Water proofing/ coba work on terrace for 50% area in progress, wall tile and kota, Granite flooring in progress at 1st floor, 2nd floor & 3rd floor classroom, water supply & drainage work in toilet at ground floor, 1st floor, 2nd & 3rd floor in progress. Slow progress due to space scarcity at site. Terrace parapet brick masonary work for 20% area in progress, 2nd floor column casting for 20% area in progress & balance 10% area could not start due to space constraints.
Water proofing/ coba work on terrace for 50% area in progress, wall tile and kota, Granite flooring in progress at 1st floor, 2nd floor & 3rd floor classroom, water supply & drainage work in toilet at ground floor, 1st floor, 2nd & 3rd floor in progress. Slow progress due to space scarcity at site. Terrace parapet brick masonary work for 20% area in progress, 2nd floor column casting for 20% area in progress & balance 10% area could not start due to space constraints.