EOR to SBV Naraina, New Delhi during 2017-18.(SH- Raising of existing boundary wall with concertina coil and P/L kota stone flooring).
Office Name
South West Building & Dwarka Court Maintenance Division
History Sheet                
T.S. Amount
3.73 Lacs
Dated
07/03/2019
Progress Details
Date of Start: 19/08/2018
Date of Completion: 16/11/2018
Expected Date of Completion: 16/11/2018
Actual Completion Date: 16/11/2018
Payment
Civil:  25.68 Lacs (Dec 2018)
% Progress :80.00 % (Dec 2018)
  
Present Position
Civil :  27/07/2023
completed