SKV MB Road Pushp Vihar, School ID 1923071
Office Name
Education South & South East Maint Divn
History Sheet     Abstract of Cost     Background Note        
Progress Details
Date of Start: 14/01/2019
Date of Completion: 10/10/2019
Expected Date of Completion: 28/02/2022
Actual Completion Date: 28/02/2022
Payment
Civil:  482.31 Lacs (Jan 2025)
% Progress : % (Jan 2025)
Present Position
Civil :  07/03/2022
Completed
Bottlenecks
Civil :  07/03/2022
Completed