Desilting of Sump well of Shakti Nagar, Sawan Park, Roshanara Bagh i/c Repairing of Pump, all around the year
Office Name
History Sheet                 NIT Document
T.S. Amount
6.14 Lacs
Dated
06/07/2020
Tender Amount
4.98 Lacs
Dated
06/07/2020
Progress Details
Date of Start: 06/07/2020
Date of Completion: 05/07/2021
Expected Date of Completion: 05/07/2021
Actual Completion Date: 05/07/2021
Contractor
M/s Sehra Electric Works
Payment
Electrical :   6.13 Lacs (0   2014)
% Progress : % (0  2014)
  
Present Position

Electrical :  21/04/2022
Work in Progress
Bottlenecks

Electrical :  21/04/2022
Work in Progress