EOR to Govt. Girls Sr Secondary School Ram Nagar Paharganj New Delhi SH Repair of boundary wall and other minor repairs works in school
Office Name
SRD Project Division 1
Progress Details
Date of Start: 03/03/2019
Date of Completion: 02/04/2019
Expected Date of Completion: 30/06/2019
Actual Completion Date:
Payment
Civil:  1.67 Lacs (Jun 2019)
% Progress :40.00 % (Jun 2019)
  
Present Position
Civil :  01/06/2019
Work in progress
Bottlenecks
Civil :  01/06/2019
Work in progress