Road taken by PWD (Year): | Road handed over to other Deptt: |
Length of Road (Km.): | 9.73 | No. of Lanes: | 6 | Lane Lentgh (Km.): | 58.66 |
Date of Last to Last Resurfacing(M/Y): | Right of Way: | 60.00 |
Main C.W. built thickness & specification of layer: |
Electrical |
No of Poles: | 1237 | No of Fittings: | 1985 | ||
Name of Coordinator 1: | M. Patra | Mobile No: | 9650880221 | Email ID: | spaceagem3@spaceagegroup.org |
Proposed Works |
General Remarks: | Ok |
Complaint |
Received: | 2 | Pending: | 2 | Close: | 0 |
Observation Details | |||
S. No. | Date | Inspection By | Observation |
---|---|---|---|
1 | 13/05/2016 | Jayesh Kumar, Pr. Chief Engineer | Growth of grass is pavered area.Gap in plantation in central verge is required to be filled. |