Providing and laying Stone Matrix Asphalt (SMA) on Masoodpur Flyover and Vasant Kunj Sector D-6 Chowk Under PWD Division South West Road-I, Under Sub Division-V
Office Name
South West Road Division 1
History Sheet                 NIT Document
T.S. Amount
29.16 Lacs
Dated
25/08/2018
Tender Amount
18.53 Lacs
Dated
05/11/2018
Progress Details
Date of Start: 05/11/2018
Date of Completion: 19/11/2018
Expected Date of Completion: 19/11/2018
Actual Completion Date: 19/11/2018
Contractor
M/s Sharma Construction Co.
  
Present Position
Civil :  15/11/2019
Work Completed
Bottlenecks
Civil :  15/11/2019
Work Completed