C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Libaspur, Delhi.
Office Name
Education North Maint Divn
T.S. Amount
3467.39 Lacs
Dated
02/01/2020
Progress Details
Date of Start: 30/05/2020
Date of Completion: 29/05/2021
Expected Date of Completion: 31/08/2022
Actual Completion Date:
Payment
Civil:   Lacs (Nov 2021)
% Progress :34.00 % (Nov 2021)
Present Position
Civil :  13/06/2022
Structure work completed. Brick work and plastering work completed in Part-A, B, C, D and in Part -E is in progress. Boundary wall work, granite work, tile works are in progress.