Public Works Department

Govt. of NCT of Delhi

लोक निर्माण विभाग, दिल्ली सरकार


 
RPVV Gandhi Nagar (School Id- 1003261)
Office Name
Education East & North East Maint Divn
Progress Details
Date of Start: 17/03/2019
Date of Completion: 11/12/2019
Expected Date of Completion: 31/08/2020
Actual Completion Date:
Payment
Civil:   Lacs (May 2020)
% Progress :32.00 % (May 2020)
Present Position
Civil :  27/05/2020
Labour available at site. Structure of 48 rooms complete. Material for flooring and finishing procured.