Block -A Structural work completed. Flooring work at all floor completed and corridor in progress. GRC tiles at front face completed and side portion is in progress. Water proofing at Terrace completed. Wall tiles, C.I. Pipes, water supply lines in toilet completed. Granite flooring in staircase steps completed. Dado work of staircase in progress. Block -B Granite work in staircase is completed. Finishing work is in progress. In B Block surrounding external development work in progress. GRC tiles at external wall in some portion is only pending. Toilet fitting & fixtures i/c W.C., wash basin, urinal, fixing work is in progress. In development work, front C.C. pavement work in front of building 80% completed and rest is in progress.
Block -A Structural work completed. Flooring work at all floor completed and corridor in progress. GRC tiles at front face completed and side portion is in progress. Water proofing at Terrace completed. Wall tiles, C.I. Pipes, water supply lines in toilet completed. Granite flooring in staircase steps completed. Dado work of staircase in progress. Block -B Granite work in staircase is completed. Finishing work is in progress. In B Block surrounding external development work in progress. GRC tiles at external wall in some portion is only pending. Toilet fitting & fixtures i/c W.C., wash basin, urinal, fixing work is in progress. In development work, front C.C. pavement work in front of building 80% completed and rest is in progress.