Road Work
Cost more than 30 Cr.
Road : Work in Progress
S. No.क्र. सं. Project Name A/A & E/S Date of Start
Completion
Expected
Expenditure
Progress
Remarks View
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 1260.63 Cr.
10/12/2014
23 (156)/CE/FPZ/F-I/PWD/2014-15/17446-57
18/04/2015
17/10/2017
31/12/2021
674.27 Cr. (Oct'21)
0.00 (Oct'21)
Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment, pylon, erection of segments is in progress Detail Report
Graph / Photo
2 Extension of Ashram Flyover to DND Flyover. 128.95 Cr.
16/12/2019
CD No. 057475804/dispart/17408-19
19/06/2020
18/06/2021
30/03/2022
34.14 Cr. (Nov'21)
0.00 (Nov'21)

The widening of Road and Piling work is in progress. The work in central portion could not be taken up due to Non-Receipt of Phase-II NOC from the Traffic Police. The widening of road in DND portion has been taken up. The transplantation of trees are in progress. Overall progress of the work is badly hampered due to sudden migration of Labour from the site due to second wave of COVID-19 and  subsquent imposing the ban on payment.

Detail Report
Graph / Photo
3 Bridges & its approaches over river Yamuna down stream of the existing bridge at Wazirabad (DTTDC) 113.10 Cr.
26/02/2010
.
20/03/2010
30/11/2017
31/05/2019
0.00 Cr. (Jun'17)
91.80 % (Jun'17)
The work is executed by DTTDC Detail Report
Graph / Photo
4 Construction of underpass along Mathura Road at Ashram Chowk New Delhi 77.92 Cr.
07/12/2018
Letter No.F.4/32/UDF/Underpass/PWD-III/2016/15739-50 dated 07.12.2018
05/07/2019
04/07/2020
31/12/2021
39.28 Cr. (Oct'21)
0.00 (Oct'21)

The work is in progress. The DTL cables are yet to be shifted despite the depositions of shifting charges on 10.11.2020. The shifting of DTL services is essential for completion of work. The progress is badly hampered due to running account of Bills to the contractor due to Financial measures.

Detail Report
Graph / Photo
5 Re-development of Chadini Chowk Road in between Lal Jain Mandir to Fateh Puri Mosque. 47.26 Cr.
02/09/2013
F.4(46)/2012-13/PWD-II/11667-11677
12/10/2013
11/04/2014
--

Detail Report
Graph / Photo
6 A/R & M/o Various Roads under PWD Sub Division M-1112 dg. 2014-15. (section II) (SH: Cleaning of storm water drains / sewer lines or dual type drains by mechanical method) 47.26 Cr.
02/09/2013
F.4(46)/2012-13/PWD-II/11667-11677
--
--
--

Detail Report
Graph / Photo
7 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 46.56 Cr.
18/12/2018
Sanction No. SS/PWD/14/2018-19 vide letter no. ENC/PWD/W/SSCP/16401-13 dated 18/12/2018 amounting to Rs. 46.56 Crore
--
--
--
0.07 Cr. (Jun'19)
0.00 (Jun'19)
Technical bid opened Detail Report
Graph / Photo
8 Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work 43.16 Cr.

Not required
30/05/2020
29/05/2022
29/05/2022
5.40 Cr. (Jun'21)
0.00 (Jun'21)
Work in Progress Detail Report
Graph / Photo
9 Strengthening & resurfacing of varioius roads under PWD M-Z M-1. (SH:: Stg. of Road No. 28, 29, 235, 237 under pWD CRMD M-112(N) by using plastic waste and Resurfacing of Service Road of ORR No. 26 fr 35.78 Cr.
23/06/2011
null
--
--
--

work completed Detail Report
Graph / Photo