Providing renovation repair of ramps railing, tactile tiles, signage etc. to make school building and environment barrier free and accessible. EOR ID 20
Office Name
North Building Division
T.S. Amount
26.00 Lacs
Dated
19/09/2019
Tender Amount
16.05 Lacs
Dated
01/11/2019
Progress Details
Date of Start: 01/11/2019
Date of Completion: 28/02/2020
Expected Date of Completion: 31/10/2020
Actual Completion Date:
Contractor
M/s Aayan Construction Co.
Payment
Civil:  9.00 Lacs (Nov 2020)
% Progress : % (Nov 2020)
  
Present Position
Civil :  14/12/2020
work is in progress 50%
Bottlenecks
Civil :  14/12/2020
work is in progress 50%