Construction of Additional 13 nos Class rooms over existing G plus 1 SPS structure with Prefabricated fibre reinforced sandwich panel including electrical installations at BCP SKV, Babarpur, Delhi
Office Name
Education East & North East Maint Divn
History Sheet         Background Note         NIT Document
T.S. Amount
239.40 Lacs
Dated
05/01/2022
Tender Amount
183.58 Lacs
Dated
27/05/2022
Progress Details
Date of Start: 27/05/2022
Date of Completion: 24/08/2022
Expected Date of Completion: 28/02/2023
Actual Completion Date: 28/02/2023
Contractor
M/s Ram Krishan Yudhister Prakash
Payment
Civil:  427.46 Lacs (Mar 2024)
% Progress : % (Mar 2024)
Present Position
Civil :  06/05/2023
Sanction received from DoE vide letter No. F.16/Estate/DoE/40 Rooms 13/BCP, SKV Babarpur/328-337 dated: 01.02.2023 amouting to Rs. 1,62,98,948/- and work has completed on 28.02.2023
Bottlenecks
Civil :  06/05/2023