnitures Pvt. Ltd. 99.6% work physically completed. Detail Report
Graph / Photo
42 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 2022.04.06 2025.04.05 1099.29 53.87 (Oct'22) 0.00 (Oct'22) SIKKA ASSOCIATES REGD. The proposal was submitted to VC, Delhi Sports University as on . The approval has been communincated as on dated . The PE has been submitted by the consultant and same is under scrutiny. Detail Report
Graph / Photo
43 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 2022.04.18 2023.03.13 1090.67 491.93 (Mar'23) 0.00 (Mar'23) K. L. ARORA & SON In Block A, Plinth beam & casting of columns in progress. In Block -B, columns from 1st floor level to 2nd floor level in progress. Work delay due to insufficient labour & resources. Detail Report
Graph / Photo
44 C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. 2023.03.09 2024.02.01 1058.78 AMOCON After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023 Detail Report
Graph / Photo
45 Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. 2018.12.15 2019.06.12 827.90 430.96 (Jan'23) 0.00 (Jan'23) S. P. Construction Work in progress Detail Report
Graph / Photo
46 Civil and Electrical Work. 2023.03.05 2023.11.29 617.03 CHANDRA CONSTRUCTION COMPANY Detail Report
Graph / Photo
47 Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. 2019.01.10 2019.07.08 585.53 123.30 (Dec'22) 0.00 (Dec'22) P S ASSOCIATES work in progress Detail Report
Graph / Photo
48 Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB 2022.09.25 2023.01.24 583.83 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
49 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 2022.01.28 2022.12.27 579.95 261.54 (Nov'22) 0.00 (Nov'22) R.K ENTERPRISES Work is in progress 3% Detail Report
Graph / Photo
50 Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 2014.09.30 2015.05.26 474.90 61.36 (May'19) 0.00 (May'19) Work completed on 31/12/2017 final payment yet to be made Detail Report
Graph / Photo
51 Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 2022.04.02 2022.09.28 462.00 283.40 (Feb'23) 0.00 (Feb'23) PRATAP SINGH Detail Report
Graph / Photo
52 Providing services of Computer Operators MTS and Drivers etc 2022.05.06 2023.05.05 441.58 359.16 (Mar'23) 0.00 (Mar'23) M/s R D Excellent Services Pvt. Ltd. work in progress Detail Report
Graph / Photo
53 C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) 2022.03.02 2022.11.26 382.04 M/s. Satyam Construction work is in progress Detail Report
Graph / Photo
54 Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system 2015.05.26 2016.05.25 316.66 Sudesh Kumar Work is completed except fittings and fixtures due to delay in taking over of DGD by DGHS. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Client being requested regularly. Detail Report
Graph / Photo
55 Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi 2018.12.27 2019.04.26 296.85 335.77 (Aug'21) 0.00 (Aug'21) Ram Krishan Yudhister Parkash

work completed

Detail Report
Graph / Photo
56 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 2019.02.28 2019.06.27 294.21 58.25 (Feb'22) 0.00 (Feb'22) AASRA Martech Pvt.Ltd. Work in progress. Detail Report
Graph / Photo
57 Civil and Electrical work. 2019.05.05 2020.03.04 292.64 Dheeraj Singh & Company Work just awarded Detail Report
Graph / Photo
58 Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). 2022.08.09 2023.08.08 292.57 8.79 (Mar'23) 0.00 (Mar'23) Nand gopal Gupta Detail Report
Graph / Photo
59 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 2022.01.16 2024.10.15 288.00 Arcop Associates Pvt. Ltd. Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval. Detail Report
Graph / Photo
60 Comprehensive architectural consultancy services for Construction of SPS School of Specialized Excellence (SoSEs) Buildings (G Plus 3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Lajpat Nagar, Hari Nagar, Karol Bagh, Gandhi Nagar & Nand Nagri (Package-A) 2022.07.20 2023.07.19 286.66 Design Accord Consultant Tenders for appointment of Architectural Consultants on Q.C.B.S. were invited in two packages one each for Pucca Construction and for SPS construction and accordingly M/s Design Accord Consultants were awarded the work. M/s Design Accord Consultants had visited all the sites of Package-A & B and have prepared initial proposal for presentation and formal approval Date & Time yet to be fixed by the DoE to present the proposal by the consultant at Directorate of Education in presence of all stake holders. Detailed presentation has been made on 06.01.2023 in Directorate of Education. Modified proposal / Presentation after incorporating suggestion of HOS /DDE /DoE being resubmitted shortly. Detail Report
Graph / Photo
61 Construction prefab hut for HQ at PTS Wazirabad, Delhi 2018.07.21 2018.11.20 285.56 Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
62 Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi 2022.12.26 2023.05.24 267.31 50.47 (Mar'23) 0.00 (Mar'23) Sham Lal Gupta and Sons the work has been recently awarded to the agency. the design acoustics Treatment for Basketball Hall submitted by the agency and the same is under checking Detail Report
Graph / Photo
63 Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool 2020.12.23 2021.06.20 262.79 54.92 (Feb'23) 0.00 (Feb'23) Maa Narayan Constuction Co. 62% Detail Report
Graph / Photo
64 Construction of Boundary at vacant land measuring 10 Bigha 02 Biswa, bearing Khasra No. 39/5 & 39/6 situated in village Madanpur Dabas Distt. North West Through PWD, GNCTD 2022.12.17 2023.04.16 178.08 Sarthak Construction Co. The work held up due to non-demarcation of boundaries by the Revenue Authority. Detail Report
Graph / Photo
65 Vertical Extension of Teaching Block No.1 of B.R. Ambedkar College, Wazirabad Road, Delhi 2018.01.16 2018.07.15 172.40 127.50 (Jan'22) 0.00 (Jan'22) JABIR HUSSAIN

work completed

Detail Report
Graph / Photo
66 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Providing & fixing industrial kitchen equipments in Boy's, Girl's & Teacher's Hostel) 2021.12.02 2022.03.01 157.41 Simple Enterprises WORK DOES NOT PERTAIN TO THIS DIVISION Detail Report
Graph / Photo
67 Providing and Installing Fire Fighting, Fire Alarm system and Public Address system 2014.08.10 2015.04.09 155.31 Detail Report
Graph / Photo
68 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 2019.01.25 2019.05.24 140.44 216.46 (Oct'21) 0.00 (Oct'21) Uma Shankar work in progress Detail Report
Graph / Photo
69 Construction of prefab hut for HQ of Meghalaya Police along with development work located at PTS Wazirabad, Delhi 2018.07.15 2018.11.14 134.50 138.77 (Jan'22) 0.00 (Jan'22) Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
70 Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) 2022.04.23 2023.01.22 124.05 9.97 (Feb'23) 0.00 (Feb'23) Dheeraj Singh & Company Detail Report
Graph / Photo
71 Changes in infrastructure of CHB to develop it as OHB Model Home.(Civil and Electrical work) 2019.10.24 2020.02.23 112.72 20.64 (Dec'22) 0.00 (Dec'22) Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 Detail Report
Graph / Photo
72 Attending Day-to-Day complaint in Mandoli Jail complex and residential area including Supply of Material, Horticulture Operation, STP operation and tank and drain cleaning 2022.06.08 2023.06.07 112.05 72.40 (Feb'23) 0.00 (Feb'23) M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
73 Providing and supplying tree planters in various places, New Delhi under MLA LAD Fund Scheme 2019.11.04 2019.12.18 91.97 91.97 (Mar'21) 0.00 (Mar'21) Rajeshwar Dayal Pandey Detail Report
Graph / Photo
74 Designing Manufacturing Installation and Commissioning of ceiling mounted Facade Access System on external facade and inner facade in Atrium at S Block Delhi High Court New Delhi 2022.12.16 2023.03.15 91.53 78.12 (Mar'23) 0.00 (Mar'23) M P BHATIA Work in progress Detail Report
Graph / Photo
75 Construction of Shed with Boxing Ring at Sports Complex, East Vinod Nagar, Delhi 2017.05.08 2017.09.04 84.89 19.39 (Jul'20) 0.00 (Jul'20) Anish Ahmed Work in Progress Detail Report
Graph / Photo
76 Up-gradation of swimming pool and other misc. civil works including electrical work 2021.08.11 2021.12.08 83.39 84.10 (Dec'22) 0.00 (Dec'22) M/s Tanishq Ions In Progress. Detail Report
Graph / Photo
77 C/o GPA for DA Staff at Shalimar Bagh, Delhi 143 Nos. Type-III Qtrs. (SH: Misc. work to make quarters habitable for allotment of 39 Nos. Type-III Qtrs. at Shalimar Bagh dg. 2022-23). 2023.03.23 2023.06.22 83.38 Zahid Hussain Detail Report
Graph / Photo
78 Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) 2022.06.25 2022.08.23 78.59 102.31 (Mar'23) 0.00 (Mar'23) Uma Shankar Detail Report
Graph / Photo
79 Repair and Renovation of toilets of Hon ble Judges Chambers and Public ladies toilet in A Block G plus 3 and staff toilet G plus 6 near to copying agency in J block at KKD Court Delhi Civil and Electrical works 2022.03.13 2022.08.19 76.84 80.97 (Dec'22) 0.00 (Dec'22) Uma Shankar Detail Report
Graph / Photo
80 Renovation of Library Block of IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, New Delhi.(SH-Civil and Electrical works). 2018.07.09 2019.01.08 75.80 77.23 (Jan'22) 0.00 (Jan'22) Kamal Construction Co. Work in progress Detail Report
Graph / Photo
81 Changes in Infrastructure of Model Home to convert it as CHB and JJB in front of Building (Civil and Electrical work). 2019.10.24 2020.01.23 71.13 20.78 (Dec'22) 0.00 (Dec'22) AJAY CONSTRUCTION CO. Detail Report
Graph / Photo
82 Providing and laying RMC in the campus of N, J1, J2, J3, K, L and M Block at Sujan Singh Park, New Delhi under MLA LAD Fund Scheme. 2019.10.27 2019.12.07 70.87 79.44 (May'21) 0.00 (May'21) Gyanchand Detail Report
Graph / Photo
83 Construction of 10 Nos FRP Gazebo rubens and 06 Nos of porta cabin Chaupal at various places of New Delhi Constituency AC40, under MLA LAD Fund Scheme 2019.11.26 2020.01.24 68.77 35.20 (Sep'22) 0.00 (Sep'22) Tripurari Prasad Singh Detail Report
Graph / Photo
84 Construction of boundary wall at Tikri Khurd (Narela Project) for Delhi District Courts, New Delhi 2021.12.19 2022.04.18 68.04 42.85 (Feb'23) 0.00 (Feb'23) Durga Construction Co. Work is in progress Detail Report
Graph / Photo
85 Recarpeting of service road from Peeragarhi Chowk to DTC Depot Nangloi, New Delhi under PWD Division West Road-2 Sub Division WR-23 during 2022-23. 2022.05.27 2022.07.10 67.55 Karambir Rana Builders Detail Report
Graph / Photo
86 SH Work of UTCS Complex Employment exchange JJB Court Working Women Hostel HLTB Complex Sanskar Ashram, Department of Social Welfare and CDMO Shahdara KKD Court Division under SD M 2312 during 2022 23. 2023.01.07 2024.01.06 64.35 Detail Report
Graph / Photo
87 Construction of Recreation Hall at PTS, Wazirabad, Delhi 2019.02.16 2019.06.15 63.80 81.48 (Mar'21) 0.00 (Mar'21) Shekhar

work completed

Detail Report
Graph / Photo
88 Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 2022.02.07 2023.02.06 63.52 48.72 (Feb'23) 0.00 (Feb'23) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
89 Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi 2022.01.22 2023.01.21 62.58 61.96 (Oct'22) 0.00 (Oct'22) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
90 Construction of rain water harwasting system in Main Court Buildings i e in A B C I J K L Blocks and Lawyers Chamber Blocks D E F G H at KKD Court Shahdara Delhi Balance Work 2021.12.18 2022.03.17 59.22 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 In Progress. Detail Report
Graph / Photo
91 Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall 2022.03.14 2022.06.11 59.19 70.85 (Jan'23) 0.00 (Jan'23) Srishti Assosiates Detail Report
Graph / Photo
92 Construction of Boundary wall at vacant lying land measuring 02 Bigha 08 Biswa bearing Khasra no. 86/12/2 (02-08) of Directorate situated in Village-Ladpur (District-North-West) Delhi through, PWD. 2022.08.26 2022.12.23 58.39 Parth Garg The work held up due to non-demarcation of boundaries by the Revenue Authority. Detail Report
Graph / Photo
93 Maintenance and repair work in Mandoli Jail complex, Delhi-110093 during year 2022-23. SH: External and Internal finishing work of Non- Residential Buildings and Residential quarters.2nd call 2022.06.10 2023.03.09 57.65 17.26 (Aug'22) 0.00 (Aug'22) Aamir Khan The work is in progress Detail Report
Graph / Photo
94 Miscellaneous Repair and Renovation works in Toilets Corridor Shafts Flooring in MV Hospital Pooth Khurd Delhi 2022.10.14 2023.01.13 57.52 Sarthak Construction Co. Work in Progress (50% Progress) Detail Report
Graph / Photo
95 Misc repair work under SRD Project Division I Sub Division III PWD New Delhi Recall 2019.09.23 2020.03.22 56.09 70.01 (Feb'21) 0.00 (Feb'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
96 AA to SKV No. 01 Gandhi Nagar Delhi dg 2018 19 2019.03.17 2019.07.16 55.57 32.21 (Jun'20) 0.00 (Jun'20) Arif 90% work in progress Detail Report
Graph / Photo
97 Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi 2021.11.21 2022.02.18 54.92 22.00 (Mar'23) 0.00 (Mar'23) Millennium Furniture Detail Report
Graph / Photo
98 C/o Medical store and Surgical Store in basement area of Indira Gandhi Hospital, Sector-9, Dwarka, New Delhi 2022.09.13 2022.11.11 54.60 0.00 (Jan'23) 20.00 % (Jan'23) DEEPAK CONSTRUCTION AND CO. Work is under progress. Detail Report
Graph / Photo
99 Expansion of 8 no Vulnerable Witness Courts at 5th and 6th floor B Block KKD Courts Delhi and other electrical installations 2022.03.19 2022.05.17 53.14 49.16 (Mar'23) 0.00 (Mar'23) SABUR ALAM Detail Report
Graph / Photo
100 Construction of 5 nos arch shaped FRP pergola, 4 nos FRP porta cabin and 25 nos FRP Security Cabin at various places of New Delhi constituency AC 40 under MLA LAD Scheme 2019.11.26 2020.01.24 51.22 5.64 (May'22) 0.00 (May'22) Tripurari Prasad Singh Detail Report
Graph / Photo
101 Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh 2017.06.27 2017.07.26 50.20 Bansal Builder Agreement closed PG forfeited Detail Report
Graph / Photo
102 False Ceiling, Granite and Wooden Flooring work in court rooms of Shahdara district Karkardooma Court Complex Delhi. Civil and Electrical Work. 2023.03.16 2023.06.13 50.09 M.N Construction Detail Report
Graph / Photo
103 Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block 2022.06.08 2022.09.05 50.04 M. N. Construction Co. Detail Report
Graph / Photo
104 Renovation of 10 Nos faculty rooms of Anatomy at MAMC 2021.05.22 2023.05.22 49.64 14.10 (Jun'22) 0.00 (Jun'22) SABUR ALAM

work completed

Detail Report
Graph / Photo
105 Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi 2022.02.26 2022.03.27 48.15 GEEKEN SEATING COLLECTION PVT LTD Detail Report
Graph / Photo
106 Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi 2022.06.25 2022.08.23 47.61 27.06 (Oct'22) 0.00 (Oct'22) Manish construction and co Detail Report
Graph / Photo
107 Construction of RCC Lift Duct and external development in the front of proposed Lift area 2022.04.17 2022.08.14 43.84 6.34 (Aug'22) 0.00 (Aug'22) TKN Developers Detail Report
Graph / Photo
108 SITC of Building Management System 2020.09.12 2021.03.11 43.49 Digital Controls & Automation Material supplied by the firm. Work is held-up by the agency. Clause 3 notice issued to the agency. Detail Report
Graph / Photo
109 Renovation of Various Rooms (Room No. 417 to 439) in the department of Pathology 4th floor of the UCMS college Block, GTB Hospital, Shahdara, Delhi 2021.12.27 2022.06.24 41.79 SHAMSHAD AHMED Work is in progress Detail Report
Graph / Photo
110 P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). 2022.06.13 2022.09.10 41.34 43.08 (Jan'23) 0.00 (Jan'23) Uma Shankar Detail Report
Graph / Photo
111 Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings incupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) 2022.07.29 2022.09.11 41.32 19.33 (Feb'23) 0.00 (Feb'23) Engineers India Construction Co. Detail Report
Graph / Photo
112 Improvement of lighting in various OTs at GTB Hospital Complex, Shahdara, Delhi. 2019.03.03 2019.05.02 40.46 19.10 (May'19) 0.00 (May'19) CARONA ELECTRICALS Work completed Detail Report
Graph / Photo
113 Water proofing treatment of Main Court Block A Block podium and basement area at Delhi High Court New Delhi 2023.01.07 2023.05.06 40.42 Complete waterproofing system inc. Work in progress Detail Report
Graph / Photo
114 Toilets renovation works 2021.07.09 2021.10.06 40.06 49.76 (Jan'23) 0.00 (Jan'23) Saeed Builders In progress. Detail Report
Graph / Photo
115 Covering of balcony of type-I flats in residential complex of Bhagwan Mahavir Hospital, Pitampura, Delhi. 2022.09.23 2022.11.22 39.90 NAVEEN Work in progress (90% progress) Detail Report
Graph / Photo
116 Up gradation of Type V Judges flats No 402 Type IV Judges flats No 205 Type VI Judge s flats No 607 and Servant Qtrs. 402 607 and 102 at Karkardooma Court Complex Delhi Civil and Electrical Works 2023.01.01 2023.03.31 38.79 Uma Shankar Detail Report
Graph / Photo
117 Improvement Multi Model intigration System at Karkardooma Court Metro Station under M-2111 dg. 2022-23. 2022.07.03 2022.09.30 38.77 Ram Kirpal Singh Detail Report
Graph / Photo
118 Providing Security Guards at North and South Block of New Court Building at District Court Complex, Saket, New Delhi 2022.10.21 2023.01.20 37.99 SS4 SAFENET Detail Report
Graph / Photo
119 EOR in Sanjay Gandhi Memorial Hospital, Delhi. (SH Construction of Badminton Court, Fixing of grill gate, rain water harvesting well to recharge ground water and other misc. works). 2019.08.28 2019.11.27 37.39 SUSHIL KUMAR work is in slow progress Detail Report
Graph / Photo
120 Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings in cupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) 2022.07.29 2022.09.11 35.17 11.76 (Oct'22) 0.00 (Oct'22) Engineers India Construction Co. Detail Report
Graph / Photo
121 Up-gradation and enhancement of aesthetic view of Swimming pool premises located at Captain Hanifuddin G.G.S.S.S. Mayur Vihar Phase-1, Pocket-4, Delhi. 2022.06.03 2022.08.31 35.06 49.30 (Feb'23) 0.00 (Feb'23) Dheeraj Singh & Company Work is under progress. Detail Report
Graph / Photo
122 CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works 2020.08.15 2020.12.14 34.45 CSM CONSTRUCTION Detail Report
Graph / Photo
123 Providing and laying interlocking paver block and RMC in the campus of Police Colony at Tilak Marg, New Delhi under MLA LAD Fund Scheme. 2019.10.27 2019.12.25 33.92 42.37 (Apr'22) 0.00 (Apr'22) Gyanchand Detail Report
Graph / Photo
124 Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system 2019.07.09 2019.10.08 33.85 14.13 (Oct'22) 0.00 (Oct'22) SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. work in Progress 6th RA 18182135 Detail Report
Graph / Photo
125 Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi 2019.08.11 2019.11.10 33.77 19.85 (Mar'23) 0.00 (Mar'23) Med Freshe Pvt. Ltd. Work in progress Med Freshe Pvt. Ltd. Detail Report
Graph / Photo
126 Construction of porta cabins Legal Aid Defence Counsel System office near facilitation centre for Legal Aid Defence Counsel System office Karkardooma Court Delhi. Civil Furniture and Electrical Works 2nd recall 2022.08.31 2022.09.29 33.23 MUZAMMIL ALI Detail Report
Graph / Photo
127 Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) 2021.12.16 2022.04.15 32.92 29.75 (Jan'23) 0.00 (Jan'23) AKSHAY KUMAR DAGAR Detail Report
Graph / Photo
128 Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) 2022.04.05 2022.07.03 32.79 30.24 (Nov'22) 0.00 (Nov'22) Cembond Construction Pvt. Ltd Detail Report
Graph / Photo
129 Granite stone cladding on outer wall and security measures on back side along boundary wall, internal wall finishing in Vivekananda College, Vivek Vihar, Delhi 2022.11.05 2023.03.04 32.71 20.35 (Mar'23) 0.00 (Mar'23) Universal Construction Company Work is under progress. Detail Report
Graph / Photo
130 Providing and fixing retro reflective informatory sign boards at various location of New Delhi constituency AC40 under MLA LAD Fund Scheme 2019.10.25 2020.01.22 32.70 12.66 (Mar'21) 0.00 (Mar'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
131 Renovation and Modification of 32 Nos Chambers of Honble Judge in A Block Delhi High Court New Delhi 2022.09.09 2022.11.07 31.97 106.99 (Jan'23) 0.00 (Jan'23) R L WADHWA Work in progress Detail Report
Graph / Photo
132 Construction of Boundary Wall at vacant plot of Nand Nagri, Delhi 2022.07.12 2022.09.09 31.83 33.43 (Dec'22) 0.00 (Dec'22) Harsh Electricals Work completed. Agency yet to submit final bill. Detail Report
Graph / Photo
133 Construction of Porta Cabin for PWD Sub Divn. Office of Civil and Electrical including enquiries of both and Development of lab collection centre and shed covering 2021.01.06 2021.04.05 31.62 0.00 (Oct'22) 100.00 % (Oct'22) Nation Star Enterprises Work is physically 100% completed. Final bill yet to be submitted by the agency. Detail Report
Graph / Photo
134 Installation of hard drawn wire fabric at D Block and B Block residential quarters for monkey protection in Fire Station Connaught Place New Delhi. 2019.02.08 2019.03.07 31.58 39.47 (Jul'19) 90.00 % (Jul'19) Vasdev Work in progress Detail Report
Graph / Photo
135 Renovation of Kotwali Building at Chandni Chowk, Police Station under SRD Division-I, Sub-Division-III, PWD, New Delhi. 2018.06.25 2018.10.24 31.39 0.00 (Feb'19) 39.16 % (Feb'19) Kamal Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
136 SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi 2018.10.16 2018.12.15 30.64 15.29 (Feb'19) 50.00 % (Feb'19) San Infotech Services work in progress 2nd RA 1696099 Detail Report
Graph / Photo
137 Providing and fixing furniture at Ground Floor and 1st Floor 2021.08.15 2021.08.29 30.45 33.54 (Mar'22) 0.00 (Mar'22) DURIAN INDUSTRIES LIMITED In progress. Detail Report
Graph / Photo
138 Renovation of toilets in J, K & L Block at Karkardooma Court, Delhi (Balance work) (IstRecall) 2021.12.30 2022.03.29 30.36 20.96 (Nov'22) 0.00 (Nov'22) Ravinder Kumar Gupta In Progress. Detail Report
Graph / Photo
139 Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 2021.12.17 2022.04.15 29.81 28.23 (Feb'23) 0.00 (Feb'23) Cembond Construction Pvt. Ltd In Progress. Detail Report
Graph / Photo
140 Comprehensive Maintenance of Old Saint Stephens College Building Kashmere Gate, CPO Building, Old Court Building, NCC Offices Buildings, Novelty Fire Station, Fire Station Jama Masjid, Disability Commissioner Office, Lok Nayak Setu Office Compl 2019.11.17 2020.11.16 29.01 36.24 (Feb'21) 0.00 (Feb'21) K.P. Singh & Co. Detail Report
Graph / Photo
141 Urgent Repair and rehabilitation of newly allotted Qtrs. after vacation of E Type Qtrs. in the Residential Campus, GTB Hospital, Shahdara, Delhi 2022.05.21 2022.09.17 28.76 SANENDRA KUMAR Work is in progress Detail Report
Graph / Photo
142 Painting in Outer side of Court building Administrative Block and Lawyer Chamber Block-II, Delhi High Court New Delhi 2023.01.12 2023.04.11 28.19 17.92 (Mar'23) 0.00 (Mar'23) IRFAN KHAN AND CO. Work in progress Detail Report
Graph / Photo
143 Making Accessible approach. Balance Work 1st recall 2022.09.24 2022.12.22 27.32 Shobhit Kumar Detail Report
Graph / Photo
144 Rehabilitation work in Police Station at Chandni Mahal, Asaf Ali Road, Delhi. 2019.09.29 2020.03.26 27.08 33.83 (Mar'21) 0.00 (Mar'21) Shah Pandya & Shot Crete Detail Report
Graph / Photo
145 Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi 2022.06.13 2022.08.11 26.85 90.32 (Mar'23) 0.00 (Mar'23) Uma Shankar Detail Report
Graph / Photo
146 Civil work, false ceiling, flooring and finishing work at Multilevel Car parking in Delhi High Court, New Delhi. 2023.03.12 2023.06.10 25.91 Yameen Work in progress Detail Report
Graph / Photo
147 Construction of 01 Nos. Clinical care centre under School Health Scheme on the vacant piece of land between Babu Ram Govt. SBV Bhola Nath Nagar and DIET Shahdara. (Civil, Furniture & Electrical Works). (4th Recall) 2022.09.16 2022.11.14 25.77 30.48 (Feb'23) 0.00 (Feb'23) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
148 Construction of yard for Malkhana of Police Station Chandni Mahal, Darya Ganj under SRD Division-I, Sub-Division-III, New Delhi. 2018.07.30 2018.10.29 25.67 23.27 (Sep'19) 0.00 (Sep'19) Krishan Kumar Work in progress Detail Report
Graph / Photo
149 Repair and renovation of Veterinary Dispensary, Bankner, Animal Husbandry Unit of GNCT of Delhi-110040 2022.08.01 2022.10.30 24.62 25.89 (Feb'23) 0.00 (Feb'23) Ankur Bhardwaj Work in Progress Detail Report
Graph / Photo
150 SITC of Lifts. 2023.02.21 2023.05.20 23.60 Techno Industries Limited Detail Report
Graph / Photo
151 Renovation & Up-gradation in Residential Quarters in SRHC hospital, Narela 2022.07.05 2022.11.04 23.12 BHUPESH KUMAR Work in Progress (60% Progress) Detail Report
Graph / Photo
152 Providing and laying bituminous concrete surface at BR Campus, Race course, New Delhi under MLA LAD fund Scheme. 3rd CALL 2019.11.26 2019.12.25 22.88 25.04 (Nov'21) 0.00 (Nov'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
153 Development Cricket ground football field and chain link fencing at newly taken over plot for sports complex at village kair in the Assembly constituency Najafgarh, Delhi. (SH: Comprehensive maintenance of cricket ground for one year) 2021.04.01 2022.03.31 22.80 Devender Pal Singh work Completed. Detail Report
Graph / Photo
154 Renovation of B Voc Labs 2019.05.20 2019.08.19 22.14 M.Y Construction 40% Work could not start due to electrical tender not in force. Detail Report
Graph / Photo
155 Re-layering of Damaged Internal Bituminous Roads at Judges Flat including raising of manhole cover, laying of C.C. pavement, paver block & Kerb stone, at Karkardooma Court, Sahadara, Delhi-110032 2022.07.15 2022.08.13 21.86 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
156 Supplying and replacement of Outlived Air Handling Units at JPCH Shastri Park, Delhi 2019.07.22 2019.09.21 21.72 US Engineers

Tender is in process

Detail Report
Graph / Photo
157 Providing and Fixing of MS tubular Window with Acrylic plastic Sheet 2019.11.14 2020.03.12 21.53 26.89 (Mar'21) 0.00 (Mar'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
158 Renovation of toilet blocks & miscellaneous civil works- Balance work 2022.06.26 2022.09.23 21.44 Sanjeev Kumar Detail Report
Graph / Photo
159 Expansion of Lawyers Cafeteria in B Block and Shifting of Filing Counter in Administrative Block & Providing and fixing work stations for IT Branch at Lawyers Chambers Block-III of Delhi High Court New Delhi. 2023.03.07 2023.04.05 21.18 R L WADHWA Work in progress Detail Report
Graph / Photo
160 Up-gradation of Type-V Judge’s flats No- G-1 Type-VI Judge’s flats No-507 and Servant Qtrs. G-1 & 507 at Karkardooma Court Complex, Delhi. (SH:- Civil Work). 2022.05.02 2022.06.30 21.17 26.26 (Mar'23) 0.00 (Mar'23) Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
161 Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex 2022.06.08 2022.09.05 20.86 Karan Walia Detail Report
Graph / Photo
162 Balance Structural Strengthening works 2022.09.11 2022.10.10 19.92 Cembond Construction Pvt. Ltd Detail Report
Graph / Photo
163 Repair Renovation of Gents Ladies Staff toilet general girls toilet and CWSN toilet block at Sarvodaya Kanya Vidyalaya Prahladpur Banger Delhi (School ID 1310032) 2022.10.21 2022.12.05 19.90 M/s R M constrution Work in progress Detail Report
Graph / Photo
164 Constn. of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi 2022.03.20 2022.07.17 19.68 Sanender Kumar Work is in progress Detail Report
Graph / Photo
165 Mechanized cleaning of Underground and Overhead RCC/ PVC water storage tanks at Rajiv Gandhi Super Specialty Hospital, Tahirpur, Delhi. 2022.04.26 2023.04.25 19.49 14.10 (Feb'23) 0.00 (Feb'23) Real Aqua Hygiene Solution Work in progress. Detail Report
Graph / Photo
166 Operation and maintenance of compost machines installed in various jail at Prison Complex Mandoli Delhi (4th Call) 2022.09.26 2023.09.25 19.02 Clean India Ventures Pvt. Ltd. Work is in progress Detail Report
Graph / Photo
167 SITC of CCTV in various Mohalla Clinic under sub division M3513 2022.04.13 2022.05.12 18.93 YASH ENTERPRISES Detail Report
Graph / Photo
168 Renovation of toilets in J K and L Block at Karkardooma Court Delhi Balance work 2021.11.06 2022.02.03 18.82 Phoenix Constructions In Progress. Detail Report
Graph / Photo
169 Provision of chequrred tiles, raising of boundary wall and other misc civil work 2022.06.26 2022.07.25 18.67 21.25 (Dec'22) 0.00 (Dec'22) Sanjeev Kumar Detail Report
Graph / Photo
170 SITC of VRV/ VRF Air Condition Plant 2022.06.12 2022.07.11 18.55 12.64 (Sep'22) 0.00 (Sep'22) Airtemp Engineers Detail Report
Graph / Photo
171 Renovation of toilets gutter fixing and barricading work. 1st recall 2022.08.21 2022.12.18 18.07 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
172 Renovation of Ladies Bar Association Room at KKD Courts Delhi. Civil Furniture and Electrical Works 1st recall. 2023.02.12 2023.03.28 18.05 Detail Report
Graph / Photo
173 Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) 2022.04.01 2022.06.29 17.32 19.11 (Dec'22) 0.00 (Dec'22) SABUR ALAM Detail Report
Graph / Photo
174 Const. of office building for Sub Division III SRD Project Divn I at Road No. 47 near Metro Pillar No. 29, Kashmere Gate, Delhi 2019.09.23 2019.12.21 17.04 21.26 (Jul'20) 0.00 (Jul'20) K.P. Singh & Co. Detail Report
Graph / Photo
175 Construction of Conference Hall and Waiting/Reception Hall in Office of Commissioner for Persons with Disabilities at Mata Sundari Road under SRD Division-I, Sub-Division-III, PWD, New Delhi. (SH-Civil Renovation Work). 2018.08.09 2018.11.08 16.72 15.33 (Oct'19) 5.60 % (Oct'19) Intkhab Alam Work in progress Detail Report
Graph / Photo
176 Construction of Record Room in Basement of Main Court Building, Saket Court Complex, New Delhi. 2022.07.18 2022.10.17 16.50 20.37 (Jan'23) 0.00 (Jan'23) M Y CONSTRUCTIONS Detail Report
Graph / Photo
177 Construction of missing drain from Jain Nagar Cygnus Hospital upto 40ft road (218mtr) towards Mangolpuri under Sub Division WR-22 during 2022-23. 2023.01.07 2023.03.07 16.29 P L Construction Detail Report
Graph / Photo
178 A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) 2017.04.13 2017.10.12 16.04 7.45 (Mar'19) 46.00 % (Mar'19) Anup Enterprises Detail Report
Graph / Photo
179 Construction of Rain Water Harvesting Pit inside ITI Campus and ITI Staff Quarter, Vivek Vihar, Delhi. 2022.07.15 2022.10.12 15.37 Shivam Builders Detail Report
Graph / Photo
180 SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. 2018.11.07 2019.02.04 15.26 17.61 (Apr'22) 0.00 (Apr'22) Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 in progress. Detail Report
Graph / Photo
181 Providing and supplying plastic moulded table in porta cabins reading room at various places of New Delhi Constituency AC40 under MLA LAD Fund Scheme. 2019.10.25 2019.12.08 15.17 DECOR MODULAR SYSTEM PVT LTD Detail Report
Graph / Photo
182 Upkeep Service 2019.10.05 2020.10.04 15.15 19.17 (Sep'22) 0.00 (Sep'22) Ashish Gupta Detail Report
Graph / Photo
183 Accessibility works 2022.08.06 2022.10.04 15.09 12.07 (Nov'22) 0.00 (Nov'22) M T Builders Detail Report
Graph / Photo
184 Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work 2022.05.29 2022.08.26 14.87 18.56 (Dec'22) 0.00 (Dec'22) Sushil Kumar Detail Report
Graph / Photo
185 Construction of porta cabin for camp office of Honble Minister at DJB (BPS/UGR) at C-6, Vasant Kunj, New Delhi 2022.01.04 2022.02.03 14.34 32.27 (Jan'23) 0.00 (Jan'23) SHRI DATTA KRUPA ENTER PRISES Detail Report
Graph / Photo
186 Addition & Alteration to Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and fixing roller blinds & cubical track system). 2023.02.22 2023.04.22 13.92 0.64 (Mar'23) 0.00 (Mar'23) Oliver Wallpapers Work is under progress. Detail Report
Graph / Photo
187 Construction of Underground sump at ITI Jija Bai for Women, Sirifort, New Delhi (Civil and Electrical work) 2021.10.23 2021.12.22 13.91 20.16 (Sep'22) 0.00 (Sep'22) SHRI DATTA KRUPA ENTER PRISES Detail Report
Graph / Photo
188 Repair/ improvement of berm, footpath and drain at Jaipur Golden Hospital, Sector-3, Rohini 2022.04.27 2022.07.26 13.86 17.21 (Sep'22) 0.00 (Sep'22) Dharambir Singh Detail Report
Graph / Photo
189 Construction of permanent shed on pavement near Gyne OPD registration 2020.08.18 2020.10.17 13.73 SS Enterprises work in progress. Detail Report
Graph / Photo
190 EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section 2018.04.02 2030.09.15 13.58 L V Enterprises Detail Report
Graph / Photo
191 Shifting of X Ray machine at Gate No 6 and provision of porta cabin at gate No 6 and covering of vehicle session at gate No 03 2019.05.20 2019.07.03 13.40 13.90 (Jan'20) 0.00 (Jan'20) Rajeev Kumar site not available for work 60% Detail Report
Graph / Photo
192 Renovation of gents and ladies toilet and guniting of ceiling of ground, 1st, 4th, 5th and 6th floor of I block, College of Art at Tilak Marg, New Delhi 2019.11.14 2020.02.11 13.30 14.80 (Mar'21) 0.00 (Mar'21) Amiruddin Detail Report
Graph / Photo
193 Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) 2022.05.19 2022.06.17 13.23 19.43 (Dec'22) 0.00 (Dec'22) Jain Electric Works Detail Report
Graph / Photo
194 Repair Renovation of old damaged porta cabins at I block and other miscellaneous work 2022.03.08 2022.05.06 12.65 15.81 (Jul'22) 0.00 (Jul'22) AMIR ISRAR Detail Report
Graph / Photo
195 Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. 2019.02.10 2019.05.10 12.52 13.79 (Jan'20) 0.00 (Jan'20) Daya Sagar Sharma work in progress Detail Report
Graph / Photo
196 Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) 2022.02.02 2022.03.03 12.04 Sanjeev Kumar In progress. Detail Report
Graph / Photo
197 Construction of missing drain from Jain Nagar Cygnus Hospital upto 40ft road (218mtr) towards Mangolpuri under Sub Division WR-22 during 2022-23 2022.08.27 2022.10.25 11.98 M/s Ashok Builders Detail Report
Graph / Photo
198 Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi 2021.12.26 2022.02.23 11.65 11.10 (Feb'23) 0.00 (Feb'23) Sanjeev Kumar In progress. Detail Report
Graph / Photo
199 Construction of parking shed for students and staff and fixing new aluminium windows in corridor of ground floor, 1st floor, 2nd floor, 3rd floor & rooms along with vension blinds at ITI Narela, Delhi-40 2022.10.16 2022.12.15 11.35 S.S. Builders Work in progress Detail Report
Graph / Photo
200 Civil Work. 2023.02.12 2023.05.12 11.21 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
201 Civil Electrical Works 2021.12.10 2022.02.07 11.21 11.94 (Oct'22) 0.00 (Oct'22) Rainbow Constructions In Progress. Detail Report
Graph / Photo
202 Providing and fixing down comer and manually operated electronic FA system 2019.09.19 2019.10.18 11.18 0.00 (Jan'21) 98.00 % (Jan'21) M/s Royale Meridian India Pvt Ltd Work completed. Final bill yet to be paid. Detail Report
Graph / Photo
203 Provision for Rain Water Harvesting Systems in Govt. Girls Sec. School (Urdu Medium) Lambi Gali, Hauz Qazi under SRD Division-I, Sub-Division-III, PWD, New Delhi dg. 2018-19. 2019.07.11 2019.09.10 11.10 1.62 (Mar'21) 0.00 (Mar'21) Shakur Ahmed & Sons Detail Report
Graph / Photo
204 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 1 (Hindi Medium) at Jama Masjid, Delhi dg. 18-19 (School ID-2127024.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 2019.03.11 2019.05.10 11.09 13.85 (Mar'20) 0.00 (Mar'20) Mohd. Asad work in progress Detail Report
Graph / Photo
205 Renovation of toilet blocks at G/F (02 nos.), F/F (02 nos.) & S/F (01 no.) 2022.10.05 2022.12.03 10.79 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
206 Miscellaneous Civil works 2022.05.10 2022.07.08 10.73 8.51 (Sep'22) 0.00 (Sep'22) Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
207 Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi 2022.05.29 2022.06.27 10.53 12.79 (Oct'22) 0.00 (Oct'22) Sundriyal Construction Detail Report
Graph / Photo
208 Construction of Old Age Home at Kanti Nagar Installation of fire doors in the building 2021.03.04 2021.04.02 10.22 11.71 (Aug'21) 0.00 (Aug'21) A. V. ENTERPRISES In progress. Detail Report
Graph / Photo
209 Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans 2022.02.28 2022.08.27 10.14 Dashmesh Enterprises Detail Report
Graph / Photo
210 Construction one no additional toilet at 14/2 Tilak Marg and Renovation of kitchen, toilets and other civil miscellaneous repair works at 36 Ashoka Road under SRD Project Division-I, Sub-Division-IV, PWD, New Delhi 2019.08.11 2019.10.10 9.97 11.78 (Nov'20) 0.00 (Nov'20) Sher Singh Detail Report
Graph / Photo
211 Construction of Two Store Room and renovation of Voter Centre Building Deoli (AC-47), Sector-IV, Pushp Vihar, New Delhi-110017. (Civil and Electrical work) 2022.01.27 2022.03.26 9.07 11.06 (Jun'22) 0.00 (Jun'22) Vision Constructions Detail Report
Graph / Photo
212 Provision for Rain Water Harvesting System in Govt Girls Sr Sec School at Gali Baraf Wali Kinari Bazar Delhi during 2018 19 School ID-1208023 under SRD Division I Sub-Division III PWD New Delhi 2019.07.11 2019.09.10 8.86 9.64 (May'22) 0.00 (May'22) Shakur Ahmed & Sons Detail Report
Graph / Photo
213 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 2 at Zeenat Mahal, Lal Kuan, Delhi (School ID-2127179) under SRD Division-I, Sub-Division-III, PWD, New Delhi 2019.07.14 2019.09.13 8.76 Shakur Ahmed & Sons Detail Report
Graph / Photo
214 Providing services of plumbing, carpentry jobs etc RECALL 2019.11.04 2020.11.03 8.68 8.68 (Mar'21) 0.00 (Mar'21) Good Luck Enterprises Detail Report
Graph / Photo
215 Distempering painting and Finishing works of various Schools under sub divn M 2313 of KKD Court Division M 231 during 2021 22 (Balance work) 2021.12.16 2022.03.15 8.33 7.20 (Jun'22) 0.00 (Jun'22) M T Builders In Progress. Detail Report
Graph / Photo
216 A R and M O to 405 DA Flats Kalyanvas Delhi 91 dg 2018 19 2018.06.18 2019.06.14 8.03 5.04 (Nov'20) 0.00 (Nov'20) SABUR ALAM work in progress 40% Detail Report
Graph / Photo
217 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Upkeep Service). 2018.09.25 2019.09.24 8.01 1.56 (Jan'20) 0.00 (Jan'20) Ashish Gupta Work in progress Detail Report
Graph / Photo
218 Provision for Rain Water Harvesting System in Sarvodaya Bal Vidyalaya at Pataudi House, Darya Ganj, Delhi (School ID-2127003.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 2019.06.25 2019.08.24 7.90 6.08 (Nov'19) 0.00 (Nov'19) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
219 Furniture work 2019.10.25 2019.12.08 7.84 7.84 (Mar'21) 0.00 (Mar'21) DURIAN INDUSTRIES LIMITED Detail Report
Graph / Photo
220 Construction of public toilet near mortuary, providing shed for blood bank and other misc. works. 2020.03.18 2020.05.17 7.80 Sudhakar Samal work in progress Detail Report
Graph / Photo
221 Provision for Rain Water Harvesting System in Govt. Boys Sr. Sec. School No. 2 (Hindi Medium) at Jama Msjid, Delhi (School ID-2127006.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 2019.06.25 2019.08.24 7.66 6.42 (Jan'20) 0.00 (Jan'20) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
222 Wall paneling wooden flooring and toilet renovation work Civil and Electrical works 2022.06.11 2022.07.10 7.36 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
223 Preparation of one room of 2nd and 3rd floor in front of lift gallery and replacement of gallery window of I Block, College of Art at Tilak Marg, New Delhi 2019.11.14 2020.01.12 7.35 9.10 (Feb'21) 0.00 (Feb'21) Amiruddin Detail Report
Graph / Photo
224 Maintenance of EI & Fans and Operation of Pumps & DG Set 2022.09.16 2023.03.15 7.28 RJP Enterprises Detail Report
Graph / Photo
225 Installation of rain water harvesting system 2018.06.02 2018.08.01 7.23 6.04 (Jul'19) 0.00 (Jul'19) Mohd Akram work in progress 70% Detail Report
Graph / Photo
226 Providing inspection vehicles on hire charge basis inspection vehicles for use in office of Executive Engineer, OPD-II and its sub-divisions 2022.09.27 2023.03.26 7.10 3.55 (Jan'23) 0.00 (Jan'23) SKIEZS Work is in progress Detail Report
Graph / Photo
227 A/R and M/O I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Repair and Renovation work of University Staff Quarters at IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi). 2019.03.29 2019.06.28 7.01 Prithvi creation work in progress Detail Report
Graph / Photo
228 Renovation of D Block 1st Floor MP Hall 2019.11.28 2020.01.26 6.80 6.89 (Sep'20) 0.00 (Sep'20) Mohd Amjad Detail Report
Graph / Photo
229 Construction of underground water storage tanks for upcoming Court Rooms with additional storage facility for existing Court Complex and Residential Complex Saket including upgrading of existing water main line feeding Residential Court Complex--- 2023.02.03 2023.03.02 6.57 ARSHAD Detail Report
Graph / Photo
230 Operation and Maintenance of 3x110 TR Capacity HVAC System and Servicing Overhauling and Comprehensive running maintenance of WTAC, Water coolers and Split AC units 2019.04.01 2019.12.31 6.53 7.48 (May'20) 0.00 (May'20) M/s Naj Refrigeration & Air Conditioning Works Detail Report
Graph / Photo
231 Sweeping of road, development of rain water harvesting system, CO sump tank and other misc repair works 2022.08.04 2023.05.10 6.41 2.70 (Oct'22) 0.00 (Oct'22) Suresh Ray Work in Progress Detail Report
Graph / Photo
232 Renovation of Room No. 126, 129 & 132 in Department of physiology of UCMS college at GTB Hospital, Shahdara, Delhi. 2022.08.26 2022.09.24 6.39 PRASHANT BUILDERS Work is in progress. Detail Report
Graph / Photo
233 Replacement of wooden sofa chair with new visitor chairs at I/C E.D. Lockup and miscellaneous furniture work at courts of Shahdara District Branch, KKD Court Delhi 2022.07.09 2022.08.07 6.07 7.32 (Jan'23) 0.00 (Jan'23) Ganpati Furniture System Pvt Ltd Detail Report
Graph / Photo
234 Tentage & sitting arrangement 2022.07.30 2022.08.09 5.68 6.37 (Mar'23) 0.00 (Mar'23) Vishal Tents and Decorators work in progress Detail Report
Graph / Photo
235 Providing and fixing dustbin at Karkardooma Court Complex, Delhi 2022.06.13 2022.07.12 5.66 21.88 (Sep'22) 0.00 (Sep'22) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
236 Raising of boundary wall of Lal quarter Kidwai Nagar residential area under MLA LAD Fund Scheme RECALL 2019.11.04 2019.12.18 5.60 4.89 (Sep'20) 0.00 (Sep'20) B P Rai and Sons Detail Report
Graph / Photo
237 Anti termite treatment of Hostel building and P F commercial ply and Mattress on beds of Hostel block Ist recall 2021.11.21 2022.01.19 5.42 6.45 (Mar'23) 0.00 (Mar'23) Verma Pesticides & Pest Control Services Pvt. Ltd. In progress. Detail Report
Graph / Photo
238 Civil Works 2022.09.01 2022.09.30 5.36 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
239 Construction of Rain water Harvesting System at Govt Boys Sr Secondary School Dev Nagar New Delhi Building ID 21281284 2019.05.30 2019.07.13 5.19 4.90 (Jan'20) 0.00 (Jan'20) Prem Sagar Work completed final bill paid Detail Report
Graph / Photo
240 Construction of Rain water Harvesting System in Sarovodya Kanya Vidyalaya Baba Ram Dev at Prasad Nagar New Delhi Building ID 21281295 2019.05.30 2019.07.13 4.97 5.56 (Nov'19) 0.00 (Nov'19) Prem Sagar Bill paid Detail Report
Graph / Photo
241 Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer 2022.01.31 2022.03.31 4.93 5.35 (Jun'22) 0.00 (Jun'22) PURIFIRES INDIA In Progress. Detail Report
Graph / Photo
242 Providing Furnitures at Ladies Bar Association Room at KKD courts, Delhi. 2023.03.22 2023.04.20 4.88 Uma Shankar Detail Report
Graph / Photo
243 Major repair work on water supply pipe line tanks. 2023.02.11 2023.04.11 4.70 5.87 (Mar'23) 0.00 (Mar'23) Mohd Azam Detail Report
Graph / Photo
244 Construction of one additional toilet for visitors at Camp Office of Honble Minister at C6, Vasant Kunj, New Delhi 2022.10.24 2022.11.23 4.64 MOHAN LAL Detail Report
Graph / Photo
245 Civil Works. 1st Recall 2023.01.06 2023.02.04 4.63 Mohd. WAZID Detail Report
Graph / Photo
246 E.O.R. to repair and replacement of sewer line, rain water disposal line and other misc. repair work in Police Station, Darya Ganj, Delhi dg. 2018-19 (SH- Improvement of drainage system under SRD Division-I, Sub-Division-III, PWD, New Delhi). 2019.02.26 2019.04.25 4.59 5.27 (Jun'19) 0.00 (Jun'19) Prashant Gupta work in progress Detail Report
Graph / Photo
247 Anti termite treatment of Hostel building and PF commercial ply and Mattress on beds of Hostel block 2021.09.29 2021.11.27 4.41 Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 Detail Report
Graph / Photo
248 EOR to Police Colony, Rajinder Nagar, New Delhi during 2018-19.(SH- Covering of open drain in Police Colony). 2018.05.30 2018.07.28 4.37 5.48 (Aug'19) 0.00 (Aug'19) G.S construction wip Detail Report
Graph / Photo
249 Misc. civil repair work 2019.09.15 2019.12.14 4.36 5.44 (Oct'21) 0.00 (Oct'21) Shabbi Abbas Detail Report
Graph / Photo
250 Installation of 1 no. borewell at Fire Station Tahirpur Delhi dg. 2022 23. Civil and Electrical Works 2022.09.21 2022.10.20 3.93 4.26 (Oct'22) 0.00 (Oct'22) Lucky Project Detail Report
Graph / Photo
251 RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. 2019.02.03 2020.02.02 3.91 1.61 (Jul'19) 0.00 (Jul'19) ARORA ELECTRICAL WORKS Detail Report
Graph / Photo
252 EOR to National Law University, Sec-14, under Sub Div-III, SWBMD, New Delhi during 2018-19.(SH- Cleaning of sewerline by using super sucker machine). 2018.06.05 2018.09.02 3.81 3.81 (Dec'18) 70.00 % (Dec'18) Surender Singh Chahal work in progress Detail Report
Graph / Photo
253 Replacement of broken kota stone flooring and wooden racks, false ceiling and white washing of MFA final year Sculpture Studio, College of Art at Tilak Marg, New Delhi 2019.11.15 2019.12.14 3.73 4.31 (Apr'21) 0.00 (Apr'21) Sher Singh Detail Report
Graph / Photo
254 Replacement of broken glass and painting of grills of window providing and fixing of signage board and other misc. work at DIET Building Karkardooma Institutional area Delhi 110032 1st Recall 2022.09.09 2022.10.08 3.59 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
255 Barricading of dangerous portion of old school building, chipping of unsound/weak concrete & demolishing damaged RCC & brick work in Gandhi Memorial School, Shahdara (Near Shyamlal College), Delhi. (1st recall) 2022.08.17 2022.09.15 3.26 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
256 Providing and fixing dustbin at Karkardooma Court Complex Delhi 2021.12.10 2022.01.08 3.10 Saman Mehboob In Progress. Detail Report
Graph / Photo
257 Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23 2022.08.26 2022.09.24 3.06 PRASHANT BUILDERS Detail Report
Graph / Photo
258 Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil and Electrical Works (2nd Recall) 2022.03.19 2022.04.17 2.62 Mohd. WAZID Detail Report
Graph / Photo
259 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate under Sub-Division-III, SRD Division-I, PWD, New Delhi During 2017-18 (SH-Specialized waterproofing treatment in the profile sheet gutter of workshop behind MAE Block). 2018.04.21 2018.05.20 2.62 0.00 (Jul'18) 2.90 % (Jul'18) Garg Waterproofing Company Work Completed and final bill paid Detail Report
Graph / Photo
260 Renovation work 2023.01.13 2023.02.11 2.61 Mohd Azam Detail Report
Graph / Photo
261 Renovation of office of Secretary in DSSSB Building at Karkardooma Shahdara Delhi dg 2022 23 2022.08.03 2022.09.01 2.56 6.25 (Feb'23) 0.00 (Feb'23) Mohd Azam Detail Report
Graph / Photo
262 Providing and erecting permanent barricading around dangerous building in Kasturba Kustha Ashram Tahirpur Delhi 1st recall 2021.12.11 2022.01.09 2.50 2.67 (Jul'22) 0.00 (Jul'22) Akhil Okharwal In Progress. Detail Report
Graph / Photo
263 Installation of Stainless Steel Grill on the window for safety and security of Valuable assets 2022.06.13 2022.07.12 2.29 2.84 (Jun'22) 0.00 (Jun'22) Mohd Azam Detail Report
Graph / Photo
264 Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil Electrical Works Ist Recall 2022.01.08 2022.02.06 2.25 MUZAMMIL ALI Detail Report
Graph / Photo
265 Construction of security gates near entrance road of Church of Divine Mercy in Shakurbasti Assembly Constituency AC-15 under MLALAD scheme, during 2021-2022. (3rd call) 2022.03.24 2022.05.23 2.19 1.13 (Sep'22) 0.00 (Sep'22) A J & CO. Detail Report
Graph / Photo
266 Installation of 1 no. bore well at Fire Station, Tahirpur Delhi dg. 2021 22. Civil and Electrical Works 2021.11.21 2021.12.20 2.16 Sudesh Jain Detail Report
Graph / Photo
267 Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 2022.06.22 2022.07.06 2.08 2.09 (Aug'22) 0.00 (Aug'22) CHETAN SHARMA Detail Report
Graph / Photo
268 A/R and M/O other PWD Roads under SRD Division -I, PWD, New Delhi during 2019-20. (SH- Painting of Kerb Stones on various roads for Independence Day under Sub Division-II.) 2019.08.13 2019.08.27 2.06 2.27 (Nov'19) 0.00 (Nov'19) MOHD AFTAB Detail Report
Graph / Photo
269 A/A to RCL Tahirpur Sunder Nagri, Delhi during 2021-22.SH:- Providing and erecting permanent barricading around the dangerous buildings in Kasturba Kustha Ashram Tahirpur Delhi 2021.09.03 2021.10.02 1.95 Sanjeev Kumar In progress. Detail Report
Graph / Photo
270 SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. 2022.03.25 2022.04.23 1.90 MKSC Design India Private Limited Work in Progress Detail Report
Graph / Photo
271 Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri 2021.09.04 2021.10.03 1.85 0.88 (Mar'22) 0.00 (Mar'22) Sanjeev Kumar Detail Report
Graph / Photo
272 Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner 2021.09.05 2023.09.04 1.81 0.82 (Dec'22) 0.00 (Dec'22) Frank Copier Pvt. Ltd. Detail Report
Graph / Photo
273 Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. 2022.06.23 2022.07.07 0.74 0.74 (Sep'22) 0.00 (Sep'22) Kesari & Associates Detail Report
Graph / Photo
274 Soil investigation and bearing capacity of soil 2021.08.19 2021.08.28 0.50 Allied Engineers Detail Report
Graph / Photo
275 Repairing of aluminium doors & Shutters. 2014.08.19 2014.09.03 Detail Report
Graph / Photo
276 Providing and laying RCC drain cover in open surface drain in basement. 2014.08.16 2014.09.15 2.58 (Mar'21) 0.00 (Mar'21) Detail Report
Graph / Photo
277 Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. 2014.09.16 2014.10.15 Detail Report
Graph / Photo
278 Finishing of exterior wall in 20 nos. CBI flats. 2014.12.08 2014.12.26 Pradeep Kumar Sharma Detail Report
Graph / Photo
279 P/F Manhole cover & Drain cover. 2015.01.08 2015.02.07 M. N. Construction Co. Detail Report
Graph / Photo
280 Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. 2014.08.18 2015.01.01 Detail Report
Graph / Photo
281 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. 2015.01.08 2015.02.04 Detail Report
Graph / Photo
282 Providing services of labour for day to day maintenance under Sub-Division M-2334. 2014.05.31 -- Detail Report
Graph / Photo
283 Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. 2014.09.18 2014.10.17 Detail Report
Graph / Photo
284 Replacement of Damaged roof of Sub Divn. Office M-233. 2014.11.11 2014.12.10 35.49 (Aug'21) 0.00 (Aug'21) Detail Report
Graph / Photo
285 Cleaning of sewer line, manhole & gully traps etc. 2014.12.22 2015.01.21 Detail Report
Graph / Photo
286 Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. 2015.01.24 2015.02.23 M. N. Construction Co. Detail Report
Graph / Photo
287 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. 2015.01.08 2015.02.07 M. N. Construction Co. Detail Report
Graph / Photo
288 Providing and fixing polycarbonate in available. 2014.12.19 2015.01.18 Detail Report
Graph / Photo
289 Improvement of Open Space in Circle Office & Division Office. 2015.02.06 -- Rajeev Sharma Detail Report
Graph / Photo
290 Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. 2015.01.17 2015.02.16 Pradeep Kumar Sharma Detail Report
Graph / Photo
291 Providing and fixing FRP door shutters in place of old damaged flush door shutters. 2014.09.18 2014.10.17 Detail Report
Graph / Photo
292 Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. 2015.02.08 2015.03.08 Detail Report
Graph / Photo
293 Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. 2015.02.06 2015.03.15 Detail Report
Graph / Photo
294 Water proofing treatment of first floor toilet. 2014.12.15 2015.01.14 Detail Report
Graph / Photo
295 Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. 2015.02.06 2015.02.20 Detail Report
Graph / Photo
296 Wall tile and other misc. civil work in Sports Complex at East Vinod Nagar. 2015.02.27 2015.03.26 Detail Report
Graph / Photo
297 Providing & fixing door and installation of PVC overhead tank for fire safety. 2015.01.17 -- Detail Report
Graph / Photo
298 Misc. Civil Works. 2015.03.16 2015.03.30 Shekhar Detail Report
Graph / Photo
299 Providing ramps in Schools & miscellenious works. 2015.02.12 2015.02.26 Detail Report
Graph / Photo
300 P/F Floor tile & broken tile. 2015.11.20 2015.12.12 Detail Report
Graph / Photo
301 Providing and laying cement concrete. 2015.03.12 2015.03.25 Indal Yadav Detail Report
Graph / Photo
302 Providing railing for Park. 2015.11.23 2015.12.05 Detail Report
Graph / Photo
303 Renovation of D.D.E. office by changing sanitary & plumbing fixtures in office toilet and internal finishing works 2016.07.04 2016.09.03 0.00 (Aug'16) 40.00 % (Aug'16) Work completed Detail Report
Graph / Photo
304 Construction of Double storeyed SPS type rooms for Cal lab,Library,Science labs,toilet for HOS & staff at Govt. Co.Ed.Edn.Dichaon Kalan,New Delhi. 2017.12.18 2019.06.15 34.21 (Jun'19) 100.00 % (Jun'19) work in progress. Detail Report
Graph / Photo
305 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 2016.06.25 2016.07.24 WORK RESCIENED. Detail Report
Graph / Photo
306 C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. 2016.03.25 2016.07.24 0.00 (Aug'16) 75.00 % (Aug'16) DOSE PERTAIN TO THIS DIVISION Detail Report
Graph / Photo
307 Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) 2016.05.10 2016.06.09 0.00 (Jul'16) 50.00 % (Jul'16) Tender re-call and date of opening 24-09-2016 Detail Report
Graph / Photo
308 EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System 2016.05.23 2016.06.23 0.00 (Jul'16) 70.00 % (Jul'16) Dose not pertain to this Division Detail Report
Graph / Photo
309 EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. 2016.04.15 2016.10.14 0.00 (Jul'16) 10.00 % (Jul'16) Completed Detail Report
Graph / Photo
310 EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. 2016.04.15 2016.07.14 0.00 (Jul'16) 15.00 % (Jul'16) Completed Detail Report
Graph / Photo
311 Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS 2016.04.05 2016.06.04 0.00 (Jul'16) 80.00 % (Jul'16) Completed Detail Report
Graph / Photo
312 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 2016.01.17 2016.04.30 0.00 (Jul'16) 80.00 % (Jul'16) polycarbonate Detail Report
Graph / Photo
313 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 2016.05.01 2016.06.30 0.00 (Jul'16) 0.01 % (Jul'16)

work in progress

Detail Report
Graph / Photo
314 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 2016.04.10 2016.06.09 0.00 (Jul'16) 0.01 % (Jul'16)

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
Graph / Photo
315 Construction of new boundary wall 2016.04.24 2016.07.20 21.77 (May'17) 100.00 % (May'17) Detail Report
Graph / Photo
316 Repair and renovation of toilets 2016.06.17 2016.08.15 0.00 (Sep'16) 91.00 % (Sep'16)

Detailed estimate under process.

Detail Report
Graph / Photo
317 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 2016.06.16 2016.09.13 0.00 (Sep'16) 53.00 % (Sep'16)

T.S. under process.

Detail Report
Graph / Photo
318 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 2016.10.16 2016.11.15 forfeited Detail Report
Graph / Photo
319 Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050. 2016.08.20 2016.09.15 0.00 (Aug'16) 0.01 % (Aug'16) work completed Detail Report
Graph / Photo
320 C/o 20 Nos. SPS type class rooms including toilet blocks, staircase and electrical installations, fan etc. at Sarvodaya (Co-ed) Sr. Sec. School, Netaji Nagar, (School I.D.) 1719102, Building I.D. 17191327). New Delhi 2014.11.04 2015.09.30 85% Work is in Progress Detail Report
Graph / Photo
321 Up gradation to Delhi Govt. D-II Flats, Vasant Kunj, New Delhi. 2017.02.05 2017.08.04 100.57 (Jul'18) 100.00 % (Jul'18) completed Detail Report
Graph / Photo
322 Providing Services of Security Guard at T.V. Branch Enquiry Office 2017.04.10 2018.04.09 2.52 (Apr'18) 90.00 % (Apr'18) Work completed Detail Report
Graph / Photo
323 Acoustic treatment system and renovation of multipurpose hall. 2017.10.20 2018.01.17 40.27 (Nov'21) 0.00 (Nov'21) 65% (Work is delayed due to ongoing electrical work as well as Covid-19) Detail Report
Graph / Photo
324 Acoustic work. 2018.02.02 2018.04.01 67.40 (Jul'18) 100.00 % (Jul'18) work in progress Detail Report
Graph / Photo
325 A/R and M/O to Residential and Non Residential building under Building Maintenance Sub Division (SW) - 4, PWD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19.(SH Engaging labour for Day to Day Maintenance). 2018.05.17 2019.05.16 94.01 (Mar'20) 0.00 (Mar'20) WORK IN PROGRESS Detail Report
Graph / Photo
326 AR and MO to District Court Resid. Complex Saket, ND-18-19 (SH Cleaning, mopping of common area, like lift lobby, staircase, basement, community centre, footpath area, terrace, servant qtr. etc. by mopping machine at Resid. Complex Saket Court, ND). 2018.09.25 2019.09.24 0.49 (Nov'18) 25.00 % (Nov'18) work in progress Detail Report
Graph / Photo
327 Construction of New block Forensic Science Laboratory, Rohini, New Delhi 2020.03.06 2021.09.05 212.87 (Aug'21) 0.00 (Aug'21) work in progress Detail Report
Graph / Photo
328 A/R and M/O to residential and Non residential Building under Sub Div-II of SWBMD at ITI Campus, Pusa, New Delhi during 2018-19.(Sh- Misc repair work and finishing work in quarters). 2018.05.23 2018.11.21 14.29 (Jul'19) 0.00 (Jul'19) work in progress. Detail Report
Graph / Photo
329 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 2018.11.02 2019.11.01 214.77 (Sep'19) 0.00 (Sep'19) Work in progress Detail Report
Graph / Photo
330 Construction of Boundary wall at Sayurpur Village, New Delhi. (SH- Providing fixing grills and concertina coil at boundary wall). 2018.07.10 2018.09.09 work in progress Detail Report
Graph / Photo
331 A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). 2018.08.03 2018.10.01 0.25 (May'22) 0.00 (May'22) WORK IN PROGRESS Detail Report
Graph / Photo
332 Construction of additional SPS type classrooms in Govt Schools Directorate of Education under Priority II 2019.09.05 2020.09.04 0.11 (Nov'19) 0.00 (Nov'19) work in progress Detail Report
Graph / Photo
333 A/A in Sanjay Gandhi Memorial Hospital, Mangolpuri, Delhi. (SH Renovation of ENT OPD, OST Centre, CMO room in main casualty, patient toilet in ward-4, change of floor tiles in digital X-ray room and change of windows in physiotherapy department etc. 2019.09.12 2020.01.09 16.74 (May'22) 0.00 (May'22) work is in slow progress Detail Report
Graph / Photo
334 Raising of main gate, C/o guard room, repair of ground water tank, providing and fixing IRC fabric jali inside the Class rooms etc. 2019.06.30 2019.08.29 1.60 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
335 Construction of Recreation Room, Coys room, Officers Quarters and Shed. 2019.06.30 2019.08.29 51.12 (Jul'20) 0.00 (Jul'20)

work completed

Detail Report
Graph / Photo
336 Construction of 2 nos.Viewers stand in Parade ground at PTS, Wazirabad, Delhi 2019.06.30 2019.07.19 8.39 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
337 Attending complaints of routine maintenance of service centre PTS, Wazirabad, Delhi. 2019.06.30 2020.06.29 7.20 (Mar'20) 0.00 (Mar'20)

work completed

Detail Report
Graph / Photo
338 Renovation of 10 Nos toilet blocks, Construction of 3 nos. R.C.C. tank of size 8 x 5 mtr. and 6 nos. M.S. grill gates. 2019.06.30 2019.08.29 52.31 (Aug'20) 0.00 (Aug'20)

work completed

Detail Report
Graph / Photo
339 Providing the services of Security Guard for day to day maintenance at D-II flats. 2019.08.02 2020.08.01 work in progress Detail Report
Graph / Photo
340 Providing security guards at Division Office M-222 (NE), Sub Division M-2222, Sub Division M-2221, Sub Division Office Loni Road and Division M-222 2019.06.30 2020.05.29 23.93 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
341 Attending day to day complaints 2019.06.24 2020.06.23 10.22 (Oct'20) 0.00 (Oct'20)

work completed

Detail Report
Graph / Photo
342 Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi 2019.06.30 2019.08.29 26.71 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
343 Pumping out rainwater to avoid water logging at DC office complex,Weavers Complex Nand Nagri and SDM Court Seelampur Delhi. 2019.06.30 2019.10.29 5.86 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
344 External plaster work of Judges Flats Including tile work in over head water storage tank of block D AND E, Steel works and other Misc. work 2019.10.24 2020.01.23 work in progress Detail Report
Graph / Photo
345 External plaster work including painting. 2019.06.16 2019.09.15 work in progress Detail Report
Graph / Photo
346 Redevelopment of rain water harvesting pits and cleaning of storm water lines at Residential and Non-Residential Complex, Saket Court, New Delhi. 2019.07.25 2019.09.24 work in progress Detail Report
Graph / Photo
347 Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. 2019.07.24 2021.09.22 in progress. Detail Report
Graph / Photo
348 RPVV Gandhi Nagar (School Id- 1003261) 2019.03.17 2019.12.11 12491.60 (Nov'20) 0.00 (Nov'20) 48 rooms handed over to HOS on 25.03.2022. 42 Additional Rooms handed over to HOS on 10.11.2022. Detail Report
Graph / Photo
349 GGSSS Mayur Vihar Ph-3 (Kondali Gharauli) (School Id- 1002352) 2019.03.17 2019.12.11 0.00 (Jan'21) 1.00 % (Jan'21) Work completed. Detail Report
Graph / Photo
350 SKV Patparganj (School Id- 1002031) 2019.03.17 2019.12.11 12491.60 (Nov'20) 0.00 (Nov'20) Work completed. Detail Report
Graph / Photo
351 GGSSS Khichripur (School Id- 1002037) 2019.03.17 2019.12.11 0.00 (Jan'21) 30.00 % (Jan'21) Work completed. Detail Report
Graph / Photo
352 AR and MO to Delhi Sachivalaya at IG Stadium Complex New Delhi dg 2018 19 2018.11.10 2019.05.09 1.02 (Jul'19) 0.00 (Jul'19) Work in Progress 95% Detail Report
Graph / Photo
353 Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). 2018.12.06 2019.08.02 308.01 (May'22) 0.00 (May'22) WORK IN PROGRESS Detail Report
Graph / Photo
354 EOR to Govt. Co-ed. Sr. Sec. School at Daulatpur and Govt. Co-ed. Sr. Sec. School at Malikpur, New Delhi. (Sh- C/o Rain Water Harvesting System). 2019.03.04 2019.05.02 69.90 (Aug'19) 0.00 (Aug'19) WORK IN PROGRESS Detail Report
Graph / Photo
355 GGSSS DDA Flat, Kalkaji, Phase-II, School ID: 1925041 2019.01.14 2019.10.10 0.00 (Sep'21) 65.00 % (Sep'21) Work is in progress Detail Report
Graph / Photo
356 GGSSS No. 3, Kalkaji School ID : 1925039 2019.01.14 2019.10.10 10365.03 (Nov'21) 0.00 (Nov'21) Work is in progress Detail Report
Graph / Photo
357 SKV,, Jonapur- BNK, School ID: 1923003 2018.12.08 2019.08.04 0.00 (Sep'21) 65.00 % (Sep'21) Work is in progress Detail Report
Graph / Photo
358 EOR to GBSSS Bijwasan, Govt. Sarvodaya Co-ed Sr. Sec. School Kitchner Road (Malcha Marg), DIET Sec-07 R.K. Puram etc New Delhi.(Sh- Construction of Rain Water Harvesting System). 2019.02.22 2019.04.24 47.84 (Jul'19) 80.00 % (Jul'19) WORK IN PROGRESS. Detail Report
Graph / Photo
359 Comprehensive architectural consultancy services for Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Jaffarpur Kalan, Nangli Sakrawati and Qutubapur (Sainik Vihar) New Delhi. (Package-1) 2021.10.04 2022.10.03 48.15 (Jan'23) 0.00 (Jan'23) Agency yet to submit the structural & service drawings vide this office letter No. 54(58) Edu. M. (East & North East)/PWD/ 151 dated: 28.02.2023 Detail Report
Graph / Photo
360 Mechanised cleaning of UG OH tank, water storage tanks, Sewer lines, Storm water drains, profile sheet, Distempering, Painting and Misc. repair work 2021.10.18 2022.05.17 Work in Progress Detail Report
Graph / Photo
361 Construction of Hospital at Hastsal, New Delhi 2021.06.17 2023.06.16 70.11 (Mar'23) 0.00 (Mar'23) Work is under progress and overall physical progress (Civil part) of work is 27%. Detail Report
Graph / Photo
362 Renovation of Labour room, Public toilet at 5th floor in MCH block and other misc. works 2021.03.17 2021.07.16 9.25 (May'22) 0.00 (May'22) work in progres Detail Report
Graph / Photo
363 Grit Wash and Internal Finishing for ABIT main building and exterior and internal finishing of workshop. 2020.11.02 2021.05.01 Work in progress Detail Report
Graph / Photo
364 Replacement of existing water closet with single piece water closet set, P/F floor and wall tile in toilets, replacement of damaged window and misc. civil works 2020.11.18 2020.11.28 In Progress. Detail Report
Graph / Photo
365 Replacement of damaged, rusted G.I. Pipelines of hospital and provision of borewell Water Pipeline and Tanks on Campus roof at Chacha Nehru Bal Chikitsalaya, Geeta Colony, Delhi dg. 2021-22 (Balance Work) 2022.04.18 2022.07.16 work completed. Detail Report
Graph / Photo
366 Misc Civil repairing work in Lift pit, lift shaft and machine room in OBH and GH at residential campus GTBH 2021.09.04 2021.10.03 Work is held up by the agency. Detail Report
Graph / Photo
367 Construction of Boundary wall at Plot No. FA 6 for District office and bataliyan, Women training college, Police line and Advanced research and Training Institute of Delhi Police Officers Narela, Delhi 110040 2022.01.20 2022.05.20 Work in Progress Detail Report
Graph / Photo
368 Development of play ground and construction of boundary wall. (Balance Work) 2022.01.20 2022.05.20 Work in Progress Detail Report
Graph / Photo
369 Renovation of Qtr no. 24,27,29,30,35,36,38 and 39 Type IV Qtrs Balance Work 2021.11.22 2021.09.27 22.75 (Oct'22) 0.00 (Oct'22) Work in progress Detail Report
Graph / Photo
370 C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) 2019.09.04 2021.03.03 502.23 (Mar'23) 0.00 (Mar'23) work in progress Detail Report
Graph / Photo
371 Development of play ground and construction of boundary wall 2022.01.20 2022.05.20 Work in progress Detail Report
Graph / Photo
372 Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING) 2019.03.17 2019.12.11 0.00 (Jan'21) 1.00 % (Jan'21) Handed over to HOS. Detail Report
Graph / Photo
373 Jhilmil Colony-SBV Avinash Chadda (ID: 1001105 ) (Addl. Rooms) 2022.04.01 2023.02.24 1st floor beam of 6 class room portion is in progress and foundation work of 2 class room & staircase is in progress at GGSSS/GSBV Jhilmil colony. Detail Report
Graph / Photo
374 Construction of Mother and Child Block and Screening OPD Block at Dr. BSA Hospital at Rohini, Delhi, i/c Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Supply of Furniture). 2020.03.06 2021.09.05 226.95 (Nov'22) 0.00 (Nov'22) work in progress Detail Report
Graph / Photo
375 Construction of 16 Nos. additional SPS class rooms (G+3) in GGSSS, Qadipur, Delhi ( Sch Id 1309265) (SH: C/o main SPS type building including internal & external water supply, sanitary installation, electrical installations, development of site i/c Fire fighting system etc. at GGSSS Qadipur Delhi -110036. (Sch. ID: 1309265) 2022.04.14 2022.10.11 180.21 (Mar'23) 0.00 (Mar'23)

Finishing works are in progress.

Detail Report
Graph / Photo
376 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24 2022.05.14 2024.05.13 Work is in progress. Detail Report
Graph / Photo
377 Balance Work (3rd Call) 2022.04.18 2022.07.16 Work completed. Detail Report
Graph / Photo
378 Repairs & maintenance of Resource Center for Children with special needs: 1208014--Partap Nagar-SKV 2022.06.30 2022.08.30 Work in Progress Detail Report
Graph / Photo
379 Providing for Services Day to Day Maintenance 2022.06.04 2023.06.03 Work in progress Detail Report
Graph / Photo
380 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 2022.06.03 2024.06.02 263.05 (Mar'23) 0.00 (Mar'23) Work in progress. Detail Report
Graph / Photo
381 Replacement of damaged, rusted G.I. Pipelines of hospital and provision of borewell Water Pipeline and Tanks on Campus roof at Chacha Nehru Bal Chikitsalaya, Geeta Colony, Delhi dg. 2021-22 (Balance Work) 2022.04.18 2022.07.16 Work completed. Detail Report
Graph / Photo
382 Construction of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi 2022.03.20 2022.07.19 Work is in progress Detail Report
Graph / Photo
383 Making school buildings barrier free and accessible to children with special needs 1310400 Ghoga G(CO ED) SSS 2021.12.17 2022.02.01 Work in progress Detail Report
Graph / Photo
384 Providing vehicle on hire charge basis for official purpose 2022.02.25 2023.02.24 Work in progress. Detail Report
Graph / Photo
385 Providing Services of Computer Operator, MTS etc. under various PWD Offices of North Building Division and office of SA North 2022.02.01 2023.01.26 Work in progress Detail Report
Graph / Photo
386 Construction of Boundary Wall on Vacant land at Dwarka sector 12 & 13 at New Delhi 2022.09.03 2023.01.02 141.26 (Mar'23) 0.00 (Mar'23) PCC work, footing casting, column casting &casting of plinth beam is in progress. Brick work above plinth is in progress. Detail Report
Graph / Photo
387 Maintenance and upkeeping of sewerage, drainage system and desilting of gully traps, manholes, Plumbing and Carpentry works etc. within the campus of Delhi Government Dispensaries situated at various places in constituencies of East, North-East and Shahdara Districts of Delhi 2022.08.01 2023.03.31 Work is in progress. Detail Report
Graph / Photo
388 Changing the Windows of Nurse Hostel in Residential Campus at GTB Hospital Shahdara Delhi 2022.08.24 2022.11.23 Work is in progress Detail Report
Graph / Photo
389 A/R & M/O to Rouse Avenue Court Complex at DDU Marg, New Delhi During 2022-23 & 2023-24. (SH: Operation and Maintenance of STP Plant of 180 KLD). 2022.09.30 2024.09.29 Work is in progress Detail Report
Graph / Photo
390 Construction of Machaan for Security Purpose and Control Room for Installation of UVSS System at Gate No. 5 of Rouse Avenue Court Complex, DDU Marg, New Delhi. 2022.10.03 2022.12.01 5.83 (Jan'23) 0.00 (Jan'23) Work is in progress Detail Report
Graph / Photo
391 Urgent Repair of boundary wall of Parking between Gate No 1 and 2 and pump house at GTB Hospital Shahdara Delhi 2022.11.08 2023.01.07 Work in progress. Detail Report
Graph / Photo
392 Renovation of Room No 135 Music Room First floor at UCMS GTB Hospital Shahdara Delhi 2023.01.08 2023.02.07 Work is in progress. Detail Report
Graph / Photo
393 Repairing works and water proofing of DGHS Dispensary OLD Seemapuri New Delhi 2023.01.08 2023.02.07 Work in progress. Detail Report
Graph / Photo
394 Renovation of Emergency Lab and Blood Storage room at Jag Pravesh Chandra Hospital, Shastri Park, Delhi 2023.01.01 2023.03.01 Work could not be started due to site is not handed over by the client department. Detail Report
Graph / Photo
395 Miscellaneous Civil works in Casualty including O.T. at Ground Floor and Room No. 205,206, 207, 208, 243 at Second Floor at Jag Pravesh Chandra Hospital, Shastri Park, Delhi 2023.01.01 2023.03.01 Work is in progress. Detail Report
Graph / Photo
396 Addition Alteration in Endoscopy First floor of Block 6 and other civil works in Rajiv Gandhi Super Specialty Hospital Tahirpur Delhi 2023.01.08 2023.02.07 Site is not available work to be started. Detail Report
Graph / Photo
397 Renovation of Room No 125 and 122 of General Surgery at 1st floor OPD Block GTB Hospital Shahdara Delhi 2023.01.19 2023.03.20 Work is in progress Detail Report
Graph / Photo
398 Expansion of Manifold room and Construction of toilet for the working staff in Manifold room and PSA Plant at Jag Pravesh Chandra hospital Shastri park, Delhi. 2022.11.20 2023.01.09 Work could not be started due to site is not handed over by the client department. Detail Report
Graph / Photo
399 Waterproofing treatment on Roof of DOT Centre Dharamshala Building at GTB Hospital Shahdara Delhi 2022.11.26 2023.01.25 Work in progress. Detail Report
Graph / Photo
400 Replacement of damaged G.I. Sheets & Covering IRC wire fabric all around Pharmacy for thermal insulation at GTB Hospital, Shahdara, Delhi 2022.11.26 2023.01.25 Work in progress. Detail Report
Graph / Photo
401 Hiring of Inspection Vehicle along with Driver for LBS Hospital Project work in the office of A.E., HPSD (East)-III, PWD during 2022-23 2022.12.01 2023.09.30 Work is in progress. Detail Report
Graph / Photo
402 Hiring of Inspection Vehicle along with Driver for Chacha Nehru Bal Chikitsalaya (G+4) (596 beds) Project work in the office of Assistant Engineer Health Project Sub-Division (East)-IV, PWD, CNBC, Geeta Colony, Delhi-110031 during 2022-23 2022.11.25 2023.09.24 Work is in progress. Detail Report
Graph / Photo
403 Miscellaneous Civil works in Police Room Porta Cabin at Jag Pravesh Chandra Hospital, Shastri Park, Delhi 2022.11.27 2023.01.25 Work could not be started due to site is not handed over by the client department. Detail Report
Graph / Photo
404 Replacement of damaged false ceiling in Emergency OT & Providing and fixing roller blinds in R. No. 511 & 513 at Jag Pravesh Chandra Hospital, Shastri Park, Delhi 2022.11.27 2023.01.10 Work could not be started due to site is not handed over by the client department. Detail Report
Graph / Photo