S. No.क्र. सं. | Project Name | A/A & E/S |
Date of Start
Completion Expected |
Expenditure
Progress |
Remarks | View |
---|---|---|---|---|---|---|
1 | Construction of Hospital at Jwalapuri, New Delhi |
319.65 Cr. 06/12/2019 F.8(A)/(7)/DGHS/HC/2019/CD#112557057/Js3hfw-4017-4034 |
07/08/2020 13/08/2022 31/08/2024 |
141.96 Cr. (Mar'24) 0.00 (Mar'24) |
Structure RCC work & masonry work completed. Sanitary installation work completed, façade work, development work & electrical work is in progress. |
Detail Report
Graph / Photo |
2 | Construction of Hospital at Hastsal, New Delhi |
319.51 Cr. 06/12/2019 F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998 |
17/06/2021 16/06/2023 31/12/2024 |
49.00 Cr. (Mar'24) 0.00 (Mar'24) |
The brick work, AAC Block, Tile, Granite, Waterproofing, Sanitary & water supply work upto 5th floor is in progress. |
Detail Report
Graph / Photo |
3 | Providing Hiring of Inspection Vehicle for CE(Health |
319.51 Cr. 06/12/2019 F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998 |
-- -- -- |
19.84 Cr. (Aug'23) 0.00 (Aug'23) |
Detail Report
Graph / Photo |
|
4 | Providing Vehicle for Inspection. |
319.51 Cr. 06/12/2019 F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998 |
-- -- -- |
35.85 Cr. (Nov'23) 0.00 (Nov'23) |
Detail Report
Graph / Photo |
|
5 | Setting up of 1912 bedded semi permanent/temporary ICU Hospital at GTB. |
316.08 Cr. 08/09/2021 12/Misc/Covid-19/2021/CD-112647590 dated 08.09.2021 |
23/09/2021 22/02/2022 30/06/2024 |
0.00 Cr. (Jul'23) 82.00 % (Jul'23) |
Work stopped due to non availability of funds. |
Detail Report
Graph / Photo |
6 | Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). |
209.59 Cr. 27/11/2015 No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre) |
25/01/2019 24/05/2019 30/09/2020 |
2.16 Cr. (Oct'21) 0.00 (Oct'21) |
work in progress |
Detail Report
Graph / Photo |
7 | Construction of Mother & Child Block and Screening OPD Block at Dr. B.S.A. Hospital at Rohini, Sector-6, New Delhi |
194.91 Cr. 09/05/2018 2(11)/pWD/-upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45 dt. 25.06.2018 |
06/03/2020 05/09/2021 31/08/2023 |
6.18 Cr. (Feb'24) 0.00 (Feb'24) |
work in progress |
Detail Report
Graph / Photo |
8 | Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
194.91 Cr. 25/06/2018 2(11)/PWD-Upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45 |
04/03/2020 03/09/2021 31/08/2024 |
53.94 Cr. (Mar'24) 0.00 (Mar'24) |
work in progress |
Detail Report
Graph / Photo |
9 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi |
172.03 Cr. 22/06/2018 F.4/261/PWD/Health/2016/GGSH CD#112412717/2492-2509 dated 22.06.2018 |
18/10/2019 10/04/2021 31/03/2024 |
74.74 Cr. (Mar'24) 0.00 (Mar'24) |
False ceiling work in Block-A & final painting are under progress. |
Detail Report
Graph / Photo |
10 | C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
117.78 Cr. 22/06/2018 5/171/SGMH/TCSUB/CT/2016 CD# 112388502/2510-2527 |
04/09/2019 03/03/2021 31/05/2024 |
5.07 Cr. (Mar'24) 0.00 (Mar'24) |
work in progress. |
Detail Report
Graph / Photo |
11 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) |
101.63 Cr. |
18/07/2021 17/07/2022 31/10/2023 |
6.06 Cr. (Oct'22) 2.00 % (Oct'22) |
Work in progress. |
Detail Report
Graph / Photo |
12 | Construction of 3 Nos. Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A-6, Paschim Vihar, Vasant Kunj and Ladpur Village, New Delhi (Package - 7). SH : Civil & Electrical work. |
101.63 Cr. |
18/07/2021 17/07/2022 31/07/2023 |
60.26 Cr. (Mar'24) 0.00 (Mar'24) |
Work is in progress. |
Detail Report
Graph / Photo |
13 | Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. |
97.09 Cr. 08/02/2021 12/Misc/Covid-19/2021/CD-112647590 dated 08.09.2021 |
23/09/2021 22/02/2022 30/06/2024 |
0.00 Cr. (Jun'23) 88.00 % (Jun'23) |
Work stopped due to non availability of funds. |
Detail Report
Graph / Photo |
14 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. |
86.31 Cr. 23/03/2018 F. RTRMH-I/9/PWD(13)/2015-16/CD#000384488/1223-39 |
06/08/2019 29/10/2020 31/05/2024 |
37.21 Cr. (Mar'24) 0.00 (Mar'24) |
Finishing works, external façade and external development works are under progress. |
Detail Report
Graph / Photo |
15 | Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) |
83.39 Cr. 26/03/2018 F/10/Estate/Renovation of staff rooms/951 schools/DoE/945-50 |
-- -- -- |
|
Detail Report
Graph / Photo |
|
16 | Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). |
83.38 Cr. 26/03/2018 F.16/estate/renovation of staff rooms/951 Schools/DOE/945-50 dated 26.03.2018 for Rs. 83,38,36,800/- |
11/02/2019 10/06/2019 10/06/2019 |
5.40 Cr. (Jul'22) 0.00 (Jul'22) |
WORK IN PROGRESS |
Detail Report
Graph / Photo |
17 | Construction of New block Forensic Science Laboratory, Rohini, New Delhi |
59.06 Cr. 13/08/2019 3(148)/FSL/2016-17/1717-29 dt. 13.03.2019 |
06/03/2020 05/09/2021 30/09/2023 |
0.00 Cr. (Aug'23) 96.00 % (Aug'23) |
96% |
Detail Report
Graph / Photo |
18 | Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi. |
51.20 Cr. 09/08/2019 14012/21/2019-UTP |
-- -- -- |
|
Detail Report
Graph / Photo |
|
19 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. |
49.15 Cr. 14/09/2021 16/Estate/DoE/Const.160 Rooms/ Sunder Nagari/2091-95 |
17/10/2022 16/10/2023 30/04/2024 |
10.62 Cr. (Feb'24) 0.00 (Feb'24) |
Terrace slab work completed, Mumty column & slab casting work in progress. Brick masonary at2nd & 3rd floor in progress. plaster work in progress at 1st & 2nd floor and also wall putty work is progress at Ground floor and 1st floor. Wall tile & floor tile work at GF, FF, SF in progress. Granite work in front staircase & GF, FF corridor is progress. Plambing work in Toilet at GF, FF, SF in progress, Terrace parapit Brick work in progress. |
Detail Report
Graph / Photo |
20 | C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi |
45.51 Cr. 30/09/2021 F-16/Estate/DoE/Cont. of school bldg./925-30 |
12/02/2022 09/11/2022 31/03/2024 |
25.68 Cr. (Mar'24) 0.00 (Mar'24) |
nitially site was encroached by local people. Encroachment on the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Work of swimming pool and MP hall is in progress. |
Detail Report
Graph / Photo |
21 | Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work). |
38.45 Cr. 31/12/2019 F.16/Estate/Const. Pucca School Building/Sector-16/Dwarka/5769-71 |
18/07/2021 17/07/2022 30/06/2024 |
8.40 Cr. (Mar'24) 0.00 (Mar'24) |
Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress. |
Detail Report
Graph / Photo |
22 | C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. |
38.30 Cr. 27/09/2021 16/Estate/DoE/Const.132Rooms/SKV East Vinod Nagar/2327-31 |
27/03/2023 19/02/2024 30/04/2024 |
8.23 Cr. (Mar'24) 0.00 (Mar'24) |
Block structure work completed also brick work completed and flooring work is in progress along with wall clading work. Plaster work at 3rd floor is in progress. For back side block 3rd floor beam casting under progress. Brick work is in progress. Work affected due to GRAP-III implementation & progress slow. |
Detail Report
Graph / Photo |
23 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. |
30.40 Cr. 02/09/2019 F.16/Estate/C/o Pucca School Building/Sec-27/PWD/4803-4809 |
31/05/2020 30/05/2021 31/03/2024 |
27.88 Cr. (Mar'24) 0.00 (Mar'24) |
Work in progress |
Detail Report
Graph / Photo |
S. No.क्र. सं. | Description | Details |
---|
S. No.क्र. सं. | Remarks | As On | Revised On |
---|
S. No.क्र. सं. | Upload Date | Description |
---|
S. No. | Date | Location | Remarks | Physical Progress (%) | View | ||
---|---|---|---|---|---|---|---|
Last | Upto | Photo | Doc |
S. No.क्र. सं. | Remarks | Date | Document |
---|
This is the Portal of Public Works Department, Govt. of NCT of Delhi, developed with an objective to enable a single window access to information and services being provided by the different wing of PWD Delhi. It is an initiative towards E-Governance Plan. यह लोक निर्माण विभाग, राष्ट्रीय राजधानी क्षेत्र (दिल्ली सरकार) का पोर्टल है जिसे इस उद्देश्य के साथ विकसित किया गया है जिससे लोक निर्माण विभाग, दिल्ली के विभिन्न स्कन्धों (विंग) द्वारा प्रदान की जा रही सूचनाओं तथा सेवाओं को एकल खिड़की के माध्यम से जाना जा सके | यह ई - गवर्नेंस योजना की दिशा में पहल है |
12th Floor, MSO Building,
I. P. Estate, New Delhi – 110002
Toll Free: 1800 11 00 93
© 2021 All Rights Reserved. Version 35.2.7 / 28-03-2024
This portal is designed, developed and maintained by M/s Calibre Websol Pvt. Ltd.
मैसर्स कैलिबर बेबसोल प्रा० लिमिटेड ने इस पोर्टल का विकास तथा अनुरक्षण / अभिकल्पन डिजाइन किया है
Session expire