Work Completed on 24/03/2021
Sub Work (Agreements) Details | |||||||
---|---|---|---|---|---|---|---|
S.No. | Sub Work Name |
P.E. Amount
Tender Amount |
Date of Start
Date of Completion |
Expected Date of Completion
Actual Date of Completion |
Fincl. Exp. % Prog |
MB
Bill |
Remarks |
1 | Repair/Replacement of existing downcommer and wetriser system |
--
13.93 |
27/08/2022 26/10/2022 |
26/10/2022 -- |
13.36 Lacs (Mar 2023)
% (Mar 2023) |
--
-- |
100% Work Completed |
2 | Rewiring and Repairing of existing Light points, power points and Light fixtures, Fire Extinguishers, Drinking Water Pumps etc. as required |
--
9.47 |
26/03/2022 25/05/2022 |
25/05/2022 -- |
19.17 Lacs (Jun 2023)
% (Jun 2023) |
--
-- |
100% Work Completed |
3 | Providing Safety Cover for electrical panels / water coolers and other misc accessories |
--
6.15 |
20/08/2022 19/10/2022 |
19/10/2022 -- |
7.43 Lacs (Sep 2022)
% (Sep 2022) |
--
-- |
100% Work Completed |
4 | Repair/Replacement of existing downcommer and wetriser system |
--
-- |
--
-- |
-- |
--
-- |
--
-- |
-- |