Widening and Strengthening of road from Najafgarh Dhansa Road to Jhuljhuli Morh via Ghummanhera Village Delhi. SH Balance work at Khaira Village and Ghummanhera School to Khaira Dabur Morh.
Office Name
South West Road Division 2
T.S. Amount
3011.20 Lacs
Dated
18/12/2014
Tender Amount
211.78 Lacs
Dated
04/05/2018
Progress Details
Date of Start: 04/05/2018
Date of Completion: 31/08/2018
Expected Date of Completion: 31/08/2018
Actual Completion Date: 27/03/2019
Contractor
M/s. Mahavir Prasad Gupta & Sons
Payment
Civil:  5.29 Lacs (Sep 2022)
% Progress : % (Sep 2022)
Present Position
Civil :  16/12/2019
WORK COMPLETED 27/03/2019
Bottlenecks
Civil :  16/12/2019
WORK COMPLETED 27/03/2019