Maint. and Elect. Consumption charges of street lighting on PWD EMD Roads under C and ND zone (SH- Desilting of Sump well of Shakti Nagar, Sawan Park, Roshanara Bagh i/c Repairing of Pump)
Office Name
History Sheet                 NIT Document
Tender Amount
7.78 Lacs
Dated
22/04/2018
Progress Details
Date of Start: 22/04/2018
Date of Completion: 21/01/2019
Expected Date of Completion: 18/02/2019
Actual Completion Date: 18/02/2019
Contractor
M/s Sehra Electric Works
  
Present Position

Electrical :  05/08/2019
WORK 100 % COMPLETED
Bottlenecks

Electrical :  05/08/2019
WORK 100 % COMPLETED