Public Works Department
Govt. of NCT of Delhi
लोक निर्माण विभाग, दिल्ली सरकार
लोक निर्माण विभाग
राष्ट्रीय राजधानी क्षेत्र, दिल्ली सरकार
S. No.क्र. सं. | Name of Workकार्य का नाम | Date of Startकार्य आरम्भ करने की तिथि | Date of Completionकार्य समाप्त करने की तिथि | Cost (In Lac) |
Expenditure (In Lac) |
Progress | Agency | Status | Viewदेखें |
---|---|---|---|---|---|---|---|---|---|
1 | C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis | 2014.08.27 | 2017.02.26 | 54511.43 | 1039.10 (Feb'23) | 0.00 (Feb'23) | Larson & Toubro Limited | Minor rectifications & left out works is under progress. |
Detail Report
Graph / Photo |
2 | setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) | 2021.09.23 | 2022.02.22 | 40775.18 | 9915.49 (Mar'23) | 0.00 (Mar'23) | SAM India Builtwell | GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. |
Detail Report
Graph / Photo |
3 | CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. | 2020.08.10 | 2023.05.09 | 38439.53 | 15429.40 (Mar'23) | 0.00 (Mar'23) | Ramacivil India Construction Private Limited | work in progress |
Detail Report
Graph / Photo |
4 | Construction of Hospital at Jwalapuri, New Delhi | 2020.08.07 | 2022.08.13 | 26950.37 | 7029.55 (Mar'23) | 0.00 (Mar'23) | Parnika Commercial and Estates Pvt. Ltd. | Structure RCC work completed. Flooring work, masonry work, façade work, road work, water proofing, gypsum plaster etc. & electrical work is in progress. |
Detail Report
Graph / Photo |
5 | C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works | 2017.08.09 | 2019.11.09 | 23127.43 | 6589.16 (Mar'23) | 0.00 (Mar'23) | NKG Infrastructure Limited | Physical Progress of the work is 98%. |
Detail Report
Graph / Photo |
6 | Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 | 2019.10.04 | 2020.07.03 | 14316.00 | 1610.31 (Mar'23) | 0.00 (Mar'23) | Quality Buildcon Pvt. Ltd. | 140 Temporary court rooms at Karkardooma, Saket and Tis Hazari The Work is in progress with upto date progress is approx. 99.5%. (i) Karkardooma: The work is completed and inaugurated on 13.05.2022, possession taken on 26.08.22. Keys have been taken over by caretaking branch during the course of third week of November. (ii) Saket: The work is completed, courts made functional dated 01.09.22. Some additional work has been proposed by court authorities which has been started and will be completed by January. (iii) Tis Hazari: Work is completed and defect rectification work is underway and final furniture placing, interconnection of fiber cable between old & new building is in progress. Fire clearance obtained dated 14.10.22. Some additional work has been proposed by court authorities has also been completed and the building has been made ready for handover pending certain costly fixtures which will be fixed and final testing and commissioning of all services will be completed within 10 days, once the security personnel are provided by the district court authorities. An estimate regarding basic housekeeping and security had also been sent to the court authorities and to the dedicated maintenance wing to facilitate the handover as well. 15th December is the tentative date of handing over to the district court authorities as decided during site visit dated 5th December however, security protocol is yet to be given. Certain minor defects were pointed out by court authorities again during 30.12.22 visit which will be rectified by year end and building will be tentatively handed over during 15 Feb 2023. |
Detail Report
Graph / Photo |
7 | Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. | 2019.12.10 | 2020.06.01 | 13992.80 | 2103.50 (Mar'23) | 0.00 (Mar'23) | Kamladitya Construction Private Limited | OPD block is completed. The deceision of Health Ministry for change in scope of work is awaited. |
Detail Report
Graph / Photo |
8 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi | 2019.10.18 | 2021.04.10 | 13447.15 | 3634.52 (Feb'23) | 0.00 (Feb'23) | Roshan Real Estate Pvt Ltd. | Work is under progress. |
Detail Report
Graph / Photo |
9 | Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. | 2020.03.04 | 2021.09.03 | 10708.84 | 3123.00 (Mar'23) | 0.00 (Mar'23) | Quality Buildcon Pvt. Ltd. | work in progress |
Detail Report
Graph / Photo |
10 | C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. | 2019.09.04 | 2021.03.03 | 7122.09 | 1553.62 (Mar'23) | 0.00 (Mar'23) | PNSC Infrastructure Pvt. Ltd | work in progress. |
Detail Report
Graph / Photo |
11 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. | 2019.08.06 | 2020.10.29 | 6563.40 | 1224.21 (Mar'23) | 0.00 (Mar'23) | PNSC Infrastructure Pvt. Ltd | Work is under progress. |
Detail Report
Graph / Photo |
12 | C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) | 2019.01.14 | 2019.11.09 | 4874.05 | 5266.38 (Mar'23) | 0.00 (Mar'23) | Shri kamal singh | Work in progress |
Detail Report
Graph / Photo |
13 | C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) | 2019.01.20 | 2019.11.15 | 4603.38 | 4716.31 (Mar'23) | 0.00 (Mar'23) | Sh. Kamal Singh | Work in progress |
Detail Report
Graph / Photo |
14 | Const 182 Nos. of additional SPS class rooms (Package-C) | 2019.03.17 | 2019.12.11 | 3699.32 | 3727.61 (Feb'23) | 0.00 (Feb'23) | SPS Infrabuild Pvt. Ltd. | Work completed. |
Detail Report
Graph / Photo |
15 | Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW | 2018.12.24 | 2019.09.19 | 3675.76 | 3278.89 (Jan'23) | 0.00 (Jan'23) | RAMA Contractor | Work completed. |
Detail Report
Graph / Photo |
16 | Const 180 Nos. of additional SPS class rooms (Package-B) | 2019.03.17 | 2019.12.11 | 3636.43 | 19151.12 (Oct'22) | 0.00 (Oct'22) | RAMA Contractor | Handed over to HOS. |
Detail Report
Graph / Photo |
17 | Const 174 Nos. of additional SPS class rooms in various schools (Package-E) | 2019.03.17 | 2019.12.11 | 3553.31 | 3181.90 (Mar'23) | 0.00 (Mar'23) | SPS Infrabuild Pvt. Ltd. | Handed over to HOS |
Detail Report
Graph / Photo |
18 | Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. | 2019.11.14 | 2021.02.13 | 3541.69 | 863.13 (Jan'23) | 0.00 (Jan'23) | Tewatia Construction Pvt. Ltd. | work in progress |
Detail Report
Graph / Photo |
19 | Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes | 2022.12.24 | 2023.06.23 | 3483.10 | 261.11 (Mar'23) | 0.00 (Mar'23) | OPTIMUM SECURITY SOLUTIONS PVT. LTD. | Work in progress |
Detail Report
Graph / Photo |
20 | Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW | 2019.03.17 | 2019.12.11 | 3455.84 | 3857.92 (Mar'23) | 0.00 (Mar'23) | RAMA Contractor | Work completed. |
Detail Report
Graph / Photo |
21 | Civil work and Internal E.I. work | 2007.04.24 | 2009.07.23 | 3002.21 | Globe Civil Project Pvt. Ltd. |
Detail Report
Graph / Photo |
|||
22 | SKV Sangam Vihar J Block Sch. ID 1923346 | 2019.03.17 | 2019.12.11 | 3002.10 | 3233.23 (Mar'23) | 0.00 (Mar'23) | Devinder Singh | Work is in progress |
Detail Report
Graph / Photo |
23 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. | 2022.10.17 | 2023.10.16 | 3000.18 | 395.49 (Feb'23) | 0.00 (Feb'23) | Jai Bhagwan | Plinth beam & stilt floor column in progress. |
Detail Report
Graph / Photo |
24 | Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi | 2020.05.29 | 2021.05.28 | 2931.78 | 4167.17 (Mar'23) | 0.00 (Mar'23) | The Krishna Construction Co. | Work in progress |
Detail Report
Graph / Photo |
25 | SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW | 2019.10.17 | 2020.07.12 | 2849.35 | 2549.96 (Feb'23) | 0.00 (Feb'23) | A. K. Builders | work in progress. |
Detail Report
Graph / Photo |
26 | Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. | 2019.06.28 | 2020.06.22 | 2806.33 | 268.76 (Feb'23) | 0.00 (Feb'23) | Roshan Real Estate Pvt Ltd. | Work in progress (40% progress) |
Detail Report
Graph / Photo |
27 | Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. | 2022.10.11 | 2023.09.05 | 2783.15 | 559.78 (Mar'23) | 0.00 (Mar'23) | DND Infra Private Limit | Pile work & Block-1 plinth beam steel binding in progress. Boundary wall lintel beam in progress & drain work completed. |
Detail Report
Graph / Photo |
28 | Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi | 2021.08.23 | 2022.05.22 | 2373.12 | 965.09 (Mar'23) | 0.00 (Mar'23) | M/s PK Gupta & Co. | RCC work of Admin cum Rest Room, Toilet Block, Workshop buildings are in progress. Work is being hampered due to : 1) Non availability of permission from SDM office for playing of Good Earth truck. 2) Progress of work effected due to NGT construction ban. |
Detail Report
Graph / Photo |
29 | SBV Jonapur, School ID: 1923359 | 2018.12.08 | 2019.08.04 | 2342.87 | 1530.26 (Mar'23) | 0.00 (Mar'23) | Reliance Elektrik works | Work is in progress |
Detail Report
Graph / Photo |
30 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. | 2020.05.31 | 2021.05.30 | 1874.70 | 1314.56 (Mar'23) | 0.00 (Mar'23) | SSP Promoters and Builders Private Limited | WORK IN PROGRESS |
Detail Report
Graph / Photo |
31 | Furniture Work RECALL | 2019.11.04 | 2019.12.18 | 1858.08 | 6.26 (Sep'21) | 0.00 (Sep'21) | Rajdhani Furnitures PVT. LTD. |
Detail Report
Graph / Photo |
|
32 | Co Hostel Bldg inclu External Development works Internal Elect Installation External Lighting lifts fire fighting system fire alarm with PA System CCTV Audio video system HVAC works | 2023.02.27 | 2024.07.26 | 1839.86 | KALYAN CHANDRA GOYAL & CO. | v |
Detail Report
Graph / Photo |
||
33 | C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc | 2022.04.01 | 2023.02.24 | 1798.93 | 215.60 (Mar'23) | 0.00 (Mar'23) | K. L. ARORA & SON | St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. |
Detail Report
Graph / Photo |
34 | C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) | 2018.12.29 | 2019.07.26 | 1743.19 | 4490.50 (Dec'22) | 0.00 (Dec'22) | AMAR CONSTRUCTION COMPANY | Work in progress |
Detail Report
Graph / Photo |
35 | Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi | 2021.03.08 | 2021.11.02 | 1583.17 | 773.07 (Dec'22) | 0.00 (Dec'22) | Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 | 90% |
Detail Report
Graph / Photo |
36 | C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc | 2022.03.26 | 2023.02.19 | 1553.88 | 518.51 (Mar'23) | 0.00 (Mar'23) | K L Arora & Son | St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. |
Detail Report
Graph / Photo |
37 | Construction of 80 Nos G plus 3 equivalent SPS Class Rooms at Govt Co Ed Sr Secondary School Gandhi Brahampur Delhi including 8 toilet blocks, 4 nos staircase 1 lift and internal and external water supply sanitary installations, electrical installations, development of site, RWH & UGR fire fighting system etc. | 2022.03.26 | 2023.02.19 | 1377.43 | K. L. ARORA & SON | Work foreclosed. |
Detail Report
Graph / Photo |
||
38 | C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc | 2022.04.02 | 2023.02.25 | 1359.28 | 486.49 (Mar'23) | 0.00 (Mar'23) | K. L. ARORA & SON | Columns of Block-3 from 1st floor level to 2nd level in progress. In Block-1, Reinforcement binding of raft in progress. Plinth beams & column casting in progress in Block-2. Work delay due to insufficient labour & resources. |
Detail Report
Graph / Photo |
39 | Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) | 2022.03.12 | 2023.02.04 | 1275.84 | 174.07 (Feb'23) | 0.00 (Feb'23) | M/s SURENDRA KUMAR | Work in progress |
Detail Report
Graph / Photo |
40 | GGSS No. 3 Sec IV, Ambedkar Nagar | 2016.03.03 | 2016.07.15 | 1212.87 | Devinder Singh | completed |
Detail Report
Graph / Photo |
||
41 | C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Non-Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi). | 2021.07.11 | 2021.09.23 | 1118.83 | 35111.01 (Mar'23) | 0.00 (Mar'23) | M/s Rajdhani Furnitures Pvt. Ltd. | 99.6% work physically completed. |
Detail Report
Graph / Photo |
42 | Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi | 2022.04.06 | 2025.04.05 | 1099.29 | 53.87 (Oct'22) | 0.00 (Oct'22) | SIKKA ASSOCIATES REGD. | The proposal was submitted to VC, Delhi Sports University as on . The approval has been communincated as on dated . The PE has been submitted by the consultant and same is under scrutiny. |
Detail Report
Graph / Photo |
43 | C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) | 2022.04.18 | 2023.03.13 | 1090.67 | 491.93 (Mar'23) | 0.00 (Mar'23) | K. L. ARORA & SON | In Block A, Plinth beam & casting of columns in progress. In Block -B, columns from 1st floor level to 2nd floor level in progress. Work delay due to insufficient labour & resources. |
Detail Report
Graph / Photo |
44 | C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. | 2023.03.09 | 2024.02.01 | 1058.78 | AMOCON | After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023 |
Detail Report
Graph / Photo |
||
45 | Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. | 2018.12.15 | 2019.06.12 | 827.90 | 430.96 (Jan'23) | 0.00 (Jan'23) | S. P. Construction | Work in progress |
Detail Report
Graph / Photo |
46 | Civil and Electrical Work. | 2023.03.05 | 2023.11.29 | 617.03 | CHANDRA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|||
47 | Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. | 2019.01.10 | 2019.07.08 | 585.53 | 123.30 (Dec'22) | 0.00 (Dec'22) | P S ASSOCIATES | work in progress |
Detail Report
Graph / Photo |
48 | Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB | 2022.09.25 | 2023.01.24 | 583.83 | MAHAVIR PRASAD GUPTA AND SONS |
Detail Report
Graph / Photo |
|||
49 | Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work | 2022.01.28 | 2022.12.27 | 579.95 | 261.54 (Nov'22) | 0.00 (Nov'22) | R.K ENTERPRISES | Work is in progress 3% |
Detail Report
Graph / Photo |
50 | Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 | 2014.09.30 | 2015.05.26 | 474.90 | 61.36 (May'19) | 0.00 (May'19) | Work completed on 31/12/2017 final payment yet to be made |
Detail Report
Graph / Photo |
|
51 | Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 | 2022.04.02 | 2022.09.28 | 462.00 | 283.40 (Feb'23) | 0.00 (Feb'23) | PRATAP SINGH |
Detail Report
Graph / Photo |
|
52 | Providing services of Computer Operators MTS and Drivers etc | 2022.05.06 | 2023.05.05 | 441.58 | 359.16 (Mar'23) | 0.00 (Mar'23) | M/s R D Excellent Services Pvt. Ltd. | work in progress |
Detail Report
Graph / Photo |
53 | C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) | 2022.03.02 | 2022.11.26 | 382.04 | M/s. Satyam Construction | work is in progress |
Detail Report
Graph / Photo |
||
54 | Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system | 2015.05.26 | 2016.05.25 | 316.66 | Sudesh Kumar | Work is completed except fittings and fixtures due to delay in taking over of DGD by DGHS. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Client being requested regularly. |
Detail Report
Graph / Photo |
||
55 | Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi | 2018.12.27 | 2019.04.26 | 296.85 | 335.77 (Aug'21) | 0.00 (Aug'21) | Ram Krishan Yudhister Parkash | work completed |
Detail Report
Graph / Photo |
56 | Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). | 2019.02.28 | 2019.06.27 | 294.21 | 58.25 (Feb'22) | 0.00 (Feb'22) | AASRA Martech Pvt.Ltd. | Work in progress. |
Detail Report
Graph / Photo |
57 | Civil and Electrical work. | 2019.05.05 | 2020.03.04 | 292.64 | Dheeraj Singh & Company | Work just awarded |
Detail Report
Graph / Photo |
||
58 | Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). | 2022.08.09 | 2023.08.08 | 292.57 | 8.79 (Mar'23) | 0.00 (Mar'23) | Nand gopal Gupta |
Detail Report
Graph / Photo |
|
59 | Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi | 2022.01.16 | 2024.10.15 | 288.00 | Arcop Associates Pvt. Ltd. | Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval. |
Detail Report
Graph / Photo |
||
60 | Comprehensive architectural consultancy services for Construction of SPS School of Specialized Excellence (SoSEs) Buildings (G Plus 3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Lajpat Nagar, Hari Nagar, Karol Bagh, Gandhi Nagar & Nand Nagri (Package-A) | 2022.07.20 | 2023.07.19 | 286.66 | Design Accord Consultant | Tenders for appointment of Architectural Consultants on Q.C.B.S. were invited in two packages one each for Pucca Construction and for SPS construction and accordingly M/s Design Accord Consultants were awarded the work. M/s Design Accord Consultants had visited all the sites of Package-A & B and have prepared initial proposal for presentation and formal approval Date & Time yet to be fixed by the DoE to present the proposal by the consultant at Directorate of Education in presence of all stake holders. Detailed presentation has been made on 06.01.2023 in Directorate of Education. Modified proposal / Presentation after incorporating suggestion of HOS /DDE /DoE being resubmitted shortly. |
Detail Report
Graph / Photo |
||
61 | Construction prefab hut for HQ at PTS Wazirabad, Delhi | 2018.07.21 | 2018.11.20 | 285.56 | Aliyan Constaruction Company | work completed |
Detail Report
Graph / Photo |
||
62 | Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi | 2022.12.26 | 2023.05.24 | 267.31 | 50.47 (Mar'23) | 0.00 (Mar'23) | Sham Lal Gupta and Sons | the work has been recently awarded to the agency. the design acoustics Treatment for Basketball Hall submitted by the agency and the same is under checking |
Detail Report
Graph / Photo |
63 | Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool | 2020.12.23 | 2021.06.20 | 262.79 | 54.92 (Feb'23) | 0.00 (Feb'23) | Maa Narayan Constuction Co. | 62% |
Detail Report
Graph / Photo |
64 | Construction of Boundary at vacant land measuring 10 Bigha 02 Biswa, bearing Khasra No. 39/5 & 39/6 situated in village Madanpur Dabas Distt. North West Through PWD, GNCTD | 2022.12.17 | 2023.04.16 | 178.08 | Sarthak Construction Co. | The work held up due to non-demarcation of boundaries by the Revenue Authority. |
Detail Report
Graph / Photo |
||
65 | Vertical Extension of Teaching Block No.1 of B.R. Ambedkar College, Wazirabad Road, Delhi | 2018.01.16 | 2018.07.15 | 172.40 | 127.50 (Jan'22) | 0.00 (Jan'22) | JABIR HUSSAIN | work completed |
Detail Report
Graph / Photo |
66 | C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Providing & fixing industrial kitchen equipments in Boy's, Girl's & Teacher's Hostel) | 2021.12.02 | 2022.03.01 | 157.41 | Simple Enterprises | WORK DOES NOT PERTAIN TO THIS DIVISION |
Detail Report
Graph / Photo |
||
67 | Providing and Installing Fire Fighting, Fire Alarm system and Public Address system | 2014.08.10 | 2015.04.09 | 155.31 |
Detail Report
Graph / Photo |
||||
68 | Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). | 2019.01.25 | 2019.05.24 | 140.44 | 216.46 (Oct'21) | 0.00 (Oct'21) | Uma Shankar | work in progress |
Detail Report
Graph / Photo |
69 | Construction of prefab hut for HQ of Meghalaya Police along with development work located at PTS Wazirabad, Delhi | 2018.07.15 | 2018.11.14 | 134.50 | 138.77 (Jan'22) | 0.00 (Jan'22) | Aliyan Constaruction Company | work completed |
Detail Report
Graph / Photo |
70 | Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) | 2022.04.23 | 2023.01.22 | 124.05 | 9.97 (Feb'23) | 0.00 (Feb'23) | Dheeraj Singh & Company |
Detail Report
Graph / Photo |
|
71 | Changes in infrastructure of CHB to develop it as OHB Model Home.(Civil and Electrical work) | 2019.10.24 | 2020.02.23 | 112.72 | 20.64 (Dec'22) | 0.00 (Dec'22) | Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 |
Detail Report
Graph / Photo |
|
72 | Attending Day-to-Day complaint in Mandoli Jail complex and residential area including Supply of Material, Horticulture Operation, STP operation and tank and drain cleaning | 2022.06.08 | 2023.06.07 | 112.05 | 72.40 (Feb'23) | 0.00 (Feb'23) | M/s Gejwal Construction Company | Work is in progress |
Detail Report
Graph / Photo |
73 | Providing and supplying tree planters in various places, New Delhi under MLA LAD Fund Scheme | 2019.11.04 | 2019.12.18 | 91.97 | 91.97 (Mar'21) | 0.00 (Mar'21) | Rajeshwar Dayal Pandey |
Detail Report
Graph / Photo |
|
74 | Designing Manufacturing Installation and Commissioning of ceiling mounted Facade Access System on external facade and inner facade in Atrium at S Block Delhi High Court New Delhi | 2022.12.16 | 2023.03.15 | 91.53 | 78.12 (Mar'23) | 0.00 (Mar'23) | M P BHATIA | Work in progress |
Detail Report
Graph / Photo |
75 | Construction of Shed with Boxing Ring at Sports Complex, East Vinod Nagar, Delhi | 2017.05.08 | 2017.09.04 | 84.89 | 19.39 (Jul'20) | 0.00 (Jul'20) | Anish Ahmed | Work in Progress |
Detail Report
Graph / Photo |
76 | Up-gradation of swimming pool and other misc. civil works including electrical work | 2021.08.11 | 2021.12.08 | 83.39 | 84.10 (Dec'22) | 0.00 (Dec'22) | M/s Tanishq Ions | In Progress. |
Detail Report
Graph / Photo |
77 | C/o GPA for DA Staff at Shalimar Bagh, Delhi 143 Nos. Type-III Qtrs. (SH: Misc. work to make quarters habitable for allotment of 39 Nos. Type-III Qtrs. at Shalimar Bagh dg. 2022-23). | 2023.03.23 | 2023.06.22 | 83.38 | Zahid Hussain |
Detail Report
Graph / Photo |
|||
78 | Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) | 2022.06.25 | 2022.08.23 | 78.59 | 102.31 (Mar'23) | 0.00 (Mar'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
79 | Repair and Renovation of toilets of Hon ble Judges Chambers and Public ladies toilet in A Block G plus 3 and staff toilet G plus 6 near to copying agency in J block at KKD Court Delhi Civil and Electrical works | 2022.03.13 | 2022.08.19 | 76.84 | 80.97 (Dec'22) | 0.00 (Dec'22) | Uma Shankar |
Detail Report
Graph / Photo |
|
80 | Renovation of Library Block of IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, New Delhi.(SH-Civil and Electrical works). | 2018.07.09 | 2019.01.08 | 75.80 | 77.23 (Jan'22) | 0.00 (Jan'22) | Kamal Construction Co. | Work in progress |
Detail Report
Graph / Photo |
81 | Changes in Infrastructure of Model Home to convert it as CHB and JJB in front of Building (Civil and Electrical work). | 2019.10.24 | 2020.01.23 | 71.13 | 20.78 (Dec'22) | 0.00 (Dec'22) | AJAY CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
82 | Providing and laying RMC in the campus of N, J1, J2, J3, K, L and M Block at Sujan Singh Park, New Delhi under MLA LAD Fund Scheme. | 2019.10.27 | 2019.12.07 | 70.87 | 79.44 (May'21) | 0.00 (May'21) | Gyanchand |
Detail Report
Graph / Photo |
|
83 | Construction of 10 Nos FRP Gazebo rubens and 06 Nos of porta cabin Chaupal at various places of New Delhi Constituency AC40, under MLA LAD Fund Scheme | 2019.11.26 | 2020.01.24 | 68.77 | 35.20 (Sep'22) | 0.00 (Sep'22) | Tripurari Prasad Singh |
Detail Report
Graph / Photo |
|
84 | Construction of boundary wall at Tikri Khurd (Narela Project) for Delhi District Courts, New Delhi | 2021.12.19 | 2022.04.18 | 68.04 | 42.85 (Feb'23) | 0.00 (Feb'23) | Durga Construction Co. | Work is in progress |
Detail Report
Graph / Photo |
85 | Recarpeting of service road from Peeragarhi Chowk to DTC Depot Nangloi, New Delhi under PWD Division West Road-2 Sub Division WR-23 during 2022-23. | 2022.05.27 | 2022.07.10 | 67.55 | Karambir Rana Builders |
Detail Report
Graph / Photo |
|||
86 | SH Work of UTCS Complex Employment exchange JJB Court Working Women Hostel HLTB Complex Sanskar Ashram, Department of Social Welfare and CDMO Shahdara KKD Court Division under SD M 2312 during 2022 23. | 2023.01.07 | 2024.01.06 | 64.35 |
Detail Report
Graph / Photo |
||||
87 | Construction of Recreation Hall at PTS, Wazirabad, Delhi | 2019.02.16 | 2019.06.15 | 63.80 | 81.48 (Mar'21) | 0.00 (Mar'21) | Shekhar | work completed |
Detail Report
Graph / Photo |
88 | Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 | 2022.02.07 | 2023.02.06 | 63.52 | 48.72 (Feb'23) | 0.00 (Feb'23) | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
89 | Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi | 2022.01.22 | 2023.01.21 | 62.58 | 61.96 (Oct'22) | 0.00 (Oct'22) | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
90 | Construction of rain water harwasting system in Main Court Buildings i e in A B C I J K L Blocks and Lawyers Chamber Blocks D E F G H at KKD Court Shahdara Delhi Balance Work | 2021.12.18 | 2022.03.17 | 59.22 | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 | In Progress. |
Detail Report
Graph / Photo |
||
91 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall | 2022.03.14 | 2022.06.11 | 59.19 | 70.85 (Jan'23) | 0.00 (Jan'23) | Srishti Assosiates |
Detail Report
Graph / Photo |
|
92 | Construction of Boundary wall at vacant lying land measuring 02 Bigha 08 Biswa bearing Khasra no. 86/12/2 (02-08) of Directorate situated in Village-Ladpur (District-North-West) Delhi through, PWD. | 2022.08.26 | 2022.12.23 | 58.39 | Parth Garg | The work held up due to non-demarcation of boundaries by the Revenue Authority. |
Detail Report
Graph / Photo |
||
93 | Maintenance and repair work in Mandoli Jail complex, Delhi-110093 during year 2022-23. SH: External and Internal finishing work of Non- Residential Buildings and Residential quarters.2nd call | 2022.06.10 | 2023.03.09 | 57.65 | 17.26 (Aug'22) | 0.00 (Aug'22) | Aamir Khan | The work is in progress |
Detail Report
Graph / Photo |
94 | Miscellaneous Repair and Renovation works in Toilets Corridor Shafts Flooring in MV Hospital Pooth Khurd Delhi | 2022.10.14 | 2023.01.13 | 57.52 | Sarthak Construction Co. | Work in Progress (50% Progress) |
Detail Report
Graph / Photo |
||
95 | Misc repair work under SRD Project Division I Sub Division III PWD New Delhi Recall | 2019.09.23 | 2020.03.22 | 56.09 | 70.01 (Feb'21) | 0.00 (Feb'21) | KAMAAL CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
96 | AA to SKV No. 01 Gandhi Nagar Delhi dg 2018 19 | 2019.03.17 | 2019.07.16 | 55.57 | 32.21 (Jun'20) | 0.00 (Jun'20) | Arif | 90% work in progress |
Detail Report
Graph / Photo |
97 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi | 2021.11.21 | 2022.02.18 | 54.92 | 22.00 (Mar'23) | 0.00 (Mar'23) | Millennium Furniture |
Detail Report
Graph / Photo |
|
98 | C/o Medical store and Surgical Store in basement area of Indira Gandhi Hospital, Sector-9, Dwarka, New Delhi | 2022.09.13 | 2022.11.11 | 54.60 | 0.00 (Jan'23) | 20.00 % (Jan'23) | DEEPAK CONSTRUCTION AND CO. | Work is under progress. |
Detail Report
Graph / Photo |
99 | Expansion of 8 no Vulnerable Witness Courts at 5th and 6th floor B Block KKD Courts Delhi and other electrical installations | 2022.03.19 | 2022.05.17 | 53.14 | 49.16 (Mar'23) | 0.00 (Mar'23) | SABUR ALAM |
Detail Report
Graph / Photo |
|
100 | Construction of 5 nos arch shaped FRP pergola, 4 nos FRP porta cabin and 25 nos FRP Security Cabin at various places of New Delhi constituency AC 40 under MLA LAD Scheme | 2019.11.26 | 2020.01.24 | 51.22 | 5.64 (May'22) | 0.00 (May'22) | Tripurari Prasad Singh |
Detail Report
Graph / Photo |
|
101 | Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh | 2017.06.27 | 2017.07.26 | 50.20 | Bansal Builder | Agreement closed PG forfeited |
Detail Report
Graph / Photo |
||
102 | False Ceiling, Granite and Wooden Flooring work in court rooms of Shahdara district Karkardooma Court Complex Delhi. Civil and Electrical Work. | 2023.03.16 | 2023.06.13 | 50.09 | M.N Construction |
Detail Report
Graph / Photo |
|||
103 | Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block | 2022.06.08 | 2022.09.05 | 50.04 | M. N. Construction Co. |
Detail Report
Graph / Photo |
|||
104 | Renovation of 10 Nos faculty rooms of Anatomy at MAMC | 2021.05.22 | 2023.05.22 | 49.64 | 14.10 (Jun'22) | 0.00 (Jun'22) | SABUR ALAM | work completed |
Detail Report
Graph / Photo |
105 | Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi | 2022.02.26 | 2022.03.27 | 48.15 | GEEKEN SEATING COLLECTION PVT LTD |
Detail Report
Graph / Photo |
|||
106 | Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi | 2022.06.25 | 2022.08.23 | 47.61 | 27.06 (Oct'22) | 0.00 (Oct'22) | Manish construction and co |
Detail Report
Graph / Photo |
|
107 | Construction of RCC Lift Duct and external development in the front of proposed Lift area | 2022.04.17 | 2022.08.14 | 43.84 | 6.34 (Aug'22) | 0.00 (Aug'22) | TKN Developers |
Detail Report
Graph / Photo |
|
108 | SITC of Building Management System | 2020.09.12 | 2021.03.11 | 43.49 | Digital Controls & Automation | Material supplied by the firm. Work is held-up by the agency. Clause 3 notice issued to the agency. |
Detail Report
Graph / Photo |
||
109 | Renovation of Various Rooms (Room No. 417 to 439) in the department of Pathology 4th floor of the UCMS college Block, GTB Hospital, Shahdara, Delhi | 2021.12.27 | 2022.06.24 | 41.79 | SHAMSHAD AHMED | Work is in progress |
Detail Report
Graph / Photo |
||
110 | P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). | 2022.06.13 | 2022.09.10 | 41.34 | 43.08 (Jan'23) | 0.00 (Jan'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
111 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings incupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 41.32 | 19.33 (Feb'23) | 0.00 (Feb'23) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
112 | Improvement of lighting in various OTs at GTB Hospital Complex, Shahdara, Delhi. | 2019.03.03 | 2019.05.02 | 40.46 | 19.10 (May'19) | 0.00 (May'19) | CARONA ELECTRICALS | Work completed |
Detail Report
Graph / Photo |
113 | Water proofing treatment of Main Court Block A Block podium and basement area at Delhi High Court New Delhi | 2023.01.07 | 2023.05.06 | 40.42 | Complete waterproofing system inc. | Work in progress |
Detail Report
Graph / Photo |
||
114 | Toilets renovation works | 2021.07.09 | 2021.10.06 | 40.06 | 49.76 (Jan'23) | 0.00 (Jan'23) | Saeed Builders | In progress. |
Detail Report
Graph / Photo |
115 | Covering of balcony of type-I flats in residential complex of Bhagwan Mahavir Hospital, Pitampura, Delhi. | 2022.09.23 | 2022.11.22 | 39.90 | NAVEEN | Work in progress (90% progress) |
Detail Report
Graph / Photo |
||
116 | Up gradation of Type V Judges flats No 402 Type IV Judges flats No 205 Type VI Judge s flats No 607 and Servant Qtrs. 402 607 and 102 at Karkardooma Court Complex Delhi Civil and Electrical Works | 2023.01.01 | 2023.03.31 | 38.79 | Uma Shankar |
Detail Report
Graph / Photo |
|||
117 | Improvement Multi Model intigration System at Karkardooma Court Metro Station under M-2111 dg. 2022-23. | 2022.07.03 | 2022.09.30 | 38.77 | Ram Kirpal Singh |
Detail Report
Graph / Photo |
|||
118 | Providing Security Guards at North and South Block of New Court Building at District Court Complex, Saket, New Delhi | 2022.10.21 | 2023.01.20 | 37.99 | SS4 SAFENET |
Detail Report
Graph / Photo |
|||
119 | EOR in Sanjay Gandhi Memorial Hospital, Delhi. (SH Construction of Badminton Court, Fixing of grill gate, rain water harvesting well to recharge ground water and other misc. works). | 2019.08.28 | 2019.11.27 | 37.39 | SUSHIL KUMAR | work is in slow progress |
Detail Report
Graph / Photo |
||
120 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings in cupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 35.17 | 11.76 (Oct'22) | 0.00 (Oct'22) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
121 | Up-gradation and enhancement of aesthetic view of Swimming pool premises located at Captain Hanifuddin G.G.S.S.S. Mayur Vihar Phase-1, Pocket-4, Delhi. | 2022.06.03 | 2022.08.31 | 35.06 | 49.30 (Feb'23) | 0.00 (Feb'23) | Dheeraj Singh & Company | Work is under progress. |
Detail Report
Graph / Photo |
122 | CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works | 2020.08.15 | 2020.12.14 | 34.45 | CSM CONSTRUCTION |
Detail Report
Graph / Photo |
|||
123 | Providing and laying interlocking paver block and RMC in the campus of Police Colony at Tilak Marg, New Delhi under MLA LAD Fund Scheme. | 2019.10.27 | 2019.12.25 | 33.92 | 42.37 (Apr'22) | 0.00 (Apr'22) | Gyanchand |
Detail Report
Graph / Photo |
|
124 | Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system | 2019.07.09 | 2019.10.08 | 33.85 | 14.13 (Oct'22) | 0.00 (Oct'22) | SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. | work in Progress 6th RA 18182135 |
Detail Report
Graph / Photo |
125 | Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi | 2019.08.11 | 2019.11.10 | 33.77 | 19.85 (Mar'23) | 0.00 (Mar'23) | Med Freshe Pvt. Ltd. | Work in progress Med Freshe Pvt. Ltd. |
Detail Report
Graph / Photo |
126 | Construction of porta cabins Legal Aid Defence Counsel System office near facilitation centre for Legal Aid Defence Counsel System office Karkardooma Court Delhi. Civil Furniture and Electrical Works 2nd recall | 2022.08.31 | 2022.09.29 | 33.23 | MUZAMMIL ALI |
Detail Report
Graph / Photo |
|||
127 | Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) | 2021.12.16 | 2022.04.15 | 32.92 | 29.75 (Jan'23) | 0.00 (Jan'23) | AKSHAY KUMAR DAGAR |
Detail Report
Graph / Photo |
|
128 | Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) | 2022.04.05 | 2022.07.03 | 32.79 | 30.24 (Nov'22) | 0.00 (Nov'22) | Cembond Construction Pvt. Ltd |
Detail Report
Graph / Photo |
|
129 | Granite stone cladding on outer wall and security measures on back side along boundary wall, internal wall finishing in Vivekananda College, Vivek Vihar, Delhi | 2022.11.05 | 2023.03.04 | 32.71 | 20.35 (Mar'23) | 0.00 (Mar'23) | Universal Construction Company | Work is under progress. |
Detail Report
Graph / Photo |
130 | Providing and fixing retro reflective informatory sign boards at various location of New Delhi constituency AC40 under MLA LAD Fund Scheme | 2019.10.25 | 2020.01.22 | 32.70 | 12.66 (Mar'21) | 0.00 (Mar'21) | Rajesh Kumar Gupta |
Detail Report
Graph / Photo |
|
131 | Renovation and Modification of 32 Nos Chambers of Honble Judge in A Block Delhi High Court New Delhi | 2022.09.09 | 2022.11.07 | 31.97 | 106.99 (Jan'23) | 0.00 (Jan'23) | R L WADHWA | Work in progress |
Detail Report
Graph / Photo |
132 | Construction of Boundary Wall at vacant plot of Nand Nagri, Delhi | 2022.07.12 | 2022.09.09 | 31.83 | 33.43 (Dec'22) | 0.00 (Dec'22) | Harsh Electricals | Work completed. Agency yet to submit final bill. |
Detail Report
Graph / Photo |
133 | Construction of Porta Cabin for PWD Sub Divn. Office of Civil and Electrical including enquiries of both and Development of lab collection centre and shed covering | 2021.01.06 | 2021.04.05 | 31.62 | 0.00 (Oct'22) | 100.00 % (Oct'22) | Nation Star Enterprises | Work is physically 100% completed. Final bill yet to be submitted by the agency. |
Detail Report
Graph / Photo |
134 | Installation of hard drawn wire fabric at D Block and B Block residential quarters for monkey protection in Fire Station Connaught Place New Delhi. | 2019.02.08 | 2019.03.07 | 31.58 | 39.47 (Jul'19) | 90.00 % (Jul'19) | Vasdev | Work in progress |
Detail Report
Graph / Photo |
135 | Renovation of Kotwali Building at Chandni Chowk, Police Station under SRD Division-I, Sub-Division-III, PWD, New Delhi. | 2018.06.25 | 2018.10.24 | 31.39 | 0.00 (Feb'19) | 39.16 % (Feb'19) | Kamal Construction Co. | Work Completed and final bill paid |
Detail Report
Graph / Photo |
136 | SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi | 2018.10.16 | 2018.12.15 | 30.64 | 15.29 (Feb'19) | 50.00 % (Feb'19) | San Infotech Services | work in progress 2nd RA 1696099 |
Detail Report
Graph / Photo |
137 | Providing and fixing furniture at Ground Floor and 1st Floor | 2021.08.15 | 2021.08.29 | 30.45 | 33.54 (Mar'22) | 0.00 (Mar'22) | DURIAN INDUSTRIES LIMITED | In progress. |
Detail Report
Graph / Photo |
138 | Renovation of toilets in J, K & L Block at Karkardooma Court, Delhi (Balance work) (IstRecall) | 2021.12.30 | 2022.03.29 | 30.36 | 20.96 (Nov'22) | 0.00 (Nov'22) | Ravinder Kumar Gupta | In Progress. |
Detail Report
Graph / Photo |
139 | Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 | 2021.12.17 | 2022.04.15 | 29.81 | 28.23 (Feb'23) | 0.00 (Feb'23) | Cembond Construction Pvt. Ltd | In Progress. |
Detail Report
Graph / Photo |
140 | Comprehensive Maintenance of Old Saint Stephens College Building Kashmere Gate, CPO Building, Old Court Building, NCC Offices Buildings, Novelty Fire Station, Fire Station Jama Masjid, Disability Commissioner Office, Lok Nayak Setu Office Compl | 2019.11.17 | 2020.11.16 | 29.01 | 36.24 (Feb'21) | 0.00 (Feb'21) | K.P. Singh & Co. |
Detail Report
Graph / Photo |
|
141 | Urgent Repair and rehabilitation of newly allotted Qtrs. after vacation of E Type Qtrs. in the Residential Campus, GTB Hospital, Shahdara, Delhi | 2022.05.21 | 2022.09.17 | 28.76 | SANENDRA KUMAR | Work is in progress |
Detail Report
Graph / Photo |
||
142 | Painting in Outer side of Court building Administrative Block and Lawyer Chamber Block-II, Delhi High Court New Delhi | 2023.01.12 | 2023.04.11 | 28.19 | 17.92 (Mar'23) | 0.00 (Mar'23) | IRFAN KHAN AND CO. | Work in progress |
Detail Report
Graph / Photo |
143 | Making Accessible approach. Balance Work 1st recall | 2022.09.24 | 2022.12.22 | 27.32 | Shobhit Kumar |
Detail Report
Graph / Photo |
|||
144 | Rehabilitation work in Police Station at Chandni Mahal, Asaf Ali Road, Delhi. | 2019.09.29 | 2020.03.26 | 27.08 | 33.83 (Mar'21) | 0.00 (Mar'21) | Shah Pandya & Shot Crete |
Detail Report
Graph / Photo |
|
145 | Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi | 2022.06.13 | 2022.08.11 | 26.85 | 90.32 (Mar'23) | 0.00 (Mar'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
146 | Civil work, false ceiling, flooring and finishing work at Multilevel Car parking in Delhi High Court, New Delhi. | 2023.03.12 | 2023.06.10 | 25.91 | Yameen | Work in progress |
Detail Report
Graph / Photo |
||
147 | Construction of 01 Nos. Clinical care centre under School Health Scheme on the vacant piece of land between Babu Ram Govt. SBV Bhola Nath Nagar and DIET Shahdara. (Civil, Furniture & Electrical Works). (4th Recall) | 2022.09.16 | 2022.11.14 | 25.77 | 30.48 (Feb'23) | 0.00 (Feb'23) | SUDHIR KUMAR SHARMA |
Detail Report
Graph / Photo |
|
148 | Construction of yard for Malkhana of Police Station Chandni Mahal, Darya Ganj under SRD Division-I, Sub-Division-III, New Delhi. | 2018.07.30 | 2018.10.29 | 25.67 | 23.27 (Sep'19) | 0.00 (Sep'19) | Krishan Kumar | Work in progress |
Detail Report
Graph / Photo |
149 | Repair and renovation of Veterinary Dispensary, Bankner, Animal Husbandry Unit of GNCT of Delhi-110040 | 2022.08.01 | 2022.10.30 | 24.62 | 25.89 (Feb'23) | 0.00 (Feb'23) | Ankur Bhardwaj | Work in Progress |
Detail Report
Graph / Photo |
150 | SITC of Lifts. | 2023.02.21 | 2023.05.20 | 23.60 | Techno Industries Limited |
Detail Report
Graph / Photo |
|||
151 | Renovation & Up-gradation in Residential Quarters in SRHC hospital, Narela | 2022.07.05 | 2022.11.04 | 23.12 | BHUPESH KUMAR | Work in Progress (60% Progress) |
Detail Report
Graph / Photo |
||
152 | Providing and laying bituminous concrete surface at BR Campus, Race course, New Delhi under MLA LAD fund Scheme. 3rd CALL | 2019.11.26 | 2019.12.25 | 22.88 | 25.04 (Nov'21) | 0.00 (Nov'21) | Rajesh Kumar Gupta |
Detail Report
Graph / Photo |
|
153 | Development Cricket ground football field and chain link fencing at newly taken over plot for sports complex at village kair in the Assembly constituency Najafgarh, Delhi. (SH: Comprehensive maintenance of cricket ground for one year) | 2021.04.01 | 2022.03.31 | 22.80 | Devender Pal Singh | work Completed. |
Detail Report
Graph / Photo |
||
154 | Renovation of B Voc Labs | 2019.05.20 | 2019.08.19 | 22.14 | M.Y Construction | 40% Work could not start due to electrical tender not in force. |
Detail Report
Graph / Photo |
||
155 | Re-layering of Damaged Internal Bituminous Roads at Judges Flat including raising of manhole cover, laying of C.C. pavement, paver block & Kerb stone, at Karkardooma Court, Sahadara, Delhi-110032 | 2022.07.15 | 2022.08.13 | 21.86 | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
156 | Supplying and replacement of Outlived Air Handling Units at JPCH Shastri Park, Delhi | 2019.07.22 | 2019.09.21 | 21.72 | US Engineers | Tender is in process |
Detail Report
Graph / Photo |
||
157 | Providing and Fixing of MS tubular Window with Acrylic plastic Sheet | 2019.11.14 | 2020.03.12 | 21.53 | 26.89 (Mar'21) | 0.00 (Mar'21) | KAMAAL CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
158 | Renovation of toilet blocks & miscellaneous civil works- Balance work | 2022.06.26 | 2022.09.23 | 21.44 | Sanjeev Kumar |
Detail Report
Graph / Photo |
|||
159 | Expansion of Lawyers Cafeteria in B Block and Shifting of Filing Counter in Administrative Block & Providing and fixing work stations for IT Branch at Lawyers Chambers Block-III of Delhi High Court New Delhi. | 2023.03.07 | 2023.04.05 | 21.18 | R L WADHWA | Work in progress |
Detail Report
Graph / Photo |
||
160 | Up-gradation of Type-V Judge’s flats No- G-1 Type-VI Judge’s flats No-507 and Servant Qtrs. G-1 & 507 at Karkardooma Court Complex, Delhi. (SH:- Civil Work). | 2022.05.02 | 2022.06.30 | 21.17 | 26.26 (Mar'23) | 0.00 (Mar'23) | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 |
Detail Report
Graph / Photo |
|
161 | Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex | 2022.06.08 | 2022.09.05 | 20.86 | Karan Walia |
Detail Report
Graph / Photo |
|||
162 | Balance Structural Strengthening works | 2022.09.11 | 2022.10.10 | 19.92 | Cembond Construction Pvt. Ltd |
Detail Report
Graph / Photo |
|||
163 | Repair Renovation of Gents Ladies Staff toilet general girls toilet and CWSN toilet block at Sarvodaya Kanya Vidyalaya Prahladpur Banger Delhi (School ID 1310032) | 2022.10.21 | 2022.12.05 | 19.90 | M/s R M constrution | Work in progress |
Detail Report
Graph / Photo |
||
164 | Constn. of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi | 2022.03.20 | 2022.07.17 | 19.68 | Sanender Kumar | Work is in progress |
Detail Report
Graph / Photo |
||
165 | Mechanized cleaning of Underground and Overhead RCC/ PVC water storage tanks at Rajiv Gandhi Super Specialty Hospital, Tahirpur, Delhi. | 2022.04.26 | 2023.04.25 | 19.49 | 14.10 (Feb'23) | 0.00 (Feb'23) | Real Aqua Hygiene Solution | Work in progress. |
Detail Report
Graph / Photo |
166 | Operation and maintenance of compost machines installed in various jail at Prison Complex Mandoli Delhi (4th Call) | 2022.09.26 | 2023.09.25 | 19.02 | Clean India Ventures Pvt. Ltd. | Work is in progress |
Detail Report
Graph / Photo |
||
167 | SITC of CCTV in various Mohalla Clinic under sub division M3513 | 2022.04.13 | 2022.05.12 | 18.93 | YASH ENTERPRISES |
Detail Report
Graph / Photo |
|||
168 | Renovation of toilets in J K and L Block at Karkardooma Court Delhi Balance work | 2021.11.06 | 2022.02.03 | 18.82 | Phoenix Constructions | In Progress. |
Detail Report
Graph / Photo |
||
169 | Provision of chequrred tiles, raising of boundary wall and other misc civil work | 2022.06.26 | 2022.07.25 | 18.67 | 21.25 (Dec'22) | 0.00 (Dec'22) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
170 | SITC of VRV/ VRF Air Condition Plant | 2022.06.12 | 2022.07.11 | 18.55 | 12.64 (Sep'22) | 0.00 (Sep'22) | Airtemp Engineers |
Detail Report
Graph / Photo |
|
171 | Renovation of toilets gutter fixing and barricading work. 1st recall | 2022.08.21 | 2022.12.18 | 18.07 | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 |
Detail Report
Graph / Photo |
|||
172 | Renovation of Ladies Bar Association Room at KKD Courts Delhi. Civil Furniture and Electrical Works 1st recall. | 2023.02.12 | 2023.03.28 | 18.05 |
Detail Report
Graph / Photo |
||||
173 | Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) | 2022.04.01 | 2022.06.29 | 17.32 | 19.11 (Dec'22) | 0.00 (Dec'22) | SABUR ALAM |
Detail Report
Graph / Photo |
|
174 | Const. of office building for Sub Division III SRD Project Divn I at Road No. 47 near Metro Pillar No. 29, Kashmere Gate, Delhi | 2019.09.23 | 2019.12.21 | 17.04 | 21.26 (Jul'20) | 0.00 (Jul'20) | K.P. Singh & Co. |
Detail Report
Graph / Photo |
|
175 | Construction of Conference Hall and Waiting/Reception Hall in Office of Commissioner for Persons with Disabilities at Mata Sundari Road under SRD Division-I, Sub-Division-III, PWD, New Delhi. (SH-Civil Renovation Work). | 2018.08.09 | 2018.11.08 | 16.72 | 15.33 (Oct'19) | 5.60 % (Oct'19) | Intkhab Alam | Work in progress |
Detail Report
Graph / Photo |
176 | Construction of Record Room in Basement of Main Court Building, Saket Court Complex, New Delhi. | 2022.07.18 | 2022.10.17 | 16.50 | 20.37 (Jan'23) | 0.00 (Jan'23) | M Y CONSTRUCTIONS |
Detail Report
Graph / Photo |
|
177 | Construction of missing drain from Jain Nagar Cygnus Hospital upto 40ft road (218mtr) towards Mangolpuri under Sub Division WR-22 during 2022-23. | 2023.01.07 | 2023.03.07 | 16.29 | P L Construction |
Detail Report
Graph / Photo |
|||
178 | A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) | 2017.04.13 | 2017.10.12 | 16.04 | 7.45 (Mar'19) | 46.00 % (Mar'19) | Anup Enterprises |
Detail Report
Graph / Photo |
|
179 | Construction of Rain Water Harvesting Pit inside ITI Campus and ITI Staff Quarter, Vivek Vihar, Delhi. | 2022.07.15 | 2022.10.12 | 15.37 | Shivam Builders |
Detail Report
Graph / Photo |
|||
180 | SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. | 2018.11.07 | 2019.02.04 | 15.26 | 17.61 (Apr'22) | 0.00 (Apr'22) | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 | in progress. |
Detail Report
Graph / Photo |
181 | Providing and supplying plastic moulded table in porta cabins reading room at various places of New Delhi Constituency AC40 under MLA LAD Fund Scheme. | 2019.10.25 | 2019.12.08 | 15.17 | DECOR MODULAR SYSTEM PVT LTD |
Detail Report
Graph / Photo |
|||
182 | Upkeep Service | 2019.10.05 | 2020.10.04 | 15.15 | 19.17 (Sep'22) | 0.00 (Sep'22) | Ashish Gupta |
Detail Report
Graph / Photo |
|
183 | Accessibility works | 2022.08.06 | 2022.10.04 | 15.09 | 12.07 (Nov'22) | 0.00 (Nov'22) | M T Builders |
Detail Report
Graph / Photo |
|
184 | Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work | 2022.05.29 | 2022.08.26 | 14.87 | 18.56 (Dec'22) | 0.00 (Dec'22) | Sushil Kumar |
Detail Report
Graph / Photo |
|
185 | Construction of porta cabin for camp office of Honble Minister at DJB (BPS/UGR) at C-6, Vasant Kunj, New Delhi | 2022.01.04 | 2022.02.03 | 14.34 | 32.27 (Jan'23) | 0.00 (Jan'23) | SHRI DATTA KRUPA ENTER PRISES |
Detail Report
Graph / Photo |
|
186 | Addition & Alteration to Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and fixing roller blinds & cubical track system). | 2023.02.22 | 2023.04.22 | 13.92 | 0.64 (Mar'23) | 0.00 (Mar'23) | Oliver Wallpapers | Work is under progress. |
Detail Report
Graph / Photo |
187 | Construction of Underground sump at ITI Jija Bai for Women, Sirifort, New Delhi (Civil and Electrical work) | 2021.10.23 | 2021.12.22 | 13.91 | 20.16 (Sep'22) | 0.00 (Sep'22) | SHRI DATTA KRUPA ENTER PRISES |
Detail Report
Graph / Photo |
|
188 | Repair/ improvement of berm, footpath and drain at Jaipur Golden Hospital, Sector-3, Rohini | 2022.04.27 | 2022.07.26 | 13.86 | 17.21 (Sep'22) | 0.00 (Sep'22) | Dharambir Singh |
Detail Report
Graph / Photo |
|
189 | Construction of permanent shed on pavement near Gyne OPD registration | 2020.08.18 | 2020.10.17 | 13.73 | SS Enterprises | work in progress. |
Detail Report
Graph / Photo |
||
190 | EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section | 2018.04.02 | 2030.09.15 | 13.58 | L V Enterprises |
Detail Report
Graph / Photo |
|||
191 | Shifting of X Ray machine at Gate No 6 and provision of porta cabin at gate No 6 and covering of vehicle session at gate No 03 | 2019.05.20 | 2019.07.03 | 13.40 | 13.90 (Jan'20) | 0.00 (Jan'20) | Rajeev Kumar | site not available for work 60% |
Detail Report
Graph / Photo |
192 | Renovation of gents and ladies toilet and guniting of ceiling of ground, 1st, 4th, 5th and 6th floor of I block, College of Art at Tilak Marg, New Delhi | 2019.11.14 | 2020.02.11 | 13.30 | 14.80 (Mar'21) | 0.00 (Mar'21) | Amiruddin |
Detail Report
Graph / Photo |
|
193 | Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) | 2022.05.19 | 2022.06.17 | 13.23 | 19.43 (Dec'22) | 0.00 (Dec'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
194 | Repair Renovation of old damaged porta cabins at I block and other miscellaneous work | 2022.03.08 | 2022.05.06 | 12.65 | 15.81 (Jul'22) | 0.00 (Jul'22) | AMIR ISRAR |
Detail Report
Graph / Photo |
|
195 | Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. | 2019.02.10 | 2019.05.10 | 12.52 | 13.79 (Jan'20) | 0.00 (Jan'20) | Daya Sagar Sharma | work in progress |
Detail Report
Graph / Photo |
196 | Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) | 2022.02.02 | 2022.03.03 | 12.04 | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
||
197 | Construction of missing drain from Jain Nagar Cygnus Hospital upto 40ft road (218mtr) towards Mangolpuri under Sub Division WR-22 during 2022-23 | 2022.08.27 | 2022.10.25 | 11.98 | M/s Ashok Builders |
Detail Report
Graph / Photo |
|||
198 | Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi | 2021.12.26 | 2022.02.23 | 11.65 | 11.10 (Feb'23) | 0.00 (Feb'23) | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
199 | Construction of parking shed for students and staff and fixing new aluminium windows in corridor of ground floor, 1st floor, 2nd floor, 3rd floor & rooms along with vension blinds at ITI Narela, Delhi-40 | 2022.10.16 | 2022.12.15 | 11.35 | S.S. Builders | Work in progress |
Detail Report
Graph / Photo |
||
200 | Civil Work. | 2023.02.12 | 2023.05.12 | 11.21 | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 |
Detail Report
Graph / Photo |
|||
201 | Civil Electrical Works | 2021.12.10 | 2022.02.07 | 11.21 | 11.94 (Oct'22) | 0.00 (Oct'22) | Rainbow Constructions | In Progress. |
Detail Report
Graph / Photo |
202 | Providing and fixing down comer and manually operated electronic FA system | 2019.09.19 | 2019.10.18 | 11.18 | 0.00 (Jan'21) | 98.00 % (Jan'21) | M/s Royale Meridian India Pvt Ltd | Work completed. Final bill yet to be paid. |
Detail Report
Graph / Photo |
203 | Provision for Rain Water Harvesting Systems in Govt. Girls Sec. School (Urdu Medium) Lambi Gali, Hauz Qazi under SRD Division-I, Sub-Division-III, PWD, New Delhi dg. 2018-19. | 2019.07.11 | 2019.09.10 | 11.10 | 1.62 (Mar'21) | 0.00 (Mar'21) | Shakur Ahmed & Sons |
Detail Report
Graph / Photo |
|
204 | Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 1 (Hindi Medium) at Jama Masjid, Delhi dg. 18-19 (School ID-2127024.) under SRD Division-I, Sub-Division-III, PWD, New Delhi | 2019.03.11 | 2019.05.10 | 11.09 | 13.85 (Mar'20) | 0.00 (Mar'20) | Mohd. Asad | work in progress |
Detail Report
Graph / Photo |
205 | Renovation of toilet blocks at G/F (02 nos.), F/F (02 nos.) & S/F (01 no.) | 2022.10.05 | 2022.12.03 | 10.79 | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 |
Detail Report
Graph / Photo |
|||
206 | Miscellaneous Civil works | 2022.05.10 | 2022.07.08 | 10.73 | 8.51 (Sep'22) | 0.00 (Sep'22) | Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 |
Detail Report
Graph / Photo |
|
207 | Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi | 2022.05.29 | 2022.06.27 | 10.53 | 12.79 (Oct'22) | 0.00 (Oct'22) | Sundriyal Construction |
Detail Report
Graph / Photo |
|
208 | Construction of Old Age Home at Kanti Nagar Installation of fire doors in the building | 2021.03.04 | 2021.04.02 | 10.22 | 11.71 (Aug'21) | 0.00 (Aug'21) | A. V. ENTERPRISES | In progress. |
Detail Report
Graph / Photo |
209 | Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans | 2022.02.28 | 2022.08.27 | 10.14 | Dashmesh Enterprises |
Detail Report
Graph / Photo |
|||
210 | Construction one no additional toilet at 14/2 Tilak Marg and Renovation of kitchen, toilets and other civil miscellaneous repair works at 36 Ashoka Road under SRD Project Division-I, Sub-Division-IV, PWD, New Delhi | 2019.08.11 | 2019.10.10 | 9.97 | 11.78 (Nov'20) | 0.00 (Nov'20) | Sher Singh |
Detail Report
Graph / Photo |
|
211 | Construction of Two Store Room and renovation of Voter Centre Building Deoli (AC-47), Sector-IV, Pushp Vihar, New Delhi-110017. (Civil and Electrical work) | 2022.01.27 | 2022.03.26 | 9.07 | 11.06 (Jun'22) | 0.00 (Jun'22) | Vision Constructions |
Detail Report
Graph / Photo |
|
212 | Provision for Rain Water Harvesting System in Govt Girls Sr Sec School at Gali Baraf Wali Kinari Bazar Delhi during 2018 19 School ID-1208023 under SRD Division I Sub-Division III PWD New Delhi | 2019.07.11 | 2019.09.10 | 8.86 | 9.64 (May'22) | 0.00 (May'22) | Shakur Ahmed & Sons |
Detail Report
Graph / Photo |
|
213 | Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 2 at Zeenat Mahal, Lal Kuan, Delhi (School ID-2127179) under SRD Division-I, Sub-Division-III, PWD, New Delhi | 2019.07.14 | 2019.09.13 | 8.76 | Shakur Ahmed & Sons |
Detail Report
Graph / Photo |
|||
214 | Providing services of plumbing, carpentry jobs etc RECALL | 2019.11.04 | 2020.11.03 | 8.68 | 8.68 (Mar'21) | 0.00 (Mar'21) | Good Luck Enterprises |
Detail Report
Graph / Photo |
|
215 | Distempering painting and Finishing works of various Schools under sub divn M 2313 of KKD Court Division M 231 during 2021 22 (Balance work) | 2021.12.16 | 2022.03.15 | 8.33 | 7.20 (Jun'22) | 0.00 (Jun'22) | M T Builders | In Progress. |
Detail Report
Graph / Photo |
216 | A R and M O to 405 DA Flats Kalyanvas Delhi 91 dg 2018 19 | 2018.06.18 | 2019.06.14 | 8.03 | 5.04 (Nov'20) | 0.00 (Nov'20) | SABUR ALAM | work in progress 40% |
Detail Report
Graph / Photo |
217 | A/R and M/O to I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Upkeep Service). | 2018.09.25 | 2019.09.24 | 8.01 | 1.56 (Jan'20) | 0.00 (Jan'20) | Ashish Gupta | Work in progress |
Detail Report
Graph / Photo |
218 | Provision for Rain Water Harvesting System in Sarvodaya Bal Vidyalaya at Pataudi House, Darya Ganj, Delhi (School ID-2127003.) under SRD Division-I, Sub-Division-III, PWD, New Delhi | 2019.06.25 | 2019.08.24 | 7.90 | 6.08 (Nov'19) | 0.00 (Nov'19) | SUDHIR KUMAR SHARMA |
Detail Report
Graph / Photo |
|
219 | Furniture work | 2019.10.25 | 2019.12.08 | 7.84 | 7.84 (Mar'21) | 0.00 (Mar'21) | DURIAN INDUSTRIES LIMITED |
Detail Report
Graph / Photo |
|
220 | Construction of public toilet near mortuary, providing shed for blood bank and other misc. works. | 2020.03.18 | 2020.05.17 | 7.80 | Sudhakar Samal | work in progress |
Detail Report
Graph / Photo |
||
221 | Provision for Rain Water Harvesting System in Govt. Boys Sr. Sec. School No. 2 (Hindi Medium) at Jama Msjid, Delhi (School ID-2127006.) under SRD Division-I, Sub-Division-III, PWD, New Delhi | 2019.06.25 | 2019.08.24 | 7.66 | 6.42 (Jan'20) | 0.00 (Jan'20) | SUDHIR KUMAR SHARMA |
Detail Report
Graph / Photo |
|
222 | Wall paneling wooden flooring and toilet renovation work Civil and Electrical works | 2022.06.11 | 2022.07.10 | 7.36 | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
223 | Preparation of one room of 2nd and 3rd floor in front of lift gallery and replacement of gallery window of I Block, College of Art at Tilak Marg, New Delhi | 2019.11.14 | 2020.01.12 | 7.35 | 9.10 (Feb'21) | 0.00 (Feb'21) | Amiruddin |
Detail Report
Graph / Photo |
|
224 | Maintenance of EI & Fans and Operation of Pumps & DG Set | 2022.09.16 | 2023.03.15 | 7.28 | RJP Enterprises |
Detail Report
Graph / Photo |
|||
225 | Installation of rain water harvesting system | 2018.06.02 | 2018.08.01 | 7.23 | 6.04 (Jul'19) | 0.00 (Jul'19) | Mohd Akram | work in progress 70% |
Detail Report
Graph / Photo |
226 | Providing inspection vehicles on hire charge basis inspection vehicles for use in office of Executive Engineer, OPD-II and its sub-divisions | 2022.09.27 | 2023.03.26 | 7.10 | 3.55 (Jan'23) | 0.00 (Jan'23) | SKIEZS | Work is in progress |
Detail Report
Graph / Photo |
227 | A/R and M/O I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Repair and Renovation work of University Staff Quarters at IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi). | 2019.03.29 | 2019.06.28 | 7.01 | Prithvi creation | work in progress |
Detail Report
Graph / Photo |
||
228 | Renovation of D Block 1st Floor MP Hall | 2019.11.28 | 2020.01.26 | 6.80 | 6.89 (Sep'20) | 0.00 (Sep'20) | Mohd Amjad |
Detail Report
Graph / Photo |
|
229 | Construction of underground water storage tanks for upcoming Court Rooms with additional storage facility for existing Court Complex and Residential Complex Saket including upgrading of existing water main line feeding Residential Court Complex--- | 2023.02.03 | 2023.03.02 | 6.57 | ARSHAD |
Detail Report
Graph / Photo |
|||
230 | Operation and Maintenance of 3x110 TR Capacity HVAC System and Servicing Overhauling and Comprehensive running maintenance of WTAC, Water coolers and Split AC units | 2019.04.01 | 2019.12.31 | 6.53 | 7.48 (May'20) | 0.00 (May'20) | M/s Naj Refrigeration & Air Conditioning Works |
Detail Report
Graph / Photo |
|
231 | Sweeping of road, development of rain water harvesting system, CO sump tank and other misc repair works | 2022.08.04 | 2023.05.10 | 6.41 | 2.70 (Oct'22) | 0.00 (Oct'22) | Suresh Ray | Work in Progress |
Detail Report
Graph / Photo |
232 | Renovation of Room No. 126, 129 & 132 in Department of physiology of UCMS college at GTB Hospital, Shahdara, Delhi. | 2022.08.26 | 2022.09.24 | 6.39 | PRASHANT BUILDERS | Work is in progress. |
Detail Report
Graph / Photo |
||
233 | Replacement of wooden sofa chair with new visitor chairs at I/C E.D. Lockup and miscellaneous furniture work at courts of Shahdara District Branch, KKD Court Delhi | 2022.07.09 | 2022.08.07 | 6.07 | 7.32 (Jan'23) | 0.00 (Jan'23) | Ganpati Furniture System Pvt Ltd |
Detail Report
Graph / Photo |
|
234 | Tentage & sitting arrangement | 2022.07.30 | 2022.08.09 | 5.68 | 6.37 (Mar'23) | 0.00 (Mar'23) | Vishal Tents and Decorators | work in progress |
Detail Report
Graph / Photo |
235 | Providing and fixing dustbin at Karkardooma Court Complex, Delhi | 2022.06.13 | 2022.07.12 | 5.66 | 21.88 (Sep'22) | 0.00 (Sep'22) | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
236 | Raising of boundary wall of Lal quarter Kidwai Nagar residential area under MLA LAD Fund Scheme RECALL | 2019.11.04 | 2019.12.18 | 5.60 | 4.89 (Sep'20) | 0.00 (Sep'20) | B P Rai and Sons |
Detail Report
Graph / Photo |
|
237 | Anti termite treatment of Hostel building and P F commercial ply and Mattress on beds of Hostel block Ist recall | 2021.11.21 | 2022.01.19 | 5.42 | 6.45 (Mar'23) | 0.00 (Mar'23) | Verma Pesticides & Pest Control Services Pvt. Ltd. | In progress. |
Detail Report
Graph / Photo |
238 | Civil Works | 2022.09.01 | 2022.09.30 | 5.36 | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
239 | Construction of Rain water Harvesting System at Govt Boys Sr Secondary School Dev Nagar New Delhi Building ID 21281284 | 2019.05.30 | 2019.07.13 | 5.19 | 4.90 (Jan'20) | 0.00 (Jan'20) | Prem Sagar | Work completed final bill paid |
Detail Report
Graph / Photo |
240 | Construction of Rain water Harvesting System in Sarovodya Kanya Vidyalaya Baba Ram Dev at Prasad Nagar New Delhi Building ID 21281295 | 2019.05.30 | 2019.07.13 | 4.97 | 5.56 (Nov'19) | 0.00 (Nov'19) | Prem Sagar | Bill paid |
Detail Report
Graph / Photo |
241 | Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer | 2022.01.31 | 2022.03.31 | 4.93 | 5.35 (Jun'22) | 0.00 (Jun'22) | PURIFIRES INDIA | In Progress. |
Detail Report
Graph / Photo |
242 | Providing Furnitures at Ladies Bar Association Room at KKD courts, Delhi. | 2023.03.22 | 2023.04.20 | 4.88 | Uma Shankar |
Detail Report
Graph / Photo |
|||
243 | Major repair work on water supply pipe line tanks. | 2023.02.11 | 2023.04.11 | 4.70 | 5.87 (Mar'23) | 0.00 (Mar'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
244 | Construction of one additional toilet for visitors at Camp Office of Honble Minister at C6, Vasant Kunj, New Delhi | 2022.10.24 | 2022.11.23 | 4.64 | MOHAN LAL |
Detail Report
Graph / Photo |
|||
245 | Civil Works. 1st Recall | 2023.01.06 | 2023.02.04 | 4.63 | Mohd. WAZID |
Detail Report
Graph / Photo |
|||
246 | E.O.R. to repair and replacement of sewer line, rain water disposal line and other misc. repair work in Police Station, Darya Ganj, Delhi dg. 2018-19 (SH- Improvement of drainage system under SRD Division-I, Sub-Division-III, PWD, New Delhi). | 2019.02.26 | 2019.04.25 | 4.59 | 5.27 (Jun'19) | 0.00 (Jun'19) | Prashant Gupta | work in progress |
Detail Report
Graph / Photo |
247 | Anti termite treatment of Hostel building and PF commercial ply and Mattress on beds of Hostel block | 2021.09.29 | 2021.11.27 | 4.41 | Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 |
Detail Report
Graph / Photo |
|||
248 | EOR to Police Colony, Rajinder Nagar, New Delhi during 2018-19.(SH- Covering of open drain in Police Colony). | 2018.05.30 | 2018.07.28 | 4.37 | 5.48 (Aug'19) | 0.00 (Aug'19) | G.S construction | wip |
Detail Report
Graph / Photo |
249 | Misc. civil repair work | 2019.09.15 | 2019.12.14 | 4.36 | 5.44 (Oct'21) | 0.00 (Oct'21) | Shabbi Abbas |
Detail Report
Graph / Photo |
|
250 | Installation of 1 no. borewell at Fire Station Tahirpur Delhi dg. 2022 23. Civil and Electrical Works | 2022.09.21 | 2022.10.20 | 3.93 | 4.26 (Oct'22) | 0.00 (Oct'22) | Lucky Project |
Detail Report
Graph / Photo |
|
251 | RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. | 2019.02.03 | 2020.02.02 | 3.91 | 1.61 (Jul'19) | 0.00 (Jul'19) | ARORA ELECTRICAL WORKS |
Detail Report
Graph / Photo |
|
252 | EOR to National Law University, Sec-14, under Sub Div-III, SWBMD, New Delhi during 2018-19.(SH- Cleaning of sewerline by using super sucker machine). | 2018.06.05 | 2018.09.02 | 3.81 | 3.81 (Dec'18) | 70.00 % (Dec'18) | Surender Singh Chahal | work in progress |
Detail Report
Graph / Photo |
253 | Replacement of broken kota stone flooring and wooden racks, false ceiling and white washing of MFA final year Sculpture Studio, College of Art at Tilak Marg, New Delhi | 2019.11.15 | 2019.12.14 | 3.73 | 4.31 (Apr'21) | 0.00 (Apr'21) | Sher Singh |
Detail Report
Graph / Photo |
|
254 | Replacement of broken glass and painting of grills of window providing and fixing of signage board and other misc. work at DIET Building Karkardooma Institutional area Delhi 110032 1st Recall | 2022.09.09 | 2022.10.08 | 3.59 | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
255 | Barricading of dangerous portion of old school building, chipping of unsound/weak concrete & demolishing damaged RCC & brick work in Gandhi Memorial School, Shahdara (Near Shyamlal College), Delhi. (1st recall) | 2022.08.17 | 2022.09.15 | 3.26 | N.M. CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
256 | Providing and fixing dustbin at Karkardooma Court Complex Delhi | 2021.12.10 | 2022.01.08 | 3.10 | Saman Mehboob | In Progress. |
Detail Report
Graph / Photo |
||
257 | Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23 | 2022.08.26 | 2022.09.24 | 3.06 | PRASHANT BUILDERS |
Detail Report
Graph / Photo |
|||
258 | Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil and Electrical Works (2nd Recall) | 2022.03.19 | 2022.04.17 | 2.62 | Mohd. WAZID |
Detail Report
Graph / Photo |
|||
259 | A/R and M/O to I.G.D.T.U.W. at Kashmere Gate under Sub-Division-III, SRD Division-I, PWD, New Delhi During 2017-18 (SH-Specialized waterproofing treatment in the profile sheet gutter of workshop behind MAE Block). | 2018.04.21 | 2018.05.20 | 2.62 | 0.00 (Jul'18) | 2.90 % (Jul'18) | Garg Waterproofing Company | Work Completed and final bill paid |
Detail Report
Graph / Photo |
260 | Renovation work | 2023.01.13 | 2023.02.11 | 2.61 | Mohd Azam |
Detail Report
Graph / Photo |
|||
261 | Renovation of office of Secretary in DSSSB Building at Karkardooma Shahdara Delhi dg 2022 23 | 2022.08.03 | 2022.09.01 | 2.56 | 6.25 (Feb'23) | 0.00 (Feb'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
262 | Providing and erecting permanent barricading around dangerous building in Kasturba Kustha Ashram Tahirpur Delhi 1st recall | 2021.12.11 | 2022.01.09 | 2.50 | 2.67 (Jul'22) | 0.00 (Jul'22) | Akhil Okharwal | In Progress. |
Detail Report
Graph / Photo |
263 | Installation of Stainless Steel Grill on the window for safety and security of Valuable assets | 2022.06.13 | 2022.07.12 | 2.29 | 2.84 (Jun'22) | 0.00 (Jun'22) | Mohd Azam |
Detail Report
Graph / Photo |
|
264 | Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil Electrical Works Ist Recall | 2022.01.08 | 2022.02.06 | 2.25 | MUZAMMIL ALI |
Detail Report
Graph / Photo |
|||
265 | Construction of security gates near entrance road of Church of Divine Mercy in Shakurbasti Assembly Constituency AC-15 under MLALAD scheme, during 2021-2022. (3rd call) | 2022.03.24 | 2022.05.23 | 2.19 | 1.13 (Sep'22) | 0.00 (Sep'22) | A J & CO. |
Detail Report
Graph / Photo |
|
266 | Installation of 1 no. bore well at Fire Station, Tahirpur Delhi dg. 2021 22. Civil and Electrical Works | 2021.11.21 | 2021.12.20 | 2.16 | Sudesh Jain |
Detail Report
Graph / Photo |
|||
267 | Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 | 2022.06.22 | 2022.07.06 | 2.08 | 2.09 (Aug'22) | 0.00 (Aug'22) | CHETAN SHARMA |
Detail Report
Graph / Photo |
|
268 | A/R and M/O other PWD Roads under SRD Division -I, PWD, New Delhi during 2019-20. (SH- Painting of Kerb Stones on various roads for Independence Day under Sub Division-II.) | 2019.08.13 | 2019.08.27 | 2.06 | 2.27 (Nov'19) | 0.00 (Nov'19) | MOHD AFTAB |
Detail Report
Graph / Photo |
|
269 | A/A to RCL Tahirpur Sunder Nagri, Delhi during 2021-22.SH:- Providing and erecting permanent barricading around the dangerous buildings in Kasturba Kustha Ashram Tahirpur Delhi | 2021.09.03 | 2021.10.02 | 1.95 | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
||
270 | SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. | 2022.03.25 | 2022.04.23 | 1.90 | MKSC Design India Private Limited | Work in Progress |
Detail Report
Graph / Photo |
||
271 | Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri | 2021.09.04 | 2021.10.03 | 1.85 | 0.88 (Mar'22) | 0.00 (Mar'22) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
272 | Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner | 2021.09.05 | 2023.09.04 | 1.81 | 0.82 (Dec'22) | 0.00 (Dec'22) | Frank Copier Pvt. Ltd. |
Detail Report
Graph / Photo |
|
273 | Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. | 2022.06.23 | 2022.07.07 | 0.74 | 0.74 (Sep'22) | 0.00 (Sep'22) | Kesari & Associates |
Detail Report
Graph / Photo |
|
274 | Soil investigation and bearing capacity of soil | 2021.08.19 | 2021.08.28 | 0.50 | Allied Engineers |
Detail Report
Graph / Photo |
|||
275 | Repairing of aluminium doors & Shutters. | 2014.08.19 | 2014.09.03 |
Detail Report
Graph / Photo |
|||||
276 | Providing and laying RCC drain cover in open surface drain in basement. | 2014.08.16 | 2014.09.15 | 2.58 (Mar'21) | 0.00 (Mar'21) |
Detail Report
Graph / Photo |
|||
277 | Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. | 2014.09.16 | 2014.10.15 |
Detail Report
Graph / Photo |
|||||
278 | Finishing of exterior wall in 20 nos. CBI flats. | 2014.12.08 | 2014.12.26 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
279 | P/F Manhole cover & Drain cover. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
280 | Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. | 2014.08.18 | 2015.01.01 |
Detail Report
Graph / Photo |
|||||
281 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. | 2015.01.08 | 2015.02.04 |
Detail Report
Graph / Photo |
|||||
282 | Providing services of labour for day to day maintenance under Sub-Division M-2334. | 2014.05.31 | -- |
Detail Report
Graph / Photo |
|||||
283 | Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. | 2014.09.18 | 2014.10.17 |
Detail Report
Graph / Photo |
|||||
284 | Replacement of Damaged roof of Sub Divn. Office M-233. | 2014.11.11 | 2014.12.10 | 35.49 (Aug'21) | 0.00 (Aug'21) |
Detail Report
Graph / Photo |
|||
285 | Cleaning of sewer line, manhole & gully traps etc. | 2014.12.22 | 2015.01.21 |
Detail Report
Graph / Photo |
|||||
286 | Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. | 2015.01.24 | 2015.02.23 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
287 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
288 | Providing and fixing polycarbonate in available. | 2014.12.19 | 2015.01.18 |
Detail Report
Graph / Photo |
|||||
289 | Improvement of Open Space in Circle Office & Division Office. | 2015.02.06 | -- | Rajeev Sharma |
Detail Report
Graph / Photo |
||||
290 | Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. | 2015.01.17 | 2015.02.16 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
291 | Providing and fixing FRP door shutters in place of old damaged flush door shutters. | 2014.09.18 | 2014.10.17 |
Detail Report
Graph / Photo |
|||||
292 | Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. | 2015.02.08 | 2015.03.08 |
Detail Report
Graph / Photo |
|||||
293 | Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. | 2015.02.06 | 2015.03.15 |
Detail Report
Graph / Photo |
|||||
294 | Water proofing treatment of first floor toilet. | 2014.12.15 | 2015.01.14 |
Detail Report
Graph / Photo |
|||||
295 | Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. | 2015.02.06 | 2015.02.20 |
Detail Report
Graph / Photo |
|||||
296 | Wall tile and other misc. civil work in Sports Complex at East Vinod Nagar. | 2015.02.27 | 2015.03.26 |
Detail Report
Graph / Photo |
|||||
297 | Providing & fixing door and installation of PVC overhead tank for fire safety. | 2015.01.17 | -- |
Detail Report
Graph / Photo |
|||||
298 | Misc. Civil Works. | 2015.03.16 | 2015.03.30 | Shekhar |
Detail Report
Graph / Photo |
||||
299 | Providing ramps in Schools & miscellenious works. | 2015.02.12 | 2015.02.26 |
Detail Report
Graph / Photo |
|||||
300 | P/F Floor tile & broken tile. | 2015.11.20 | 2015.12.12 |
Detail Report
Graph / Photo |
|||||
301 | Providing and laying cement concrete. | 2015.03.12 | 2015.03.25 | Indal Yadav |
Detail Report
Graph / Photo |
||||
302 | Providing railing for Park. | 2015.11.23 | 2015.12.05 |
Detail Report
Graph / Photo |
|||||
303 | Renovation of D.D.E. office by changing sanitary & plumbing fixtures in office toilet and internal finishing works | 2016.07.04 | 2016.09.03 | 0.00 (Aug'16) | 40.00 % (Aug'16) | Work completed |
Detail Report
Graph / Photo |
||
304 | Construction of Double storeyed SPS type rooms for Cal lab,Library,Science labs,toilet for HOS & staff at Govt. Co.Ed.Edn.Dichaon Kalan,New Delhi. | 2017.12.18 | 2019.06.15 | 34.21 (Jun'19) | 100.00 % (Jun'19) | work in progress. |
Detail Report
Graph / Photo |
||
305 | Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. | 2016.06.25 | 2016.07.24 | WORK RESCIENED. |
Detail Report
Graph / Photo |
||||
306 | C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. | 2016.03.25 | 2016.07.24 | 0.00 (Aug'16) | 75.00 % (Aug'16) | DOSE PERTAIN TO THIS DIVISION |
Detail Report
Graph / Photo |
||
307 | Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) | 2016.05.10 | 2016.06.09 | 0.00 (Jul'16) | 50.00 % (Jul'16) | Tender re-call and date of opening 24-09-2016 |
Detail Report
Graph / Photo |
||
308 | EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System | 2016.05.23 | 2016.06.23 | 0.00 (Jul'16) | 70.00 % (Jul'16) | Dose not pertain to this Division |
Detail Report
Graph / Photo |
||
309 | EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. | 2016.04.15 | 2016.10.14 | 0.00 (Jul'16) | 10.00 % (Jul'16) | Completed |
Detail Report
Graph / Photo |
||
310 | EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. | 2016.04.15 | 2016.07.14 | 0.00 (Jul'16) | 15.00 % (Jul'16) | Completed |
Detail Report
Graph / Photo |
||
311 | Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS | 2016.04.05 | 2016.06.04 | 0.00 (Jul'16) | 80.00 % (Jul'16) | Completed |
Detail Report
Graph / Photo |
||
312 | Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. | 2016.01.17 | 2016.04.30 | 0.00 (Jul'16) | 80.00 % (Jul'16) | polycarbonate |
Detail Report
Graph / Photo |
||
313 | providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. | 2016.05.01 | 2016.06.30 | 0.00 (Jul'16) | 0.01 % (Jul'16) | work in progress |
Detail Report
Graph / Photo |
||
314 | E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi | 2016.04.10 | 2016.06.09 | 0.00 (Jul'16) | 0.01 % (Jul'16) | Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270 |
Detail Report
Graph / Photo |
||
315 | Construction of new boundary wall | 2016.04.24 | 2016.07.20 | 21.77 (May'17) | 100.00 % (May'17) |
Detail Report
Graph / Photo |
|||
316 | Repair and renovation of toilets | 2016.06.17 | 2016.08.15 | 0.00 (Sep'16) | 91.00 % (Sep'16) | Detailed estimate under process. |
Detail Report
Graph / Photo |
||
317 | Renovation of Classrooms, Corridor, Principal Room & Staff Room. | 2016.06.16 | 2016.09.13 | 0.00 (Sep'16) | 53.00 % (Sep'16) | T.S. under process. |
Detail Report
Graph / Photo |
||
318 | Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. | 2016.10.16 | 2016.11.15 | forfeited |
Detail Report
Graph / Photo |
||||
319 | Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050. | 2016.08.20 | 2016.09.15 | 0.00 (Aug'16) | 0.01 % (Aug'16) | work completed |
Detail Report
Graph / Photo |
||
320 | C/o 20 Nos. SPS type class rooms including toilet blocks, staircase and electrical installations, fan etc. at Sarvodaya (Co-ed) Sr. Sec. School, Netaji Nagar, (School I.D.) 1719102, Building I.D. 17191327). New Delhi | 2014.11.04 | 2015.09.30 | 85% Work is in Progress |
Detail Report
Graph / Photo |
||||
321 | Up gradation to Delhi Govt. D-II Flats, Vasant Kunj, New Delhi. | 2017.02.05 | 2017.08.04 | 100.57 (Jul'18) | 100.00 % (Jul'18) | completed |
Detail Report
Graph / Photo |
||
322 | Providing Services of Security Guard at T.V. Branch Enquiry Office | 2017.04.10 | 2018.04.09 | 2.52 (Apr'18) | 90.00 % (Apr'18) | Work completed |
Detail Report
Graph / Photo |
||
323 | Acoustic treatment system and renovation of multipurpose hall. | 2017.10.20 | 2018.01.17 | 40.27 (Nov'21) | 0.00 (Nov'21) | 65% (Work is delayed due to ongoing electrical work as well as Covid-19) |
Detail Report
Graph / Photo |
||
324 | Acoustic work. | 2018.02.02 | 2018.04.01 | 67.40 (Jul'18) | 100.00 % (Jul'18) | work in progress |
Detail Report
Graph / Photo |
||
325 | A/R and M/O to Residential and Non Residential building under Building Maintenance Sub Division (SW) - 4, PWD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19.(SH Engaging labour for Day to Day Maintenance). | 2018.05.17 | 2019.05.16 | 94.01 (Mar'20) | 0.00 (Mar'20) | WORK IN PROGRESS |
Detail Report
Graph / Photo |
||
326 | AR and MO to District Court Resid. Complex Saket, ND-18-19 (SH Cleaning, mopping of common area, like lift lobby, staircase, basement, community centre, footpath area, terrace, servant qtr. etc. by mopping machine at Resid. Complex Saket Court, ND). | 2018.09.25 | 2019.09.24 | 0.49 (Nov'18) | 25.00 % (Nov'18) | work in progress |
Detail Report
Graph / Photo |
||
327 | Construction of New block Forensic Science Laboratory, Rohini, New Delhi | 2020.03.06 | 2021.09.05 | 212.87 (Aug'21) | 0.00 (Aug'21) | work in progress |
Detail Report
Graph / Photo |
||
328 | A/R and M/O to residential and Non residential Building under Sub Div-II of SWBMD at ITI Campus, Pusa, New Delhi during 2018-19.(Sh- Misc repair work and finishing work in quarters). | 2018.05.23 | 2018.11.21 | 14.29 (Jul'19) | 0.00 (Jul'19) | work in progress. |
Detail Report
Graph / Photo |
||
329 | Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. | 2018.11.02 | 2019.11.01 | 214.77 (Sep'19) | 0.00 (Sep'19) | Work in progress |
Detail Report
Graph / Photo |
||
330 | Construction of Boundary wall at Sayurpur Village, New Delhi. (SH- Providing fixing grills and concertina coil at boundary wall). | 2018.07.10 | 2018.09.09 | work in progress |
Detail Report
Graph / Photo |
||||
331 | A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). | 2018.08.03 | 2018.10.01 | 0.25 (May'22) | 0.00 (May'22) | WORK IN PROGRESS |
Detail Report
Graph / Photo |
||
332 | Construction of additional SPS type classrooms in Govt Schools Directorate of Education under Priority II | 2019.09.05 | 2020.09.04 | 0.11 (Nov'19) | 0.00 (Nov'19) | work in progress |
Detail Report
Graph / Photo |
||
333 | A/A in Sanjay Gandhi Memorial Hospital, Mangolpuri, Delhi. (SH Renovation of ENT OPD, OST Centre, CMO room in main casualty, patient toilet in ward-4, change of floor tiles in digital X-ray room and change of windows in physiotherapy department etc. | 2019.09.12 | 2020.01.09 | 16.74 (May'22) | 0.00 (May'22) | work is in slow progress |
Detail Report
Graph / Photo |
||
334 | Raising of main gate, C/o guard room, repair of ground water tank, providing and fixing IRC fabric jali inside the Class rooms etc. | 2019.06.30 | 2019.08.29 | 1.60 (Mar'21) | 0.00 (Mar'21) | work completed |
Detail Report
Graph / Photo |
||
335 | Construction of Recreation Room, Coys room, Officers Quarters and Shed. | 2019.06.30 | 2019.08.29 | 51.12 (Jul'20) | 0.00 (Jul'20) | work completed |
Detail Report
Graph / Photo |
||
336 | Construction of 2 nos.Viewers stand in Parade ground at PTS, Wazirabad, Delhi | 2019.06.30 | 2019.07.19 | 8.39 (Jan'20) | 0.00 (Jan'20) | work completed |
Detail Report
Graph / Photo |
||
337 | Attending complaints of routine maintenance of service centre PTS, Wazirabad, Delhi. | 2019.06.30 | 2020.06.29 | 7.20 (Mar'20) | 0.00 (Mar'20) | work completed |
Detail Report
Graph / Photo |
||
338 | Renovation of 10 Nos toilet blocks, Construction of 3 nos. R.C.C. tank of size 8 x 5 mtr. and 6 nos. M.S. grill gates. | 2019.06.30 | 2019.08.29 | 52.31 (Aug'20) | 0.00 (Aug'20) | work completed |
Detail Report
Graph / Photo |
||
339 | Providing the services of Security Guard for day to day maintenance at D-II flats. | 2019.08.02 | 2020.08.01 | work in progress |
Detail Report
Graph / Photo |
||||
340 | Providing security guards at Division Office M-222 (NE), Sub Division M-2222, Sub Division M-2221, Sub Division Office Loni Road and Division M-222 | 2019.06.30 | 2020.05.29 | 23.93 (Mar'21) | 0.00 (Mar'21) | work completed |
Detail Report
Graph / Photo |
||
341 | Attending day to day complaints | 2019.06.24 | 2020.06.23 | 10.22 (Oct'20) | 0.00 (Oct'20) | work completed |
Detail Report
Graph / Photo |
||
342 | Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi | 2019.06.30 | 2019.08.29 | 26.71 (Mar'21) | 0.00 (Mar'21) | work in progress |
Detail Report
Graph / Photo |
||
343 | Pumping out rainwater to avoid water logging at DC office complex,Weavers Complex Nand Nagri and SDM Court Seelampur Delhi. | 2019.06.30 | 2019.10.29 | 5.86 (Jan'20) | 0.00 (Jan'20) | work completed |
Detail Report
Graph / Photo |
||
344 | External plaster work of Judges Flats Including tile work in over head water storage tank of block D AND E, Steel works and other Misc. work | 2019.10.24 | 2020.01.23 | work in progress |
Detail Report
Graph / Photo |
||||
345 | External plaster work including painting. | 2019.06.16 | 2019.09.15 | work in progress |
Detail Report
Graph / Photo |
||||
346 | Redevelopment of rain water harvesting pits and cleaning of storm water lines at Residential and Non-Residential Complex, Saket Court, New Delhi. | 2019.07.25 | 2019.09.24 | work in progress |
Detail Report
Graph / Photo |
||||
347 | Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. | 2019.07.24 | 2021.09.22 | in progress. |
Detail Report
Graph / Photo |
||||
348 | RPVV Gandhi Nagar (School Id- 1003261) | 2019.03.17 | 2019.12.11 | 12491.60 (Nov'20) | 0.00 (Nov'20) | 48 rooms handed over to HOS on 25.03.2022. 42 Additional Rooms handed over to HOS on 10.11.2022. |
Detail Report
Graph / Photo |
||
349 | GGSSS Mayur Vihar Ph-3 (Kondali Gharauli) (School Id- 1002352) | 2019.03.17 | 2019.12.11 | 0.00 (Jan'21) | 1.00 % (Jan'21) | Work completed. |
Detail Report
Graph / Photo |
||
350 | SKV Patparganj (School Id- 1002031) | 2019.03.17 | 2019.12.11 | 12491.60 (Nov'20) | 0.00 (Nov'20) | Work completed. |
Detail Report
Graph / Photo |
||
351 | GGSSS Khichripur (School Id- 1002037) | 2019.03.17 | 2019.12.11 | 0.00 (Jan'21) | 30.00 % (Jan'21) | Work completed. |
Detail Report
Graph / Photo |
||
352 | AR and MO to Delhi Sachivalaya at IG Stadium Complex New Delhi dg 2018 19 | 2018.11.10 | 2019.05.09 | 1.02 (Jul'19) | 0.00 (Jul'19) | Work in Progress 95% |
Detail Report
Graph / Photo |
||
353 | Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). | 2018.12.06 | 2019.08.02 | 308.01 (May'22) | 0.00 (May'22) | WORK IN PROGRESS |
Detail Report
Graph / Photo |
||
354 | EOR to Govt. Co-ed. Sr. Sec. School at Daulatpur and Govt. Co-ed. Sr. Sec. School at Malikpur, New Delhi. (Sh- C/o Rain Water Harvesting System). | 2019.03.04 | 2019.05.02 | 69.90 (Aug'19) | 0.00 (Aug'19) | WORK IN PROGRESS |
Detail Report
Graph / Photo |
||
355 | GGSSS DDA Flat, Kalkaji, Phase-II, School ID: 1925041 | 2019.01.14 | 2019.10.10 | 0.00 (Sep'21) | 65.00 % (Sep'21) | Work is in progress |
Detail Report
Graph / Photo |
||
356 | GGSSS No. 3, Kalkaji School ID : 1925039 | 2019.01.14 | 2019.10.10 | 10365.03 (Nov'21) | 0.00 (Nov'21) | Work is in progress |
Detail Report
Graph / Photo |
||
357 | SKV,, Jonapur- BNK, School ID: 1923003 | 2018.12.08 | 2019.08.04 | 0.00 (Sep'21) | 65.00 % (Sep'21) | Work is in progress |
Detail Report
Graph / Photo |
||
358 | EOR to GBSSS Bijwasan, Govt. Sarvodaya Co-ed Sr. Sec. School Kitchner Road (Malcha Marg), DIET Sec-07 R.K. Puram etc New Delhi.(Sh- Construction of Rain Water Harvesting System). | 2019.02.22 | 2019.04.24 | 47.84 (Jul'19) | 80.00 % (Jul'19) | WORK IN PROGRESS. |
Detail Report
Graph / Photo |
||
359 | Comprehensive architectural consultancy services for Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Jaffarpur Kalan, Nangli Sakrawati and Qutubapur (Sainik Vihar) New Delhi. (Package-1) | 2021.10.04 | 2022.10.03 | 48.15 (Jan'23) | 0.00 (Jan'23) | Agency yet to submit the structural & service drawings vide this office letter No. 54(58) Edu. M. (East & North East)/PWD/ 151 dated: 28.02.2023 |
Detail Report
Graph / Photo |
||
360 | Mechanised cleaning of UG OH tank, water storage tanks, Sewer lines, Storm water drains, profile sheet, Distempering, Painting and Misc. repair work | 2021.10.18 | 2022.05.17 | Work in Progress |
Detail Report
Graph / Photo |
||||
361 | Construction of Hospital at Hastsal, New Delhi | 2021.06.17 | 2023.06.16 | 70.11 (Mar'23) | 0.00 (Mar'23) | Work is under progress and overall physical progress (Civil part) of work is 27%. |
Detail Report
Graph / Photo |
||
362 | Renovation of Labour room, Public toilet at 5th floor in MCH block and other misc. works | 2021.03.17 | 2021.07.16 | 9.25 (May'22) | 0.00 (May'22) | work in progres |
Detail Report
Graph / Photo |
||
363 | Grit Wash and Internal Finishing for ABIT main building and exterior and internal finishing of workshop. | 2020.11.02 | 2021.05.01 | Work in progress |
Detail Report
Graph / Photo |
||||
364 | Replacement of existing water closet with single piece water closet set, P/F floor and wall tile in toilets, replacement of damaged window and misc. civil works | 2020.11.18 | 2020.11.28 | In Progress. |
Detail Report
Graph / Photo |
||||
365 | Replacement of damaged, rusted G.I. Pipelines of hospital and provision of borewell Water Pipeline and Tanks on Campus roof at Chacha Nehru Bal Chikitsalaya, Geeta Colony, Delhi dg. 2021-22 (Balance Work) | 2022.04.18 | 2022.07.16 | work completed. |
Detail Report
Graph / Photo |
||||
366 | Misc Civil repairing work in Lift pit, lift shaft and machine room in OBH and GH at residential campus GTBH | 2021.09.04 | 2021.10.03 | Work is held up by the agency. |
Detail Report
Graph / Photo |
||||
367 | Construction of Boundary wall at Plot No. FA 6 for District office and bataliyan, Women training college, Police line and Advanced research and Training Institute of Delhi Police Officers Narela, Delhi 110040 | 2022.01.20 | 2022.05.20 | Work in Progress |
Detail Report
Graph / Photo |
||||
368 | Development of play ground and construction of boundary wall. (Balance Work) | 2022.01.20 | 2022.05.20 | Work in Progress |
Detail Report
Graph / Photo |
||||
369 | Renovation of Qtr no. 24,27,29,30,35,36,38 and 39 Type IV Qtrs Balance Work | 2021.11.22 | 2021.09.27 | 22.75 (Oct'22) | 0.00 (Oct'22) | Work in progress |
Detail Report
Graph / Photo |
||
370 | C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) | 2019.09.04 | 2021.03.03 | 502.23 (Mar'23) | 0.00 (Mar'23) | work in progress |
Detail Report
Graph / Photo |
||
371 | Development of play ground and construction of boundary wall | 2022.01.20 | 2022.05.20 | Work in progress |
Detail Report
Graph / Photo |
||||
372 | Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING) | 2019.03.17 | 2019.12.11 | 0.00 (Jan'21) | 1.00 % (Jan'21) | Handed over to HOS. |
Detail Report
Graph / Photo |
||
373 | Jhilmil Colony-SBV Avinash Chadda (ID: 1001105 ) (Addl. Rooms) | 2022.04.01 | 2023.02.24 | 1st floor beam of 6 class room portion is in progress and foundation work of 2 class room & staircase is in progress at GGSSS/GSBV Jhilmil colony. |
Detail Report
Graph / Photo |
||||
374 | Construction of Mother and Child Block and Screening OPD Block at Dr. BSA Hospital at Rohini, Delhi, i/c Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Supply of Furniture). | 2020.03.06 | 2021.09.05 | 226.95 (Nov'22) | 0.00 (Nov'22) | work in progress |
Detail Report
Graph / Photo |
||
375 | Construction of 16 Nos. additional SPS class rooms (G+3) in GGSSS, Qadipur, Delhi ( Sch Id 1309265) (SH: C/o main SPS type building including internal & external water supply, sanitary installation, electrical installations, development of site i/c Fire fighting system etc. at GGSSS Qadipur Delhi -110036. (Sch. ID: 1309265) | 2022.04.14 | 2022.10.11 | 180.21 (Mar'23) | 0.00 (Mar'23) | Finishing works are in progress. |
Detail Report
Graph / Photo |
||
376 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24 | 2022.05.14 | 2024.05.13 | Work is in progress. |
Detail Report
Graph / Photo |
||||
377 | Balance Work (3rd Call) | 2022.04.18 | 2022.07.16 | Work completed. |
Detail Report
Graph / Photo |
||||
378 | Repairs & maintenance of Resource Center for Children with special needs: 1208014--Partap Nagar-SKV | 2022.06.30 | 2022.08.30 | Work in Progress |
Detail Report
Graph / Photo |
||||
379 | Providing for Services Day to Day Maintenance | 2022.06.04 | 2023.06.03 | Work in progress |
Detail Report
Graph / Photo |
||||
380 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 | 2022.06.03 | 2024.06.02 | 263.05 (Mar'23) | 0.00 (Mar'23) | Work in progress. |
Detail Report
Graph / Photo |
||
381 | Replacement of damaged, rusted G.I. Pipelines of hospital and provision of borewell Water Pipeline and Tanks on Campus roof at Chacha Nehru Bal Chikitsalaya, Geeta Colony, Delhi dg. 2021-22 (Balance Work) | 2022.04.18 | 2022.07.16 | Work completed. |
Detail Report
Graph / Photo |
||||
382 | Construction of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi | 2022.03.20 | 2022.07.19 | Work is in progress |
Detail Report
Graph / Photo |
||||
383 | Making school buildings barrier free and accessible to children with special needs 1310400 Ghoga G(CO ED) SSS | 2021.12.17 | 2022.02.01 | Work in progress |
Detail Report
Graph / Photo |
||||
384 | Providing vehicle on hire charge basis for official purpose | 2022.02.25 | 2023.02.24 | Work in progress. |
Detail Report
Graph / Photo |
||||
385 | Providing Services of Computer Operator, MTS etc. under various PWD Offices of North Building Division and office of SA North | 2022.02.01 | 2023.01.26 | Work in progress |
Detail Report
Graph / Photo |
||||
386 | Construction of Boundary Wall on Vacant land at Dwarka sector 12 & 13 at New Delhi | 2022.09.03 | 2023.01.02 | 141.26 (Mar'23) | 0.00 (Mar'23) | PCC work, footing casting, column casting &casting of plinth beam is in progress. Brick work above plinth is in progress. |
Detail Report
Graph / Photo |
||
387 | Maintenance and upkeeping of sewerage, drainage system and desilting of gully traps, manholes, Plumbing and Carpentry works etc. within the campus of Delhi Government Dispensaries situated at various places in constituencies of East, North-East and Shahdara Districts of Delhi | 2022.08.01 | 2023.03.31 | Work is in progress. |
Detail Report
Graph / Photo |
||||
388 | Changing the Windows of Nurse Hostel in Residential Campus at GTB Hospital Shahdara Delhi | 2022.08.24 | 2022.11.23 | Work is in progress |
Detail Report
Graph / Photo |
||||
389 | A/R & M/O to Rouse Avenue Court Complex at DDU Marg, New Delhi During 2022-23 & 2023-24. (SH: Operation and Maintenance of STP Plant of 180 KLD). | 2022.09.30 | 2024.09.29 | Work is in progress |
Detail Report
Graph / Photo |
||||
390 | Construction of Machaan for Security Purpose and Control Room for Installation of UVSS System at Gate No. 5 of Rouse Avenue Court Complex, DDU Marg, New Delhi. | 2022.10.03 | 2022.12.01 | 5.83 (Jan'23) | 0.00 (Jan'23) | Work is in progress |
Detail Report
Graph / Photo |
||
391 | Urgent Repair of boundary wall of Parking between Gate No 1 and 2 and pump house at GTB Hospital Shahdara Delhi | 2022.11.08 | 2023.01.07 | Work in progress. |
Detail Report
Graph / Photo |
||||
392 | Renovation of Room No 135 Music Room First floor at UCMS GTB Hospital Shahdara Delhi | 2023.01.08 | 2023.02.07 | Work is in progress. |
Detail Report
Graph / Photo |
||||
393 | Repairing works and water proofing of DGHS Dispensary OLD Seemapuri New Delhi | 2023.01.08 | 2023.02.07 | Work in progress. |
Detail Report
Graph / Photo |
||||
394 | Renovation of Emergency Lab and Blood Storage room at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2023.01.01 | 2023.03.01 | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
||||
395 | Miscellaneous Civil works in Casualty including O.T. at Ground Floor and Room No. 205,206, 207, 208, 243 at Second Floor at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2023.01.01 | 2023.03.01 | Work is in progress. |
Detail Report
Graph / Photo |
||||
396 | Addition Alteration in Endoscopy First floor of Block 6 and other civil works in Rajiv Gandhi Super Specialty Hospital Tahirpur Delhi | 2023.01.08 | 2023.02.07 | Site is not available work to be started. |
Detail Report
Graph / Photo |
||||
397 | Renovation of Room No 125 and 122 of General Surgery at 1st floor OPD Block GTB Hospital Shahdara Delhi | 2023.01.19 | 2023.03.20 | Work is in progress |
Detail Report
Graph / Photo |
||||
398 | Expansion of Manifold room and Construction of toilet for the working staff in Manifold room and PSA Plant at Jag Pravesh Chandra hospital Shastri park, Delhi. | 2022.11.20 | 2023.01.09 | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
||||
399 | Waterproofing treatment on Roof of DOT Centre Dharamshala Building at GTB Hospital Shahdara Delhi | 2022.11.26 | 2023.01.25 | Work in progress. |
Detail Report
Graph / Photo |
||||
400 | Replacement of damaged G.I. Sheets & Covering IRC wire fabric all around Pharmacy for thermal insulation at GTB Hospital, Shahdara, Delhi | 2022.11.26 | 2023.01.25 | Work in progress. |
Detail Report
Graph / Photo |
||||
401 | Hiring of Inspection Vehicle along with Driver for LBS Hospital Project work in the office of A.E., HPSD (East)-III, PWD during 2022-23 | 2022.12.01 | 2023.09.30 | Work is in progress. |
Detail Report
Graph / Photo |
||||
402 | Hiring of Inspection Vehicle along with Driver for Chacha Nehru Bal Chikitsalaya (G+4) (596 beds) Project work in the office of Assistant Engineer Health Project Sub-Division (East)-IV, PWD, CNBC, Geeta Colony, Delhi-110031 during 2022-23 | 2022.11.25 | 2023.09.24 | Work is in progress. |
Detail Report
Graph / Photo |
||||
403 | Miscellaneous Civil works in Police Room Porta Cabin at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2022.11.27 | 2023.01.25 | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
||||
404 | Replacement of damaged false ceiling in Emergency OT & Providing and fixing roller blinds in R. No. 511 & 513 at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2022.11.27 | 2023.01.10 | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
S. No.क्र. सं. | Description | Details |
---|
S. No.क्र. सं. | Remarks | As On | Revised On |
---|
S. No.क्र. सं. | Upload Date | Description |
---|
S. No. | Date | Location | Remarks | Physical Progress (%) | View | ||
---|---|---|---|---|---|---|---|
Last | Upto | Photo | Doc |
S. No.क्र. सं. | Remarks | Date | Document |
---|
This is the Portal of Public Works Department, Govt. of NCT of Delhi, developed with an objective to enable a single window access to information and services being provided by the different wing of PWD Delhi. It is an initiative towards E-Governance Plan. यह लोक निर्माण विभाग, राष्ट्रीय राजधानी क्षेत्र (दिल्ली सरकार) का पोर्टल है जिसे इस उद्देश्य के साथ विकसित किया गया है जिससे लोक निर्माण विभाग, दिल्ली के विभिन्न स्कन्धों (विंग) द्वारा प्रदान की जा रही सूचनाओं तथा सेवाओं को एकल खिड़की के माध्यम से जाना जा सके | यह ई - गवर्नेंस योजना की दिशा में पहल है |
12th Floor, MSO Building,
I. P. Estate, New Delhi – 110002
Toll Free: 1800 11 00 93
© 2021 All Rights Reserved. Version 34.2.8 / 25-03-2023
This portal is designed, developed and maintained by M/s Calibre Websol Pvt. Ltd.
मैसर्स कैलिबर बेबसोल प्रा० लिमिटेड ने इस पोर्टल का विकास तथा अनुरक्षण / अभिकल्पन डिजाइन किया है
Session expire