Running Operation and Routine Maintenance of Central AC Plant
Office Name
History Sheet                 NIT Document
Tender Amount
4.80 Lacs
Dated
07/05/2022
Progress Details
Date of Start: 07/05/2022
Date of Completion: 06/05/2023
Expected Date of Completion: 06/05/2023
Actual Completion Date:
Contractor
M/s Chopra Enterprises
Payment
Electrical :   5.99 Lacs (0   2014)
% Progress : % (0  2014)
  
Present Position

Electrical :  23/08/2023

100% Work Completed

Bottlenecks

Electrical :  23/08/2023

100% Work Completed