C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.)
Office Name
Education East & North East Maint Divn
History Sheet         Background Note         NIT Document
T.S. Amount
1730.39 Lacs
Dated
02/12/2021
Tender Amount
1090.67 Lacs
Dated
02/03/2022
Progress Details
Date of Start: 18/04/2022
Date of Completion: 13/03/2023
Expected Date of Completion: 31/03/2024
Actual Completion Date:
Contractor
Ms K. L. ARORA & SON
Payment
Civil:  157.75 Lacs (Mar 2024)
Present Position
Civil :  18/03/2024
Block -A Structural work completed. Flooring work at all floor completed and corridor in progress. GRC tiles at front face completed and side portion is in progress. Water proofing at Terrace completed. Wall tiles, C.I. Pipes, water supply lines in toilet completed. Granite flooring in staircase steps completed. Dado work of staircase in progress. Block -B Granite work in staircase is completed. Finishing work is in progress. In B Block surrounding external development work in progress. GRC tiles at external wall in some portion is only pending. Toilet fitting & fixtures i/c W.C., wash basin, urinal, fixing work is in progress. In development work, front C.C. pavement work in front of building 80% completed and rest is in progress.
Bottlenecks
Civil :  18/03/2024
Block -A Structural work completed. Flooring work at all floor completed and corridor in progress. GRC tiles at front face completed and side portion is in progress. Water proofing at Terrace completed. Wall tiles, C.I. Pipes, water supply lines in toilet completed. Granite flooring in staircase steps completed. Dado work of staircase in progress. Block -B Granite work in staircase is completed. Finishing work is in progress. In B Block surrounding external development work in progress. GRC tiles at external wall in some portion is only pending. Toilet fitting & fixtures i/c W.C., wash basin, urinal, fixing work is in progress. In development work, front C.C. pavement work in front of building 80% completed and rest is in progress.