Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING)
Office Name
Education East & North East Maint Divn
History Sheet     Abstract of Cost     Background Note        
Progress Details
Date of Start: 17/03/2019
Date of Completion: 11/12/2019
Expected Date of Completion: 12/10/2022
Actual Completion Date: 15/12/2022
Payment
Civil:   Lacs (Jan 2021)
% Progress :1.00 % (Jan 2021)
Present Position
Civil :  03/06/2023
Handed over to HOS.
Bottlenecks
Civil :  03/06/2023
Handed over to HOS.